South St. Paul Public Schools — Transcript

Monday, January 26, 2026

Student Programs and Initiatives

Middle School Curriculum Updates (Science & English Language Arts)

Superintendent and Board Evaluation Process

District Financial Planning and Budget Process

Community Support and Social Issues

Facility Needs and Funding for School Buildings

Votes (6)

Resolution Authorizing Issuance of School Building Bonds and Renewing Capital Projects Levy Authorization and Calling an Election

6-0 Approved

Dissent: None

Moved by Unknown [0:45:50] · Seconded by Unknown [0:45:55]

The board discussed a recommendation to call a special election on May 12, 2026, for two ballot questions. The first question involves a bond referendum to address critical facility needs such as aging mechanical, plumbing, and electrical systems, roofing, exterior repairs, safety improvements, and ADA accessibility. This investment, the first significant one since 2013, is projected to cost less than $12 per month for a $300,000 home. The second question is a tax-neutral renewal of the existing capital projects levy, which funds safety, security, cyber security, and technology needs (e.g., security cameras, phone systems, tech infrastructure). The urgency was emphasized due to the 2022 facilities study identifying $150 million in deferred maintenance, and the escalating costs of construction inflation (5% annually). Board members highlighted the importance of being good stewards of existing facilities and leveraging the May election date to allow construction to begin in summer.

Approval of the June 30, 2025 Year End Audit

6-0 Approved

Dissent: None

Moved by Unknown [1:07:30] · Seconded by Unknown [1:07:35]

The Finance Director presented the key findings of the annual audit performed by LB Carson. The district received an unmodified audit opinion, the highest possible, confirming compliance and transparent accounting. However, two internal control weaknesses were identified: segregation of duties within the finance department and monthly reconciliation processes. The team is actively working on corrective actions. The audit also noted a ~20% decline in Adjusted ADMs from 2016-2025, but the last two years showed promising stabilization. The district's total fund balance increased to $15.3 million, attributed to conservative budgeting, a past referendum, and good stewardship, providing approximately 11 weeks of operational funds.

Resolution Directing Administration to Make Recommendations for Adjustments in Programs and/or Positions

6-0 Approved

Dissent: None

Moved by Unknown [1:08:20] · Seconded by Unknown [1:08:25]

This annual resolution grants the administration the flexibility to recommend adjustments to programs and staffing as district needs evolve. The Finance Director clarified that this resolution does not presume reductions but ensures the district is prepared to respond thoughtfully and responsibly to changing circumstances. It marks an initial step in the adopted budget process for the upcoming year.

Reject Packer Activity Center (PAC) Ventilation Bid

6-0 Approved

Dissent: None

Moved by Unknown [1:10:00] · Seconded by Unknown [1:10:05]

The Director of Buildings and Grounds reported that only one bid was received for the ventilation improvements at the Packer Activity Center, submitted by CM Construction. This bid significantly exceeded the allocated budget for the project. Administration recommended rejecting the bid to allow for refinement of the project scope with W Architects and re-bidding the project to obtain more competitive pricing. The low bid response was attributed to timing, as the bid period coincided with the holidays.

Approve Grow Your Own Candidate Agreements

6-0 Approved

Dissent: None

Moved by Unknown [1:12:20] · Seconded by Unknown [1:12:25]

The Student Services Director presented the Grow Your Own program, initially launched in the 2022-23 school year as a tri-district initiative offering scholarships and teacher pathways. The program has expanded to include three additional staff members, primarily focusing on supporting them in obtaining special education licenses. The agreements formally define the terms and conditions for their participation during their educational journey. The board commended the program as an excellent way to retain dedicated staff and benefit students.

Approve Community Ed Fee Schedule

6-0 Approved

Dissent: None

Moved by Unknown [1:14:15] · Seconded by Unknown [1:14:20]

The Education Director and Finance Director jointly proposed an increase in fees for the Kids Choice childcare program and the community preschool program. These increases, approximately $10-$20 per month for preschool and $1 per daily rate for Kids Choice, are intended to address rising operational costs, particularly labor, and maintain the financial stability of the Community Education fund. A comparison with neighboring districts indicated that the proposed fees remain reasonable and offer good value, especially considering scholarships available and the three-day-a-week preschool schedule compared to some two-day offerings.

Notable Quotes (5)

So, after months of conversation and kind of research and working with our community and our staff and uh the school board, I'm excited to bring um a recommendation on behalf of the administration before you um to call a special election on May 12th of this year. and that is to address a lot of the critical needs that we have at our facilities.

Lisa Brand Decker [0:46:00]
Resolution Authorizing Issuance of School Building Bonds and Renewing Capital Projects Levy Authorization and Calling an Election

This isn't about fancy glitzy stuff per se. This is about addressing aging facilities critical system needs. So for example, if our air handling systems go down, we can't bring fresh air into the building. We can't have people in the building.

Dr. Brian Zambrino [0:49:10]
Resolution Authorizing Issuance of School Building Bonds and Renewing Capital Projects Levy Authorization and Calling an Election

The one thing that gives me some pause is that the work that was done to try to figure out what we need to do was a couple years ago. And every year that we wait and decide not to maintain our facilities. Um the dollars that we expend as a district go less far.

Director Cummings [0:58:30]
Resolution Authorizing Issuance of School Building Bonds and Renewing Capital Projects Levy Authorization and Calling an Election

Some people might ask, why are we coming in May instead of November? And it is to be able to move forward on being able to do this work. Obviously, we don't want to interrupt the education that's happening in our buildings. So, a lot of construction projects need to happen during the summer.

Chair Hume [1:00:20]
Resolution Authorizing Issuance of School Building Bonds and Renewing Capital Projects Levy Authorization and Calling an Election

It was mentioned that there are scholarships provided and I wanted to reinforce that for our families because to send a three or fouryear-old to preschool gives them such a leg up and we've seen how prepared they are coming into kindergarten.

Director Claflin [1:16:10]
Approve Community Ed Fee Schedule

Ordinances & Resolutions (11)

Meeting Agenda and MinutesOther

Approval of the regular meeting agenda and minutes from previous work sessions and meetings in December 2025 and January 2026.

Amplify curriculumOther

New phenomenon-based science curriculum for 6th-8th graders implemented at South St. Paul Middle School.

Arts and Letters curriculumOther

New English Language Arts curriculum for 6th-8th graders implemented at South St. Paul Middle School, continuing Wit & Wisdom from elementary.

Strategic PlanPlan

Adopted in 2025, used as the framework for the board's mid-year self-evaluation and the superintendent's mid-year evaluation, featuring pillars like Packer Performance, Packer Pride, and Packer Promise.

Guiding Change DocumentOther

Reviewed during the work session to frame the budget process, focusing on achieving a balanced budget and strategic goals.

Resolution relating to the authorizing the issuance of school building bonds renewing the expiring capital projects levy authorization of the school district and calling an election thereonResolution

Resolution to call a special election on May 12th, 2026, for two ballot questions: a bond referendum for critical facility maintenance and a renewal of the capital projects levy for safety, security, and technology.

Facility StudyOther

Conducted in 2022 by Wald and Mark Fenton, identifying approximately $150 million in deferred maintenance needs across district buildings.

GASB 101Other

A new accounting standard related to vacation and sick leave, successfully implemented during the audit period.

Resolution directing administration to make recommendations for adjustments in programs and/or positions and reasons thereforResolution

Annual resolution providing flexibility to the administration to adjust programs and staffing as district needs evolve, without presuming reductions, as a preparatory step for the budget process.

Grow Your Own Candidate AgreementsOther

Agreements defining terms and conditions for staff members participating in a tri-district program offering scholarships and teacher pathways, with a current focus on special education licenses.

Community Ed Fee ScheduleOther

A proposed fee schedule for Kids Choice (childcare) and community preschool programs, with increases to address rising costs and maintain competitiveness with neighboring districts.