June 26, 2025 Highway 100 Interchange Project Bi-Weekly Presentation
Sunday, June 29, 2025
Vernon Avenue and Highway 100 interchange project status
Construction timeline and substantial completion date
Traffic control and pedestrian safety updates
Edina Liquor Store site work and temporary closure
Utility conflict with Xcel Energy power line
Noise wall construction and residential impact
Upcoming ramp closures and traffic detour modifications
School zone impacts during construction
Notable Quotes (3)
This is a major concern from the project schedule standpoint... it could make some major delays if if something isn't addressed.
Construction Schedule/UtilitiesAddressing the unmapped Xcel Energy power line hitting a construction hurdle.
Give yourself extra time You need extra time to get in and out of that school campus to drop kids off pick up kids.
School Zone TrafficResponding to questions about OLG school access during heavy construction.
The completion date that was in the bid documents was November 15 2025.
Project TimelineClarifying that the project will not be finished by the time school starts in the fall.
People (1)
ChadProject Representative/Lead
Provides project updates, responds to public questions, and mediates between agencies.
Places Mentioned
Vernon AvenueHighway 100Interlocken BoulevardEaton AvenueGraange RoadEdina Liquor StoreHoliday Station (vicinity of West Bridge support)Sunny Slope Road WestHawthorne Condos/Hawthorne CourtOur Lady of Grace (OLG) School campus
Events & Meetings (3)
- Meeting Number 7 (Project Update)
- Monday, June 30th (Edina Liquor Store construction start)
- Mid-July (Potential ramp closure timeline)