Edina City Council — Transcript

Monday, December 9, 2024

Story

Edina approves street reconstruction plan for aging neighborhood

Assessment Policy and Funding

Multimodal Transportation and Street Design

Resident Concerns and Project Impacts

Votes (1)

Public Hearing for 2025 Street Reconstruction Program - President's Neighborhood (A & B)

Carried

Dissent: Council Member Risser initially questioned the short timeline for online feedback, but ultimately supported an amended motion to extend the online public input period without formal dissent.

Moved by Council Member Agu [1:49:16] · Seconded by Council Member Jackson [1:49:18]

The public hearing initiated with staff presentations detailing the necessity of the project due to aging infrastructure (60-70 year old streets, deteriorating water mains), the shift in assessment policy (now 57.86% assessed to property owners for roadway costs), and proposed design changes including narrower streets for traffic calming, full utility replacement, and new multimodal facilities. The Transportation Commission's recommendation for separate bike and pedestrian facilities on Washington Avenue was noted, differing from staff's shared-use path proposal. Residents raised concerns about increased assessment costs, reduced on-street parking, the burden of sidewalk maintenance, safety of bike facilities on Washington Avenue (especially with semi-trucks), potential impact on mature trees, and construction inconvenience. There was a request for more transparent data supporting traffic calming and property value increases, and for considering alternative landscaping options beyond sod.

Notable Quotes (9)

we've changed the the methodology that we use for Street reconstruction uh assessments over time uh you're going to be the beneficiary of that he's going to talk about that that changing methodology a little bit where we switched uh from several years ago where we charged everybody for uh the roadway reconstruction everything under the street being paid for by all of us together uh as well as KB and gutter...

Mayor Hubin [2:43]
Public Hearing for 2025 Street Reconstruction Program - President's Neighborhood (A & B)

this really ties back to the budget work plan right pillar number one that you guys see and developed was the strong Foundation we want to make sure our infrastructure meets the community needs now and into the future.

Director Milner [5:02]
Public Hearing for 2025 Street Reconstruction Program - President's Neighborhood (A & B)

the Citywide average pavement condition index rating is 78 and the present a andb neighborhood average pavement condition rating for the streets is 26.

Aaron Ditzler/Assistant City Engineer [15:45]
Public Hearing for 2025 Street Reconstruction Program - President's Neighborhood (A & B)

there was a lot of kind of industrywide uh research that was done to come up with those Street widths for that rationale since then as we've implemented living streets we've done post reconstruction uh traffic counts and volume counts on these streets and we have seen you know anywhere from 1 to 2 m per hour to as much as a 5 m hour reduction in uh speeds on these local streets so we do have the data to support that there is a traffic calming uh benefit.

Aaron Ditzler/Assistant City Engineer [28:11]
Public Hearing for 2025 Street Reconstruction Program - President's Neighborhood (A & B)

our climate action plan specifically notes that we really need to reduce dependence on Turf and grass and you know I think this is a wonderful opportunity to try to give people some more options it may even save the city some money certainly it would save on the amount of water that's being used so it would be great if that language could be put into information going out to Residents.

Council Member Risser [29:23]
Public Hearing for 2025 Street Reconstruction Program - President's Neighborhood (A & B)

that was our recommendation that we felt strongly we put in front of you for this particular project but it leaves us with probably some questions for future reconstruction as well.

Andy Lewis/Chair of the Transportation Commission [45:50]
Public Hearing for 2025 Street Reconstruction Program - President's Neighborhood (A & B)

my primary concern right now is timing uh the proposed start time I believe would be in May and will take approximately 12 weeks to complete that is my concern because uh I'm pregnant and due April 12th so that will basically cover my entire maternity leave of dust noise I won't be able to go outside pretty much.

Marissa Esterly/Resident [1:32:32]
Public Hearing for 2025 Street Reconstruction Program - President's Neighborhood (A & B)

but my concern is I had several ash trees that were covering our property which were fantastic and then they had emerald ash bore and we had to cut them down I have one remaining tree that provides shade uh on the south side of my property which gets beaten with sun and that's the one thing that helps reduce some of my energy costs.

Joe Esterly/Resident [1:38:10]
Public Hearing for 2025 Street Reconstruction Program - President's Neighborhood (A & B)

the risk of hitting hit by a car is way greater I mean it's not even my opinion that's the fact then if you're on a sidewalk where a bike and a pedestrian would happen to interact the risk of a getting hit by cargo 30 plus of death is a is a big number of the percentages so I would prefer to keep the interested and families off the street and have a wider facility off the street which would allow parking on the street which would also allow parking that's why we kind of came up with that Balan solution...

Director Milner [2:01:05]
Public Hearing for 2025 Street Reconstruction Program - President's Neighborhood (A & B)

Ordinances & Resolutions (13)

Comprehensive PlanPlan

Guiding document for project design.

Race and Equity PlanPlan

Guiding document for project design.

Climate Action Living Streets PlanPlan

Guiding document for project design.

Pedestrian and Bicycle Master PlanPlan

Key guiding document for multimodal facility recommendations.

Active Routes School PlanPlan

Guiding document for project design.

Budget Work Plan (Pillar #1: Strong Foundation)Plan

City budget pillar emphasizing infrastructure development.

Living Streets PlanPlan

Plan developed in 2014-2015 that informed street width standards.

Chapter 429Other

State Statute governing special benefit tests for assessments.

BA 466Improvement Number

Improvement number for roadway improvements.

A293Improvement Number

Improvement number for alley improvements.

Edina's Pedestrian Bicycle Master PlanPlan

Plan used to guide the development of pedestrian and bicycle facilities within Edina.

Hopkins Pedestrian Bicycle Master PlanPlan

Hopkins' plan, consulted for regional multimodal connectivity, recommends a bike boulevard on Third Street and Second Street which Hopkins staff no longer support.

5-year Capital Improvement PlanPlan

City's plan for capital projects, currently does not include further south Washington Avenue improvements.

View Source