3/27/24 Construction Meeting - Mississippi Drive Area, Improvement Project No. 22402
Sunday, March 16, 2025
Project overview and schedule
Road construction and paving methodology
Intersection realignment at Adair Ave and West River Road
Utility infrastructure improvements (sanitary manholes, water mains)
ADA-compliant pedestrian ramp upgrades
Storm sewer and water treatment structure enhancements
Curb stop and gate valve repairs
Street lighting modernization
Communication strategies and hotline
Assessment structure and payment options
Notable Quotes (2)
If you see a flasher don't go around it because you'll probably step in some wet concrete.
Construction safetySafety warning for residents regarding ADA ramp upgrades.
If you are a regular user of email I'm sure we have neighbors and they feel typically an elderly demographic who don't get those please be a neighbor go connect with them.
Resident communicationAdvice on community cohesion during construction.
People (4)
Sam MorrisConstruction Manager
City of Champlain representative; main point of contact for construction operations.
Jen EdisonSenior Project Engineer
Works for WSB, the firm that designed the project plans and specifications.
Heather NelsonCity Engineer
Representing the City of Champlain's engineering department.
Tim LroyCouncil Member
Provides advice on resident communication and personal experience with city projects.
Places Mentioned
Adair AvenueWest River RoadPorter DrivePorter CircleColoradoEdward CourtMississippi DriveMississippi RiverWest River ParkChamplin
Events & Meetings (4)
- Project start: Beginning of April
- Phase 1: April to mid-July
- Phase 2: May to August
- Assessment deadline: November 15