Joint Planning Commission and Council Work Session - June 4, 2024
Saturday, March 15, 2025
Introduction of Tract development team
Data center project overview and rationale
Infrastructure requirements for data centers
Community impact concerns (noise, traffic, water, power)
Proposed development sustainability and economic benefits
PUD overlay process and zoning steps
Votes (1)
Approve agenda
PassedVoice vote
Moved by Steve · Seconded by Hol
Notable Quotes (3)
our goal is to acquire larger tracks of land where we can master plan and identify the framework for the development
Master planningExplaining the firm's development strategy.
we essentially then sell shovel ready sites to the hyperscalers
Business modelDescribing the business model of selling to major tech clients.
the energy that will be utilized by the data centers will not impact the Grid in the broader community
Power infrastructureAddressing concerns regarding power reliability.
People (6)
DeannaCity Staff
Coordinates the city council/planning commission joint work session.
Kristen DeanDirector of Entitlements
Lead presenter for the development team and project proposal.
Kevin ArrowTract Team Member
Attending the presentation.
Philip SandinoTract Team Member
Engages with local power companies.
Alan CatullCivil Engineer
Managing civil engineering and design.
Ashley PayConsultant
Managing the AUAR process.
Places Mentioned
Farmington, MinnesotaLoudoun County, VirginiaHanover County, VirginiaNevadaUtah
Events & Meetings (2)
- June 4, 2024: Farmington City Council special work session
- May 14, 2024: Prior Planning Commission hearing