Sep. 4, 2025 Highway 100 Interchange Project Bi-Weekly Presentation

Wednesday, September 3, 2025

Vernon Avenue and Highway 100 interchange project status

Construction safety and pedestrian traffic concerns

Project schedule delays due to Xcel Energy and CPKC Rail utility conflicts

Stage 4 detours and ramp closures beginning September 15

Business outreach and 'Worth the Detour' loyalty program

Highway 100 overhead sign maintenance update

5100 Eden Avenue development demolition updates

Construction progress on noise walls and retaining walls

Notable Quotes (3)

The Vernon Avenue bridge will not be done by November 15th.

Chad Milner
Project scheduleAddressing project completion deadlines.

Unless we learn something that this is going to be a much longer closure, at this point we're going to leave it as is.

Chad Milner
Traffic managementExplaining the continued closure of Gus Young Lane.

Should have been corrected long time ago in my opinion and it's not.

Chad Milner
Project managementCommenting on the utility conflict timeline.

People (1)

Places Mentioned

Vernon Avenue and Highway 100 interchangeEden AvenueBenton AvenueInterlocken BoulevardCPKC rail line50th StreetGrange RoadGrand View district50th and France districtEdina TheaterGus Young LaneHawthorne CourtArcadia

Events & Meetings (2)

  • September 15, 2025: Commencement of Stage 4 detours and ramp closures
  • November 15, 2025: Planned substantial completion date (excluding Vernon Ave Bridge)
View Source
Sep. 4, 2025 Highway 100 Interchange Project Bi-Weekly Presentation - Edina Recorder