Edina City Council — Transcript

Monday, July 21, 2025

Story

Major Highway 100 on-ramp closing for months of construction

Votes (1)

Vernon Avenue and Highway 100 Interchange Project Update

No official action or vote was taken; this was an informational update.

The city engineer provided details on upcoming closures related to the interchange project, specifically the 50th Street on-ramp to northbound Highway 100. This closure, lasting several months, facilitates the construction of a noise wall, a new on-ramp, and a signal system. Comprehensive detour routes were outlined, including both local and signed options. The speaker also addressed traffic safety and courtesy, noting issues with yielding to pedestrians and managing traffic flow around roundabouts, emphasizing cooperative driving for a safer travel experience.

Notable Quotes (3)

coming soon, the on-ramp from 50th Street to northbound Highway 100 will be closed. That work will close that intersection for a few months until late fall.

Chad Milner/City Engineer [0:06]
Vernon Avenue and Highway 100 Interchange Project Update

This will allow the contractor to build a noise wall from Minhaha Creek up to 50th Street. It'll allow them to build the new on-ramp and install the new signal system in that location.

Chad Milner/City Engineer [0:06]
Vernon Avenue and Highway 100 Interchange Project Update

We also ask that you be courteous to pedestrians and cyclists within the district. We're seeing a lack of yielding to pedestrians using crosswalks midblock and crosswalks around the roundabouts.

Chad Milner/City Engineer [0:06]
Vernon Avenue and Highway 100 Interchange Project Update
View Source
Edina City Council - Edina Recorder