Hastings Public Schools — Transcript

Monday, August 17, 2026

Story

Hastings pauses data center permits, approves water line project

Interim Moratorium Ordinance for Data Centers

Water Service Line Replacement Project Phase One Contract Award

Authorization for Local Council in Environmental Litigation

Initiation of Environmental Litigation

Votes (4)

Interim Moratorium Ordinance Related to Data Centers

Motion prevails

Dissent: None

Moved by Council member Hauschild [Approx. 0m 18s] · Seconded by Council member Leifeldt [Approx. 0m 18s]

Community Development Director John Hinsman introduced the second reading and adoption of an interim moratorium ordinance on data centers, citing the lack of a definition in current city code and the need for time to research impacts and develop regulations. A public member, John Larson, expressed concerns about data centers' impact on water quality. Council members, including Leifeldt and Hauschild, supported the moratorium as a proactive measure to prevent potential issues such as excessive water usage and harmful pollutants, referencing experiences in other communities.

Contract Award for Water Service Line Replacement Project Phase One

Motion prevails

Dissent: None

Moved by Council member Pemble [Approx. 0m 21s] · Seconded by Council member Lawrence [Approx. 0m 21s]

Justin Babcock, WSB project manager, presented the recommendation to award the contract for the first phase of the water service line replacement program. Fitzgerald Excavating submitted the lowest qualified bid at $718,775, and was noted for their extensive experience in similar utility and residential reconstruction projects. The project costs are aligned with the city's budget, which includes a $1 million grant from the Minnesota Public Facilities Authority.

Authorization to Engage Local Council for Environmental Litigation

Motion prevails

Dissent: None

Moved by Council member Pemble [Approx. 0m 23s] · Seconded by Council member Beck [Approx. 0m 23s]

City Administrator Dan Washa explained that the city's legal services contract with Pawa Law Group for environmental litigation anticipates engaging local counsel. He recommended authorizing Pawa Law Group to work with Lockridge Grindal Nauen PLLP, emphasizing that local counsel's fees would be covered from Pawa Law Group's share of recovery, thereby incurring no additional cost to the city.

Initiation of Environmental Litigation

Motion prevails

Dissent: None

Moved by Council member Leifeldt [Approx. 0m 24s] · Seconded by Council member Verchota [Approx. 0m 24s]

City Administrator Dan Washa, following a prior discussion with Pawa Law Group on legal strategy, recommended that the City Council authorize Pawa Law Group to proceed with initiating environmental litigation. This marked a formal step by the city to pursue legal action regarding environmental matters.

Notable Quotes (6)

What the interim moratorium ordinance would do is it would create a pause in the acceptance, deliberation, or issuance of any uh permits related to data centers over the next year or so. The purpose behind that is when we take a look at our code as it sits right now, we do not define data centers.

— Community Development Director John Hinsman [Approx. 0m 10s]
Interim Moratorium Ordinance Related to Data Centers

From what I see, you know, nobody really even knows what they are, what they do, and and except uh, they ruin the water in every community that they're in and they turn it brown. And I just think that there needs to be more looking into this before anything's approved or any data centers come to Hastings, which is such a beautiful place, and not get it destroyed.

— John Larson [Approx. 0m 12s]
Interim Moratorium Ordinance Related to Data Centers

Data centers can be really poor fit for our small communities um as they demand excessive local resources. Um they can be problematic facilities um that typically rely on evaporating cooling, which can drain our municipal water supplies, and utilize backup diesel generators that emit harmful pollutants.

— Council member Hauschild [Approx. 0m 17s]
Interim Moratorium Ordinance Related to Data Centers

The low bid was Fitzgerald Excavating with a base bid of $718,775. Fitzgerald Excavating has extensive experience in residential reconstruction projects and utility projects. And in initial discussions with Fitzgerald Excavating, they plan on using the pull method to complete water service line replacements and then complete restoration activities in kind as they go site by site completing the homes we've selected um for this project.

— Justin Babcock [Approx. 0m 20s]
Contract Award for Water Service Line Replacement Project Phase One

Pawa Law Group uh, proposes working with uh, Lockridge Grindal Nauen PLLP uh, as local council. Uh, would note that local council's fees would be paid uh, from Pawa Law Group's share of recovery uh, if if there is.

— City Administrator Dan Washa [Approx. 0m 22s]
Authorization to Engage Local Council for Environmental Litigation

City Council met with uh, Pawa Law Group uh, couple weeks ago on the 3rd to discuss legal strategy regarding potential environmental litigation. Uh, my recommendation is to authorize Pawa Law Group to initiate environmental litigation at this time.

— City Administrator Dan Washa [Approx. 0m 24s]
Initiation of Environmental Litigation

Ordinances & Resolutions (6)

Proclamation for International Overdose and Fentanyl Poisoning Awareness MonthOther

Official declaration by the City of Hastings recognizing August for awareness of the opioid and fentanyl crisis.

Interim Moratorium Ordinance related to Data CentersOrdinance

Ordinance enacted to temporarily halt the acceptance and processing of permits for data centers.

codeOther

The City's regulatory framework, specifically identified as lacking definitions for data centers.

2026 intended use planPlan

A plan that reserves $1 million for the City of Hastings as part of a state grant for water service line replacement.

Water Service Line Replacement Program Phase OnePlan

The initial phase of a city project to replace water service lines.

legal services contractOther

An existing contract with Pawa Law Group for environmental litigation, anticipating the engagement of local council.

View Source
Hastings Public Schools - Hastings Recorder