Planning Commission Meeting - July 8, 2025
Tuesday, July 8, 2025
Minutes approval for June 10, 2025 meeting
Public Hearing: Conditional Use Permit for community solar garden (Dimension Energy)
Project overview and site constraints analysis
Environmental, utility, and decommissioning plan discussion
Votes (1)
Approval of the minutes from June 10, 2025
ApprovedVoice vote
Moved by Unspecified · Seconded by Unspecified
Notable Quotes (2)
If the investment tax credit goes away tomorrow, we'll still go ahead and build this project.
Project FinancialsQ&A session regarding federal policy changes.
The decommissioning plan is signed and executed with the city prior to release of the building permit.
DecommissioningSummary of requirements for the permit.
People (3)
JaredStaff/Planner
Outlined project site details, zoning, and required conditions of approval.
Daniel SorzanoDirector of Development, Midwest
Discussing company history and project feasibility.
Alex FernoEnvironmental Planner
Discussing environmental due diligence and wetland protections.
Places Mentioned
South of County Road 50, west side of Flagstaff AvenueFarmington, MinnesotaLakeville, Minnesota
Events & Meetings (2)
- July 8, 2025 Regular Meeting of the Planning Commission
- June 10, 2025 Regular Meeting (Minutes approval)
Ordinances & Resolutions (1)
P143400 87010
Conditional use permit request for a 4.95 megawatt community solar garden on 18.54 acres.