Pavement Management Plan - Episode 5: Reclamation

Chanhassen City CouncilFriday, April 25, 2025
Watch on original source

Chanhassen explains cost-effective road repair technique for deteriorating streets

Full Document Analysis

Notable Quotes (3)

Full depth reclamation or FDR involves grinding up a road's existing asphalt and mixing it with the top part of the aggregate base to create a new base layer.

Pavement Management Plan: Full Depth Reclamation (FDR) Technique Explanation

We use this construction technique when the existing pavement shows signs of significant deterioration and generally scores below a 60 on the overall condition index a zero to 100 point scale we use to rate a road's health.

Pavement Management Plan: Full Depth Reclamation (FDR) Technique Explanation

Although this method is more expensive and extensive than the mill and overlay technique it avoids the more costly total reconstruction which involves various additional improvements.

Pavement Management Plan: Full Depth Reclamation (FDR) Technique Explanation

Ordinances & Resolutions (4)

Pavement Management PlanPlan

City's strategic plan for managing street upkeep, prioritizing road work, and scheduling construction and repairs.

Overall Condition Index (OCI)Other

A 0 to 100-point scale used to rate a road's health and determine eligibility for specific repair techniques like full depth reclamation.

Pavement Management SeriesOther

A series of informational videos providing more detail on road repair selection processes and techniques.

chanhassenm.gov/projectsOther

Official city website providing information about ongoing projects around Chanhassen.