a long-awaited replacement is coming to the pedestrian bridge over MInnesota Highway 62 the city will hire a fabricator to help finalize plans for a new accessible pedestrian bridge

dorothia Marty [00:00:00]Hiring a Fabricator for Accessible Pedestrian Bridge Replacement

we're at about 30% design for this pedestrian bridge and we're at a point where a fabricator will be able to help us estimate the true cost of the project We have a $6 million budget we want to ensure that we stay within the budget

dorothia Marty [00:00:00]Hiring a Fabricator for Accessible Pedestrian Bridge Replacement

if the project remains on track final bridge plans would be complete in September with construction in 2026 upon completion the city will own and be responsible for maintenance of the bridge