July 13, 2021 Park Commission Meeting

Tuesday, July 13, 2021

Mayor Rising Community Festival post-event update

Blue Jay Park fence and safety infrastructure

Park Pavilion development concepts and feasibility

Public Workshed repurposing assessment

2021 long-term capital improvement project priorities

Park signage installation status

Splash pad design and development updates

Areas of Interest (5)

  • Rising maintenance costs and design scope creep in municipal park pavilion projects.
  • Concerns over safety and accessibility at Blue Jay Park parking and recreation areas.
  • Strategic planning issues regarding the necessity of a kitchen facility vs. simple park shelters.
  • City staff recommendation to pause new projects to focus on budget and existing completion.
  • Challenges in coordinating community festival logistics and public engagement booth visibility.

Votes (2)

Approve the agenda

PassedAll in favor

Moved by Unspecified · Seconded by Unspecified

Approve June 8th minutes

PassedAll in favor

Moved by Unspecified · Seconded by Unspecified

Notable Quotes (3)

I think next time having like a large sign and then people can kind of come to us and know who we are instead of us having to

— Maggie
Mayor Rising Community FestivalOn improving future festival presence.

I mean if we can find a case where yes we are I mean then it would be something to consider but I just kind of kyle kind of bummed me

— Mike
Pavilion DiscussionRegarding the impossibility of repurposing the workshed.

I would say at that time that would make sense to maybe discuss investing in that ahead of time but it is feasible

— Maggie
Infrastructure PlanningRegarding pre-installing sewer lines for future park needs.

People (3)

MaggiePark Staff/Organizer

Coordinates park commission meetings, festival planning, and project management.

2 quotes

“it was kind of a little chilly in the morning too so maybe the hydro blaster not working out was a good good thing”

Reflecting on the Community Festival event.

“it's not something we've are the other ones are reservable”

Explaining the lack of formal reservation systems for current pavilions.

MikePark Board Member

Participates in discussions regarding pavilion designs, budgets, and park maintenance.

1 quote

“I like your design I like your concept I like your idea I just I think we're going to end up in the same place”

On the feasibility of repurposing the public workshed.

KyleStaff/Engineer

Evaluated site plans, fencing, and structural feasibility of buildings.

Places Mentioned

Blue Jay ParkDiscovery ParkWestridge ParkThird StreetWater Treatment Facility

Events & Meetings (6)

  • June 8th (Previous Meeting)
  • 2016 (Pavilion design initial phase)
  • 2018 (Pavilion bidding)
  • July (Mid/End - Signage installation)
  • August (Splash pad concept presentation)
  • September (Proposed Joint Council/Commission meeting)
View Source
July 13, 2021 Park Commission Meeting - Mayer Recorder