[0:00] chanhassen is home to approximately 119
[0:03] miles of city-owned streets these
[0:05] streets serve as a major form of
[0:07] transportation for our 26,000 residents
[0:10] 500 businesses and hundreds of daily
[0:16] visitors our roads see a lot throughout
[0:18] the year and they especially take a
[0:20] beating in the winter when plows are
[0:21] scraping and salting them in order to
[0:23] ensure that our roads are in good
[0:25] working condition the city's engineering
[0:27] department utilizes a pavement
[0:28] management plan what goes into this plan
[0:31] how do we decide what roads are repaired
[0:34] and how do we decide what kind of work
[0:35] each road needs to start the city is
[0:38] broken up into three geographical areas
[0:41] each area is field reviewed every 3
[0:43] years one of the reviewing techniques
[0:45] our engineers use to evaluate road
[0:47] conditions is the overall condition
[0:48] index or OCI the OCI is a series of
[0:51] ratings that help determine what sorts
[0:53] of repairs each road needs like with
[0:56] school grades or bowling the higher the
[0:57] score the
[0:59] better generally if your road scores 90
[1:02] or higher it's in excellent shape and
[1:04] just needs some minor maintenance and
[1:05] maybe some monitoring if your score is
[1:07] between 80 to 90 your road's in really
[1:09] good condition just might need some
[1:11] minor maintenance like some cracks
[1:13] sealed or maybe some potholes filled 70
[1:15] to 80 means we might use a Milland
[1:17] overlay rehabilitation method and 60 to
[1:20] 70 means we definitely will 50 to 60 is
[1:23] a decision between mill and overlay and
[1:25] a full depth reclamation 40 to 50 is a
[1:28] definite full depth reclamation and
[1:30] anything 40 or lower is a full
[1:32] reconstruction now although this is how
[1:34] we use the rating system generally to
[1:36] address road rehabilitation there are
[1:38] other engineering factors that may play
[1:40] a role in the selection process so what
[1:42] does this all mean well a basic
[1:45] maintenance technique is seal coating or
[1:47] chip sealing this involves applying a
[1:49] thin layer of oil and rock to the road
[1:51] surface to prevent moisture penetration
[1:53] and UV damage and extend the lifespan of
[1:56] the road by approximately 7 years mill
[1:58] and overlay takes us a little bit deeper
[2:01] this involves removing or milling the
[2:03] top layer of existing asphalt and
[2:05] replacing or overlaying it with new
[2:08] asphalt this process restores the
[2:11] surface improves the ride quality and
[2:13] extends the road's life by approximately
[2:15] 15 years
[2:17] full depth reclamation or FDR involves
[2:20] pulverizing the existing asphalt as well
[2:23] as some of the gravel layer beneath it
[2:25] that debris is then recycled and
[2:27] compacted to create a new durable base
[2:30] for the road lace some new asphalt and
[2:32] pow a new road this recycling technique
[2:36] eliminates the need for costly removal
[2:38] and disposal of old materials while
[2:40] improving and strengthening the
[2:42] longevity of the road reconstruction
[2:45] it's kind of a big deal it's a complete
[2:47] overhaul and upgrade of a road including
[2:50] removing and replacing existing pavement
[2:52] subbase and drainage systems it can also
[2:55] include widening or realigning portions
[2:58] of the road and improving it if there
[2:59] are issues like increased traffic or
[3:02] safety concerns that need addressing so
[3:04] yeah it's kind of a big deal city staff
[3:07] annually analyze these condition ratings
[3:09] and proceed in a logical manner within
[3:11] the provided funding the goal of the
[3:13] pavement management plan is to do the
[3:15] right maintenance at the right time stay
[3:18] tuned for more about our pavement
[3:19] management plan including information
[3:21] about the planning and design process a
[3:23] deeper dive into construction and a more
[3:25] formal look at the three more intensive
[3:27] road repair techniques: Milland overlay
[3:30] FDR and reconstruction for other
[3:32] information about the projects happening
[3:34] around Chanhassen visit
[3:35] chanhassenm.gov/rojects