3/27/24 Construction Meeting - Mississippi Drive Area, Improvement Project No. 22402

Champlin City CouncilMonday, March 17, 2025
Watch on original source

Project overview and schedule

Road construction and paving methodology

Intersection realignment at Adair Ave and West River Road

Utility infrastructure improvements (sanitary manholes, water mains)

ADA-compliant pedestrian ramp upgrades

Storm sewer and water treatment structure enhancements

Curb stop and gate valve repairs

Street lighting modernization

Communication strategies and hotline

Assessment structure and payment options

Full Document Analysis

Notable Quotes (2)

If you see a flasher don't go around it because you'll probably step in some wet concrete.

— Sam Morris
Construction safetySafety warning for residents regarding ADA ramp upgrades.

If you are a regular user of email I'm sure we have neighbors and they feel typically an elderly demographic who don't get those please be a neighbor go connect with them.

— Tim Lroy
Resident communicationAdvice on community cohesion during construction.

People (4)

Sam MorrisConstruction Manager

City of Champlain representative; main point of contact for construction operations.

1 quote

“I'll be spending 80% of this summer on the road project working with the contractor making sure that any material he brings in on site or any infrastructure he implements into the street um meets the city's plans and specs.”

Describing his role as the lead inspector for the project.

Jen EdisonSenior Project Engineer

Works for WSB, the firm that designed the project plans and specifications.

Heather NelsonCity Engineer

Representing the City of Champlain's engineering department.

Tim LroyCouncil Member

Provides advice on resident communication and personal experience with city projects.

1 quote

“Get on that email blast and use the hotline as you as you have concerns don't hesitate don't get mythed don't get frustrated.”

Encouraging residents to use official communication channels to resolve construction issues.

Places Mentioned

Adair AvenueWest River RoadPorter DrivePorter CircleColoradoEdward CourtMississippi DriveMississippi RiverWest River ParkChamplin

Events & Meetings (4)

  • Project start: Beginning of April
  • Phase 1: April to mid-July
  • Phase 2: May to August
  • Assessment deadline: November 15