Verdon Avenue and Highway 100 Interchange Project - Meeting #8

E Interlockcan Boulevard and Vernon Avenue Intersection Work

Excel Power Line Relocation - Schedule Risk

Stage 3A Part One - Highway 100 On-Ramp Closure (July 21st)

Traffic Control and Pedestrian Safety at Interlockcan and Vernon

Public Communication and Information Dissemination

Votes (4)

Verdon Avenue and Highway 100 Interchange Project - Construction Progress Update

No formal vote recorded; informational update only

Project staff provided detailed updates on construction progress at multiple locations. At E Interlockcan Boulevard and Vernon Avenue, underground work is nearing completion with curb, gutter, and sidewalk installation underway. Paving is scheduled for early the following week, with traffic to be shifted from the Caribou corner to the Dino Liquor side. The project maintains a November 15th completion target, though schedule risks exist. Progress on the Vernon Avenue bridge abutments is visible, with east side construction ahead of west side due to the Excel power line conflict.

Stage 3A Part One - Highway 100 On-Ramp Closure and Detour Routes (July 21st)

No formal vote recorded; informational update and public notification only

Project staff presented the planned closure of the northbound on-ramp to Highway 100 at 50th Street, effective July 21st through late May, to enable noise wall construction, equipment storage, and grading operations. Two detour options were presented: a local route using frontage roads and Benton Avenue, and a regional route via Highway 62. Interactive GIS maps showing current conditions and the Stage 3A Part One closure scenario were displayed. The southbound exit ramp at Eden Avenue will remain open throughout the project. Part Two of Stage 3 (closure of southbound off-ramps) is planned for later in the summer with dates to be determined.

Traffic Control and Pedestrian Safety Review at Interlockcan and Vernon Intersection

No formal vote; commitment to review and address traffic control signage during traffic shift

A resident raised concerns about driver confusion at the Interlockcan and Vernon intersection, particularly regarding turn lanes and access to Walgreens. The resident noted that the recent traffic shift has created confusion, with increased honking and driver frustration. The resident specifically asked whether turn lane configurations would be improved, both permanently and in the near term. Project staff acknowledged the concern and committed to reviewing traffic control signage and markings during the upcoming traffic shift scheduled for the following week. Staff indicated that Derek (contractor) and John (project representative) heard the concern and would address it.

Public Communication and Information Dissemination Strategy

No formal vote; informational update and communication plan announcement

Project staff outlined the communication strategy for the July 21st closure and subsequent traffic changes. Updated interactive GIS maps will be posted to bettertogether.org. Information will be distributed through multiple channels including press releases, social media, and email notifications. A social media video will be released during the week to inform the public of the upcoming closure and detour options. The project team emphasized the importance of using these communication channels to reach residents and commuters.

Notable Quotes (15)

Project goals. We've seen this every time, but really improving safety and mobility for all users once the project is complete, improving traffic operations, consolidating those access points.

Project Manager/Chad [0:41-0:47]
Verdon Avenue and Highway 100 Interchange Project - Construction Progress Update

It was bid with a completion date of no November 15th of this year and there's still an issue that we're concerned about affecting that schedule which we'll talk about here shortly.

Project Manager/Chad [1:57-2:02]
Verdon Avenue and Highway 100 Interchange Project - Construction Progress Update

The concrete work will be done this week and they're coming in at 6:00 a.m. on Monday morning to pave the parking lot for here. And then they'll pave this intersection too where the green arrows are so traffic can move over. They'll pave one layer through everything and then they'll come back and pave the second layer of pavement on the parking lot around 10:00 a.m. roughly. So, all the paving should be done at noon.

Project Manager/Chad [3:15-3:40]
Verdon Avenue and Highway 100 Interchange Project - Construction Progress Update

The other issue that we're concerned about that we talked about at the last meeting was this Excel power line that was horizontally and vertically different than what we thought in the plans. This is the west support for the Vernon Avenue bridge. Here's the railroad. Uh, it was struck and repaired. There's some old agreements between CPKC Rail and Excel. Doesn't cover this line. The railroad says you need a new agreement. Excel was willing to move this. Our contractors willing to help move it, but without agreements. New agreements showing this line, not an aerial line. Railroad won't approve the work and Excel won't do the work. So, they are in that process right now requiring permits and agreements. Uh there has been some movement on the plans the last week. We're hoping this stuff gets uh cleared up, everything signed and permitted in the next couple weeks. Otherwise, it's going to be some major impacts to the schedule.

Project Manager/Chad [4:08-5:05]
Verdon Avenue and Highway 100 Interchange Project - Construction Progress Update

And again, Ediana, Henipin County, and Mindot have any control over these two agencies. They have to work it out. We keep asking every couple days on where they're at. Um, but we're concerned and hopefully we can just get it figured out and continue to work on this.

Project Manager/Chad [5:08-5:21]
Verdon Avenue and Highway 100 Interchange Project - Construction Progress Update

So northbound onramp is scheduled to be closed July 21st until late May. that allows them to build a noise wall that connects down by Miniha Creek and comes up this tree line all the way up to 50th Street. So, they can make room and build that noise wall, store equipment, do the grading operations, all the stuff that's needed that they can't do when traffic is using that on-ramp.

Project Manager/Chad [6:00-6:22]
Stage 3A Part One - Highway 100 On-Ramp Closure and Detour Routes (July 21st)

The local option is you use the frontage roads, the purple, and go down the Benton Avenue. And there's an on-ramp right here at that location to get on northbound. So, that's more the local route. Use either frontage road and Benton Avenue.

Project Manager/Chad [7:09-7:26]
Stage 3A Part One - Highway 100 On-Ramp Closure and Detour Routes (July 21st)

The official detour route. The regional one is you go down, get on southbound 100 at Eden, go all the way on it all the way down the highway 62. Take eastbound 62, loop, take that exit, then loop again on the northbound 100, and then you are at northbound 100. Continue on your way.

Project Manager/Chad [7:26-7:46]
Stage 3A Part One - Highway 100 On-Ramp Closure and Detour Routes (July 21st)

When you say south ramps, that's plural for both like the south the the ramp that goes from Eden onto a highway 100 south. That's that one will be open forever... Eden Avenue to go southbound 100 will be open for the duration of the project.

Nicole [12:42-13:22]
Stage 3A Part One - Highway 100 On-Ramp Closure and Detour Routes (July 21st)

I live right on the corner of Interlockan and Vernon, and it's a hot mess express, as we all know, trying to turn that corner. Um, and I've noticed that they're they're doing stuff on the other side. Are are they going to change the turn lane there? coming from say Jerry's onto Interlockan or turning from Interlockan towards Jerry's right on the corner by Caribou... I'm just noticing a lot of people are maybe my age or older are very confused there.

Resident/Anelopey [13:42-14:22]
Traffic Control and Pedestrian Safety Review at Interlockcan and Vernon Intersection

So they'll be shifting traffic most likely next week. So right now you're driving right on that corner of Caribou, right? All the traffic is going to be shifted to the corner of basically the liquor store. So you'll be on the other side. So it's going to make it a less less of a tight corner to swing through there. So it should be a little easier to navigate.

Project Manager/Chad [14:22-14:43]
Traffic Control and Pedestrian Safety Review at Interlockcan and Vernon Intersection

And then also up um when you turn because a lot of us turn in to go to the liquor or not liquor store to Walgreens or whatever... that is that going to be better um people don't really know what to do there when they're trying to go straight or turn from... what's that road? Well, it's ver onto the little driveway into Walgreens and Jerry. So, there's a turn lane there. No, but they don't. Nobody supposed to use it, but we can look at the traffic control.

Resident/Anelopey [14:49-15:25]
Traffic Control and Pedestrian Safety Review at Interlockcan and Vernon Intersection

Yeah. With this traffic shift next week, we have an opportunity to look at all those things. So, we have Derek and the contractor John on the call, so they both heard that. So, we can check that out next week and make sure it's all clear as we do that traffic shift next week.

Project Manager/Chad [15:42-15:56]
Traffic Control and Pedestrian Safety Review at Interlockcan and Vernon Intersection

All the various methods people should be very familiar with all these methods of communications better together.org is your main source of information. We are we have new maps that we've just finished up that'll be posted for the next change in the traffic operations which I'll get into shortly. But when we do those traffic changes, we do a lot of updates using press releases, social media, emails, those sorts of things. So look for those updates coming very soon through all those different channels with this latest change in the traffic.

Project Manager/Chad [1:31-2:02]
Public Communication and Information Dissemination Strategy

We'll be posting new maps to the website. Um, check it out. Like I mentioned, we'll be blasting out a lot of this information about the July 21st closure. We're going to do a no new social media video this week to get that out. And the options are the frontage roads that local detour down the Benton or down the Highway 62 then coming back up northbound 100.

Project Manager/Chad [16:09-16:35]
Public Communication and Information Dissemination Strategy

Ordinances & Resolutions (4)

bettertogether.orgPlan

Interactive GIS mapping platform and primary information source for project updates, traffic changes, and detour routes

Stage 3A Part One Road Closures and DetoursPlan

Traffic management plan for northbound Highway 100 on-ramp closure beginning July 21st, including detour routes and construction activities

CPKC Rail and Excel Power Line AgreementsPermit

Required new agreements and permits for Excel power line relocation at Vernon Avenue bridge west support; currently pending approval

Noise Wall Construction PlanPlan

Construction plan for noise wall extending from Miniha Creek along tree line to 50th Street, requiring Highway 100 on-ramp closure