StoryMall of America Redevelopment Contract ExtensionJuly 22, 2026

Mall of America Redevelopment Contract Extension

Published Jul 25, 2026

{

"headline": "Port Authority Extends Mall of America Redevelopment Contract Amid Pandemic Impacts",

"subheadline": "The Bloomington Port Authority approved a second amendment to the 2016 Master Redevelopment Contract for the Mall of America property, citing unavoidable delays caused by the recent pandemic.",

"blocks": [

{

"type": "paragraph",

"text": "Bloomington, MN – The Bloomington Port Authority voted 4-2 to approve a second amendment to the 2016 Master Redevelopment Contract with MAC Land Holdings for the Mall of America property on June 17, 2025. The decision grants an extension to the ambitious redevelopment project, acknowledging significant disruptions and unavoidable delays encountered since the original agreement."

},

{

"type": "paragraph",

"text": "The amendment primarily addresses the need to adjust timelines impacted by external factors, particularly the recent global pandemic. Officials emphasized that the contract language included provisions for such unforeseen circumstances, allowing for extensions under specific conditions."

},

{

"type": "quote",

"text": "This is the second amendment of this version of the contract and it recognizes pandemic impacts to the redevelopment of the property as outlined in the staff report. The contract language does provide for extensions under certain circumstances that are unavoidable delays and in this case those delays include epidemics, government actions and force closures.",

"attribution": "Holly, Port Authority Commissioner"

},

{

"type": "paragraph",

"text": "The resolution, which had previously passed the City Council unanimously, was presented as a straightforward measure to keep the long-term development on track. Commissioner Nelson noted the consensus at the City Council level."

},

{

"type": "quote",

"text": "I don't have any questions. Just um as was alluded to, we looked at this last night as city council passed it unanimously. Um, I don't think there was a great discussion because it seems like a pretty straightforward issue to me that we just uh this is just an extension as we work together uh to get things done.",

"attribution": "Commissioner Nelson"

},

{

"type": "paragraph",

"text": "However, the decision was not without dissent. Commissioner LZ raised concerns about the ongoing nature and scale of the project, questioning the characterization of the extension as "straightforward," particularly given the significant financial commitments involved."

},

{

"type": "quote",

"text": "I watched that last night and all due respect to Mr. Nelson, the spending of $180 million is not preuncter or straightforward. I don't think I don't think it ever has been... I just don't think there's anything straightforward about this at all. Uh I think it's turned into a neverending project. I think it's got a fatigue factor to it.",

"attribution": "Commissioner LZ"

},

{

"type": "context",

"text": "The 2016 Master Redevelopment Contract governs the private redevelopment of land associated with the Mall of America, a cornerstone property within the City of Bloomington's South Loop area. These contracts often outline phased development, financial incentives, and timelines for major projects aimed at enhancing the city's economic landscape. Amendments are typically sought when unforeseen circumstances or market changes impact the feasibility or schedule of the original terms."

},

{

"type": "paragraph",

"text": "The approval of the second amendment underscores the Port Authority's commitment to the long-term vision for the Mall of America and its surrounding area. Despite the differing opinions on the project's pace and complexity, the majority vote indicates a continued effort to adapt development plans to external challenges and facilitate growth in one of Bloomington’s key economic drivers."

},

{

"type": "paragraph",

"text": "The specific details of the new timelines and milestones resulting from this amendment were not immediately disclosed, but the vote ensures that the framework for the Mall of America's redevelopment remains active, allowing developers to adjust their strategies in light of the acknowledged delays."

}

]

}

Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.

Go deeper on this topic

Research related meeting documents and build a brief — without rewriting the story.

Full analysis

Votes (2)

Second Amendment to the 2016 Master Redevelopment Contract for Private Redevelopment of Land with MAC Land Holdings

Motion carries 4-2 against (4 in favor, 2 opposed)

Dissent: Commissioner LZ [N/A] and one other unnamed commissioner.

Moved by President Ericson [N/A] · Seconded by Unknown [N/A]

The proposed amendment extends two performance thresholds by two years each (from 10 to 12 years, and 20 to 22 years) and adjusts redevelopment value requirements (reduction from $500M to $400M for the first threshold, increase from $700M to $800M for the second, total $1.2B unchanged). The justification was pandemic-related unavoidable delays. Commissioner Nelson expressed support, citing City Council's unanimous approval and the straightforward nature of an extension. Commissioner LZ vehemently opposed, criticizing the ongoing nature of the project, Triple 5's inability to secure private financing, and the significant TIF expenditure, calling it a 'neverending project' with 'fatigue factor'.

External Auditor's Report on the Port Authority's 2025 Year-End Financials

Motion carries 6-0 (Unanimously approved)

Dissent: None

Moved by Mr. Peterson [N/A] · Seconded by Unknown [N/A]

Andy Herring from Red Path presented the audit results for the City, Port Authority, and Housing Authority for 2025. He reported an unmodified opinion, the highest level, indicating financial statements were free from material misstatement and in accordance with GAAP. No findings related to internal controls, legal compliance, or material fraud were identified, though a federal compliance finding for Housing Choice Vouchers (not Port-specific) was mentioned. Key financial highlights for the Port included a $1.4 million increase in tax increment revenue and an $11 million increase in overall fund balance.

Notable Quotes (5)

This is the second amendment of this version of the contract and it recognizes pandemic impacts to the redevelopment of the property is outlined in the staff report. The contract language does provide for extensions under certain circumstances that are unavoidable delays and in this case those delays include epidemics, government actions and force closures.

— Holly/Port Authority Commissioner [N/A]
Second Amendment to the 2016 Master Redevelopment Contract for Private Redevelopment of Land with MAC Land Holdings

I don't have any questions. Just um as was alluded to, we looked at this last night as city council passed it unanimously. Um, I don't think there was a great discussion because it seems like a pretty straightforward issue to me that we just uh this is just an extension as we work together uh to get things done.

— Commissioner Nelson [N/A]
Second Amendment to the 2016 Master Redevelopment Contract for Private Redevelopment of Land with MAC Land Holdings

I watched that last night and all due respect to Mr. Nelson, the spending of $180 million is not preuncter or straightforward. I don't think I don't think it ever has been... I just don't think there's anything straightforward about this at all. Uh I think it's turned into a neverending project. I think it's got a fatigue factor to it.

— Commissioner LZ [N/A]
Second Amendment to the 2016 Master Redevelopment Contract for Private Redevelopment of Land with MAC Land Holdings

The result, we issued a clean opinion or an unmodified opinion, and that's the highest level of opinion you can receive.

— Andy Herring [N/A]
External Auditor's Report on the Port Authority's 2025 Year-End Financials

Thankfully, we did not uh come across any instances of for sure instances of fraud or anything that we suspected there to be fraud or any suspicions or allegations of that kind.

— Andy Herring [N/A]
External Auditor's Report on the Port Authority's 2025 Year-End Financials

Ordinances & Resolutions (7)

2016 Master Redevelopment Contract for Private Redevelopment of LandContract

The primary contract governing private redevelopment and use of tax increment financing on MOA property, subject to a second amendment.

Resolution approving an amendment to the 2016 master redevelopment contractResolution

Official action taken by the Port Authority to approve the proposed changes to the MOA contract.

Auditor's ReportOther

External audit report on the Port Authority's 2025 year-end financials, along with the City and Housing Authority.

Sewer Availability Charge (SAC) ProgramsPolicy/Program

City programs (Deferral and Credit) designed to provide financial assistance for SAC fees for businesses.

Minnesota Investment FundFund/Application

State fund that Seagate is applying to for potential expansion support.

Opportunity Housing OrdinanceOrdinance

An inclusionary zoning requirement for new developments within the city, currently undergoing updates.

Spending Plan TIFFinancial Instrument

Refers to the use of Tax Increment Financing and the associated legislative extension for its application.

Source document

Was this story helpful?

Other Topics from This Document

  • External Auditor's Report for 2025

  • Small Business Assistance Grant Program Review

  • Sewer Availability Charge (SAC) Programs Update

  • Administrator Updates and City Development Projects

Want to know when new stories arrive?

Enter your email to receive updates.

We will not use your email for any other purpose. You can unsubscribe at any time.