Chanhassen — Transcript
Friday, April 25, 2025Analysis complete
1 Topic in This Document
Chanhassen Pavement Management Plan and Full Depth Reclamation
▸Full Extraction
“Full depth reclamation or FDR involves grinding up a road's existing asphalt and mixing it with the top part of the aggregate base to create a new base layer.”
— Unknown [0:23]Pavement Management Plan: Full Depth Reclamation (FDR) Technique Explanation
“We use this construction technique when the existing pavement shows signs of significant deterioration and generally scores below a 60 on the overall condition index a zero to 100 point scale we use to rate a road's health.”
— Unknown [0:41]Pavement Management Plan: Full Depth Reclamation (FDR) Technique Explanation
“Although this method is more expensive and extensive than the mill and overlay technique it avoids the more costly total reconstruction which involves various additional improvements.”
— Unknown [1:06]Pavement Management Plan: Full Depth Reclamation (FDR) Technique Explanation