Inver Grove Heights — Transcript
4 Topics in This Document
Delaney Court and Delaney Circle Improvements Project Overview
Project Status, Schedule, and Assessments
Construction Process and Resident Considerations
Resident Q&A: Mailboxes, Schedule, and Driveway Aprons
▸Full Extraction
“this is for street improvements for delaney circle and delaney court the scope of the improvements it's considered a partial reconstruction of both streets it includes some a few roadway and driveway culvert replacements and some minor ditch grading improvements for storm water drainage”
“the city received bids on april 27th and then city council awarded the project mcnamara contracting was the low bidder that occurred on may 10th the next step following tonight's meeting is the tentative construction start is scheduled for the week of june 14th with a project completion expected in early august”
“at council direction and based on some feedback from from residents we're moving the assessment hearing to after construction and the assessments will be the final assessments will be proposed based on actual construction costs”
“residential driveway access will generally be maintained at all times it will be restricted when there's equipment operating directly in front of your driveway um but that'll be a fairly brief period of time”
“they the contract will remove them and they will also reinstall them during during while the road work is occurring the contract is required to get get um direction from the postmaster what what we expect is there will likely be a shared mailbox cluster probably up at invergrove trail”
“at this point we're we're matching the roadway profile so we're not expecting to replace any driveways all of them are going to need some reasonable saw cut line... we're very much minimizing driveway impacts”
“well it's um residents supported all the neighborhoods request in the whole neighborhood or you know most of the neighborhood signed the petition for it and this is a no it was long overdue it needed to be done”