Hastings Public Schools — Transcript

Wednesday, August 5, 2026

Highway 61 Project Overview and Status

Design Features and Safety Enhancements

Construction Staging and Traffic Management

City Utility Replacement and Trunk Sewer Line Project

Project Funding and Future Steps

Notable Quotes (19)

I'm wearing three hats. I'm not only the project manager, I'm the area engineer for Dakota County, and I'm also the project coordinator for the construction side or the CMGC side.

Highway 61 Project Introduction and Overview

No, Robert, you can't build it that way. You can't do it that way. We can build it this way.

Highway 61 Project Introduction and Overview

Our project purpose, our purpose and need to help the people and goods travel safely and efficiently along 61 using all types of transportation while keeping the road in good condition and supporting connections between the communities.

Highway 61 Project Introduction and Overview

Construction we're seeing now as we've got the contractor on board that this is going to be a 2-year project. We know for a fact. We tried to see if we could do it in 1 and 1/2 years. It's just not going to happen. This is a 2-year project.

Highway 61 Project Introduction and Overview

So, the roundabouts two full-size roundabouts are going to be added at 61.

Design Features and Aesthetic Enhancements

Keep moving. Get out of that roundabout. Get out of their way.

Design Features and Aesthetic Enhancements

We are going to make that median mountable. So, it's going to be a mountable median. So, that 5% of time or left less that you do have to make that movement, you'll the fire department will have a light there with a with a flashing beacon and they can mount it.

Design Features and Aesthetic Enhancements

I I just hope that you will be thinking about salt-resistant vegetation.

Design Features and Aesthetic Enhancements

That retaining wall, as you guys know, is at about a 35° angle and it's failing. The old tunnel that's under the road is failing.

Design Features and Aesthetic Enhancements

We know this is going to be um really hard on a community for 2 years.

Construction Staging, Traffic Management, and Utilities

The reason I'm asking is the block off of a million to the east and 7th and this this whole thing is causing me to think about moving.

Construction Staging, Traffic Management, and Utilities

I've seen other businesses and land owners benefit from a road project like this. I've seen Ford dealerships move to a mall and sell their cars out of the mall parking lot while we did the construction and boom through the whole time.

Construction Staging, Traffic Management, and Utilities

A lot of times when we have an issue with with 61, uh our comment in the last decade has been "We'll fix it when the trunk highway project comes through.

Construction Staging, Traffic Management, and Utilities

We need to get a right of entry signed by you. So, for us to have a contractor go our contractor to go in onto the property to do their work to replace those services up to the property line, they need to get access to do that.

Construction Staging, Traffic Management, and Utilities

I do not want to build this project and then have someone say, "Well, I didn't know about this.

Project Funding and Future Steps

We're still under funded. We're less than half funded. We're still working hard to get it this funded...

Project Funding and Future Steps

But this was a project of merit, which is a like it was rated very high nationally, but did not actually receive the money.

Project Funding and Future Steps

We're trying to make this a legacy project for Hastings. We're trying to give you guys the Cadillac project here if we can. We can. If not, we're going to go back to the Volkswagen Beetle and do it.

Project Funding and Future Steps

Uniqueness of a CMGC project. We have the contractor on board. I can let a small little project like the crossovers and the retaining wall at the bridge if we agree to numbers right now and let a small portion of this project with the contractor that we have on board now in '27.

Project Funding and Future Steps

Ordinances & Resolutions (13)

30% plansPlan

Current design phase of the project, available for review.

60% plansPlan

Next design milestone, expected around November, with another public meeting.

Final plansPlan

Plans that will be 'tweaked' but are largely based on the done layout.

Vision studyOther

Comprehensive analysis informing the project's purpose and need, including traffic data.

LayoutPlan

The finalized geometric layout, signed by the central office geometric design unit.

Build grantOther

A $20 million government grant applied for but not received.

Infra grantOther

A grant currently being applied for to help close the funding gap.

Cooperative construction agreementOther

Agreement with Met Council for funding the trunk sewer line relocation.

Municipal consent documentsOther

Draft documents to be provided to the city council next month for public and municipal consent.

Comp plan analysisOther

A study underway to assess the impact of the trunk sewer line relocation on Hastings.

fact sheetOther

Information sheet available to the public, containing contact details.

right of entryPermit

Document needed from property owners to allow contractors onto private property for utility work.

ADA fundingOther

Additional funds recently secured for Americans with Disabilities Act compliance.

View Source