reconstruction is when the entire road is completely removed and replaced

Unknown [0:20]Overview of Pavement Management Plan: Road Reconstruction Method

We use this construction technique when the existing pavement shows significant signs of deterioration and generally scores below 40 on the overall condition index

Unknown [0:46]Overview of Pavement Management Plan: Road Reconstruction Method

reconstruction is necessary when a road reaches the end of its life cycle this type of repair represents a significant investment in the future of Chanhasson's transportation network