10/3/24 Assessment Informational Meeting Mississippi Drive Area, Improvement Project No. 22402

Tuesday, April 15, 2025

Road project recap and status update

Construction challenges (gradation issues, organic material)

Infrastructure improvements (storm sewer, sanitary sewer, water main)

Project cost breakdown

Assessment funding and policy explanation

Property owner assessment payment options

Assessment appeal process (Minnesota State Statute)

Upcoming assessment hearing and timeline

Notable Quotes (2)

instead of trying to drill them out and possibly ruining the gate valve, we decided to replace all of them

Sam Morris
Water main improvementsExplaining the cost increase due to replacing corroded gate valves.

the total estimated project cost at this point... is just over 5 million

Heather Nelson
Project costsSummary of total project expenditure including storm, sanitary, water, and electrical.

People (3)

Sam MorrisConstruction Manager

City of Champlin employee overseeing the 3.6-mile road project.

Heather NelsonCity Engineer

City of Champlin engineer managing project costs and assessment logistics.

StephanieStaff

Managed remote meeting participants and questions.

Places Mentioned

Champlin, MinnesotaIntersection of D and West River RoadHennepin County

Events & Meetings (3)

  • October 15, 2024: Formal assessment hearing/council meeting
  • October 16 - November 15, 2024: Assessment payment window
  • November 30, 2024: Deadline for certifying assessments to Hennepin County
View Source
10/3/24 Assessment Informational Meeting Mississippi Drive Area, Improvement Project No. 22402 - Champlin Recorder