RecordingTranscript available10:32
Fridley Street Rehabilitation Project No. 2026-01
Fridley Public SchoolsSaturday, June 21, 2025
Watch on original sourceDocument Analysis
Analyze the transcript to extract topics, key quotes, people, and more — then generate focused stories for any topic.
Transcript
[0:00] Welcome to the introductory presentation
[0:02] for the city of Fidley's 2026 street
[0:04] rehabilitation project. This project is
[0:06] slated to take place in the Melody Manor
[0:08] neighborhood. This video will cover a
[0:10] host of topics including the project
[0:12] background and location, anticipated
[0:14] construction activities, tenative
[0:16] schedule, and project funding. Following
[0:19] the presentation, additional information
[0:21] will be provided on how to stay informed
[0:23] and provide feedback on the project.
[0:31] First, I'd like to get into the street
[0:33] resurfacing plan. The city of Frley has
[0:35] an ongoing obligation to the public to
[0:37] efficiently maintain its streets and
[0:39] provide a high level of service to its
[0:41] users. To accomplish this, city staff
[0:44] have developed a long-term pavement
[0:45] maintenance program informed by routine
[0:48] pavement evaluation to identify and
[0:50] schedule necessary improvements
[0:51] throughout the city. Other factors that
[0:53] influence the need for a project can
[0:55] include utility improvements, adjacent
[0:57] projects, excessive maintenance costs,
[0:59] and available funding. On this map, you
[1:02] can see a 10-year outlook for the city's
[1:04] pavement maintenance schedule. Note the
[1:06] streets within the Melody Manor
[1:07] neighborhood are currently scheduled for
[1:09] improvements in 2026 and 2027.
[1:12] Taking a closer look at the Melody Manor
[1:14] neighborhood. The highlighted streets
[1:16] shown in this map are being considered
[1:18] for improvements in either 2026 or 2027.
[1:22] Streets not highlighted in the map are
[1:23] not candidates for the upcoming street
[1:25] projects because they were completed
[1:26] back in 2007. The street segments that
[1:29] the city are evaluating for the street
[1:31] project include 76th Avenue, 4th Street,
[1:34] Fifth Street, 75th Avenue, 74th Avenue,
[1:39] Symphony Street, Madison Street, Lyric
[1:41] Lane, Tempo Terrace, Melody Drive,
[1:45] Concierto Curf, Memory Lane, Van Beern
[1:48] Street, Ael Street, and Baker Street.
[1:52] This project will address existing
[1:53] pavement deterioration, replayed water
[1:55] man and select areas and include other
[1:58] minor utility work. Their inclusion with
[2:00] the 2026 or 2027 street rehabilitation
[2:03] projects dependent upon the findings of
[2:05] the feasibility study. Since the project
[2:08] scope and the schedule is still being
[2:09] finalized, we encourage all residents
[2:11] within the neighborhood to stay informed
[2:12] and engaged.
[2:19] Up next, I will talk about the existing
[2:21] conditions within the neighborhood. In
[2:22] general, pavement conditions in this
[2:24] area are in decline with increased
[2:26] cracking and surface wear. For this
[2:28] reason, multiple streets have reached
[2:30] the point where minor maintenance is no
[2:31] longer effective. In addition, some
[2:34] utility infrastructure such as water man
[2:36] and storm sewer are nearing the end of
[2:37] their effective service life and will
[2:39] require replacement. Coordinated street
[2:42] rehabilitation and utility improvements
[2:44] offer the most costefficient and lasting
[2:47] solutions.
[2:53] Up next, I will talk about the project
[2:55] schedule. A typical street project has
[2:57] three different phases which starts with
[2:58] preliminary engineering, then proceeds
[3:00] to final design and bidding, and then
[3:02] concludes with construction and the
[3:04] final assessment hearing. This process
[3:06] generally takes approximately 18 to 24
[3:08] months. The first phase I'll discuss is
[3:10] the preliminary engineering for the
[3:12] project and this will take place between
[3:14] June and November of this year. This
[3:16] introductory video presentation is the
[3:18] first public engagement for the project.
[3:20] This video will give residents a basic
[3:22] understanding of the project. Then staff
[3:24] will host an in-person openhouse on June
[3:27] 24th. This openhouse is your first
[3:29] opportunity to meet the project team,
[3:31] ask questions, and provide feedback.
[3:33] Materials will also be available on our
[3:35] website for those unable to attend in
[3:36] person. Staff will begin the feasibility
[3:39] study for the project in the summer,
[3:40] refining the project area and scope.
[3:42] During this time, residents also have
[3:44] the opportunity to meet and discuss the
[3:46] project with staff while work is
[3:48] occurring on the feasibility report. In
[3:50] September of this year, staff will host
[3:52] the second openhouse to present the
[3:54] preliminary findings of the feasibility
[3:56] study and receive additional feedback
[3:58] from residents. Once finalized, the
[4:00] feasibility study will be formally
[4:01] presented to city council. In November
[4:04] of this year, a preliminary hearing on
[4:06] the proposed improvements will be held
[4:07] before the city council to consider
[4:09] ordering the proposed improvements as
[4:11] detailed in this feasibility study.
[4:13] During this time, properties subject to
[4:15] special assessment will have the
[4:16] opportunity to address council regarding
[4:18] the project. Please note that a mailed
[4:20] and published notice will be provided
[4:22] about the date of this hearing in
[4:23] advance. If council orders the
[4:25] improvements, staff will proceed to the
[4:27] final design and bidding phase for the
[4:30] project. The timeline is approximately
[4:31] from November to February for this
[4:34] phase. During this time, staff will
[4:36] prepare plans and specifications and
[4:38] begin coordination with private
[4:40] utilities and other agencies and solicit
[4:42] bids from contractors. Staff will also
[4:45] continue to work with residents
[4:46] throughout the final design. Publicly
[4:48] received bids will be considered for
[4:49] award by city council following the
[4:52] final design and bidding for the
[4:53] project. If approved and awarded by city
[4:56] council, the project will advance to the
[4:58] construction phase. Construction is
[5:00] anticipated to occur between May and
[5:01] September. Finally, in October of 2026,
[5:05] the city council will hold the final
[5:06] hearing on improvements. The purpose of
[5:08] the hearing is to finalize assessment
[5:09] amounts and hear those who wish to
[5:11] address the city council regarding the
[5:13] project. A mailed and published notice
[5:15] will be provided about the date of this
[5:16] hearing in advance. Next, I would like
[5:18] to discuss about construction activities
[5:20] and what to expect. Let's take a look at
[5:22] what typically can be expected during
[5:24] construction in more detail. Prior to
[5:26] the city's street project beginning, the
[5:28] city allows for private utility
[5:30] operators such as gas, electric, and
[5:32] communication utilities to replace
[5:34] and/or relocate existing utilities prior
[5:37] to the city's rehabilitation project.
[5:39] Once completed, the city begins its
[5:41] rehabilitation project. Pavement
[5:44] rehabilitation is typically accomplished
[5:45] through pavement reclamation. During
[5:48] this process, equipment grinds up the
[5:50] existing pavement and part of the
[5:51] underlying base to create a new stable
[5:53] foundation using the material already in
[5:55] place. City utility improvements
[5:58] typically occur following the pavement
[6:00] reclamation. This may include
[6:02] replacement of water mane, fire
[6:03] hydrants, storm, and sanitary sewer as
[6:06] identified in the feasibility report and
[6:08] final plans. Where water manes are
[6:11] replaced, residents will be connected to
[6:12] a temporary above ground water system
[6:15] for use during construction. You may see
[6:17] temporary hoses along boulevards or
[6:19] across driveways. Crews will work with
[6:22] each affected property to connect and
[6:24] maintain these services throughout
[6:26] construction. The project will also
[6:28] include spot replacement of broken or
[6:30] settled curb and gutter sections. Once
[6:32] installed, the new concrete will require
[6:34] a 7-day curing period during which
[6:36] vehicle traffic is prohibited. Driveways
[6:39] impacted by curb replacement will
[6:41] receive a notice and accommodation
[6:43] instructions in advance. The reclaimed
[6:45] base is then compacted and graded in
[6:47] tolerance for the new asphalt surface to
[6:50] be paved in two layers. After
[6:52] replacement of the new asphalt surface,
[6:54] the contractor will then saw and seal
[6:56] the pavement. While it may be
[6:58] counterintuitive, we cut fully new
[7:00] pavement sections to reduce cracking.
[7:03] Finally, boulevards disturbed by
[7:05] construction activities will be
[7:06] restored. Other things to expect during
[7:09] construction include existing utilities
[7:11] markings such as gas, electric,
[7:14] telecommunications for construction
[7:16] coordination. These are typically marked
[7:18] with paint and colored flags. There may
[7:20] be temporary disruptions to your
[7:21] driveway access during major work. On
[7:24] street parking restrictions while work
[7:25] is underway, temporary water shut offs
[7:28] and notifications prior to hydrant or
[7:29] valve replacement. And there will be
[7:31] weekly updates and notices for key
[7:32] project milestones. Construction
[7:34] activities generally occur Monday
[7:36] through Friday between 7 a.m. and 700
[7:39] p.m. We understand that construction can
[7:41] be inconvenient. Our goal is to maintain
[7:43] access and services as much as possible
[7:45] and to keep you informed.
[7:52] Another piece to the street project is
[7:54] the project funding and special
[7:56] assessments. Pavement rehabilitation
[7:58] projects are typically funded through a
[8:00] combination of sources, including state
[8:02] aid funding, city utility funds, and
[8:04] special assessments to benefiting
[8:06] properties. The city has a long-standing
[8:08] special assessment policy that
[8:10] distributes costs related to roadway
[8:12] improvements based upon property type
[8:14] and other factors. Please note that
[8:16] special assessments are composed solely
[8:18] of costs related to the pavement
[8:19] improvements with all utility
[8:21] improvements costs not assessed to
[8:23] benefiting properties. Properties are
[8:25] categorized into two groups for
[8:27] assessment purposes. The first being
[8:29] lowdensity residential properties up to
[8:31] four dwelling units are assessed at a
[8:34] proportional rate on a perlot basis. The
[8:36] second being non- lowdensity residential
[8:38] properties such as commercial and
[8:40] apartment buildings are assessed based
[8:42] on the front footage adjacent to the
[8:43] improved street. Preliminary estimates
[8:45] of special assessment will be determined
[8:47] during the feasibility study for the
[8:49] project. This estimate will be provided
[8:51] in a mailed notice prior to the
[8:52] preliminary hearing on improvement.
[8:55] Special assessment amounts will be
[8:56] finalized using actual construction
[8:58] costs following project completion. The
[9:01] final assessment amount will be provided
[9:03] in the mailed notice before the final
[9:04] hearings on improvements. The city
[9:06] offers three methods of payment for
[9:08] special assessments. These include
[9:10] option one, a onetime payment with a
[9:12] minimum of $100 within 30 days of the
[9:15] final assessment hearing. Option two,
[9:17] annual installment applied to property
[9:19] taxes and paid over a 10-year term with
[9:21] interest. The remaining balance can be
[9:23] paid in full with acred interest at any
[9:25] time during the term. And option three
[9:27] is individuals with qualifying age,
[9:28] disability, and income may be eligible
[9:30] for assessment deferment until future
[9:32] sale of property. Please note that
[9:34] interest occurs until property is sold.
[9:36] Options one and two may be combined to
[9:38] structure payment according to
[9:39] individuals needs.
[9:46] Thank you for taking the time to learn
[9:48] about the proposed project in your area.
[9:49] These improvements will enhance the
[9:51] safety, reliability, and appearance of
[9:53] our neighborhood streets for years to
[9:55] come. To stay up to date, the project
[9:57] website will be updated regularly
[9:58] throughout design and construction with
[10:00] maps, schedule changes, and general
[10:02] updates. You can visit the project page
[10:04] on the city's website, or you can scan
[10:06] the QR code shown. We recommend
[10:09] subscribing to email notifications for
[10:11] timely information. You can subscribe by
[10:13] emailing us at the email below. We also
[10:16] invite you to share your input with city
[10:17] staff by taking a brief survey available
[10:20] on the project web page. Your feedback
[10:22] will help inform the design of the
[10:23] overall project. We look forward to
[10:25] working with you as this project moves
[10:27] forward. If you have any questions,
[10:29] don't hesitate to reach