Sep. 4, 2025 Highway 100 Interchange Project Bi-Weekly Presentation
Edina City CouncilThursday, September 4, 2025
Watch on original sourceDocument Analysis
Analyze the transcript to extract topics, key quotes, people, and more — then generate focused stories for any topic.
Transcript
[0:00] Good morning everybody. Vernon Avenue
[0:02] and Highway 100 interchange project
[0:04] update meeting number 12. Just a
[0:07] reminder that we are recording these and
[0:09] we'll post them online afterwards. So
[0:12] I'm Chad Milner, engineering director.
[0:14] Thanks for joining us. Uh thanks for
[0:16] your patience. The project continues to
[0:18] move forward. Businesses are open and
[0:20] accessible. Of course with construction
[0:23] comes noise, dust, and vibrations. Um
[0:26] stop for pedestrians and crosswalks. We
[0:28] still have uh school started. So, we
[0:31] have a lot more people and kids and
[0:33] students using Eden Avenue, specifically
[0:36] Benton Avenue. There's crosswalks, kids
[0:38] going to school. Make sure we're being
[0:41] safe, courteous, and not only the
[0:43] pedestrians, but also the fellow
[0:45] drivers. So, please be patient. If
[0:48] you're not comfortable with that midb
[0:49] block crossing at uh Eden Avenue, please
[0:53] use the fully controlled traffic signal
[0:55] at Vernon and Eden instead.
[0:59] These are the project goals. Um again,
[1:02] it's to improve safety, mobility, create
[1:05] separated pedestrian routes, improve
[1:07] traffic operations,
[1:09] and the other ones there listed. We have
[1:12] the project schedule listed there. The
[1:14] com substantial completion date and
[1:17] reopening November 15, 2025. Um I can
[1:21] say that
[1:23] good good portion of the project will be
[1:25] reopened, but uh the Vernon Avenue
[1:27] bridge will not be done by November
[1:29] 15th. So that's an issue we'll talk
[1:31] about here a little bit more.
[1:34] This is the project again. It starts
[1:36] just west of Interlockan Boulevard. has
[1:38] the Vernon Avenue Bridge over the CPKC
[1:41] rail line. Then the Highway 100 bridge
[1:44] over Highway 100 that spans
[1:47] uh carries 50th Street and Vernon Avenue
[1:52] and then ends just near Graange Road on
[1:54] the east side.
[1:57] We've been doing all these communication
[1:59] channels for residents and businesses.
[2:02] uh continue to look for those, continue
[2:04] to push out that information. If people
[2:06] have questions, better together.org,
[2:10] visit the Vernon Highway 100 project
[2:12] page. That is your best spot to find
[2:15] information as we continue to move
[2:18] forward this fall.
[2:21] We have some big detours coming, so
[2:22] we're creating a special business
[2:26] outreach. So we want anybody that's
[2:28] associated with businesses to please
[2:30] fill out a survey. So go to this website
[2:33] edinaamn.gov
[2:36] businessup support and fill out the
[2:39] survey if you interested. But we are
[2:41] going to support the Grand View and 50th
[2:43] and France businesses this fall. We're
[2:45] going to have the worth the detour
[2:47] passport. So, it'll be a loyalty program
[2:50] where customers can collect stamps when
[2:52] you shop and dine at participating
[2:55] businesses and then enter to win gift
[2:56] cards at those favorite local spots. We
[3:00] want to thank the Explory Dina for their
[3:03] support.
[3:04] So, there's also going to be a
[3:06] restaurant week social media contest and
[3:09] a free familyfriendly movie on select
[3:13] Saturday mornings at the Dina Theater.
[3:15] So again, find all the details at better
[3:18] together.org. And if you're a specific
[3:20] business, go to that other website and
[3:22] fill out a survey. We did mail out
[3:24] letters to many of the businesses in
[3:27] both the Grand View and the 50th in
[3:29] France districts. So thank you and
[3:32] please fill out the survey.
[3:35] Construction details, uh, Interlock and
[3:37] Verdon, that's still a free flow
[3:39] intersection there. It's working and
[3:41] operating. We've got questions of can we
[3:44] open up Gus Young Lane by the Dino
[3:46] Liquor Store. We're hoping to have a
[3:48] crane there at any moment to start
[3:50] working on that west abutment. We did
[3:52] open it. We'd have to have either a
[3:54] four-way stop or a temporary signal. Um,
[3:58] and that would really, I think, impact
[4:00] traffic operations on this intersection.
[4:02] So unless we learn something that this
[4:04] is going to be a much longer closure, at
[4:08] this point we're going to leave it as is
[4:10] and prepare to place a crane and other
[4:12] equipment there to work on that west
[4:14] abutment.
[4:17] And why aren't we working on that west
[4:19] abupment? It's because the XL power line
[4:21] was as shown here and circled in green
[4:24] was in a different spot than originally
[4:27] uh thought. was hit in May and Excel
[4:31] Energy and TPKC Rail are continue to
[4:35] work on permits and agreements. We do
[4:36] not have it. They're working on it. I
[4:38] thought it would be done early to mid
[4:40] August. We have no control over these
[4:43] two agencies. Uh and it's major impact
[4:46] of schedule andor cost. and we still
[4:48] don't know what those are because until
[4:50] we actually get a permit and the
[4:52] contractor can start working. We can't
[4:55] put together any of those timing details
[4:57] or cost potential details. So, we're
[5:01] just in a waiting pattern. We're all
[5:03] contacting them. The mayor's contacting
[5:05] individuals. We're trying to get this
[5:07] move forward. um should have been
[5:10] corrected long time ago in my opinion
[5:12] and it's not and we're doing everything
[5:14] we can but this bridge will not be done
[5:16] November 15th. Uh we're just past that
[5:19] timing now. So until we know when this
[5:21] work can occur, updated schedules won't
[5:25] be developed. There's kind of
[5:27] potentially two options where they work
[5:30] uh straight through into the winter and
[5:33] heat and heat everything to do the
[5:35] concrete work, but there's a cost with
[5:37] that. order they go away and come back
[5:38] in the spring to finish. So, those are
[5:41] the two options we're looking at once we
[5:43] know when they can actually start.
[5:47] Road closures and detours. We have a big
[5:49] kind of the last detour stage four
[5:53] coming up. This is probably going to be
[5:54] the most impactful. Um and it's going to
[5:58] start on Monday, September 15th. So, all
[6:01] offramps
[6:03] are going to be closed on the 15th.
[6:08] So, if you're coming southbound on 100
[6:10] and use that Arcadia exit, that will be
[6:12] closed. That'll be a new closure. You're
[6:15] heading northbound and you take the exit
[6:17] to Graange Road, that will be closed.
[6:20] So, these three red X's will be new
[6:23] closures. The blue one was already been
[6:25] in place for a few weeks. We're updating
[6:28] our maps on the website and the
[6:29] interactive GIS map. Those will be
[6:31] updated soon. Um, but that's a big
[6:36] impact that's going to start September
[6:38] 15th and until until the mid- November
[6:42] date so they can build all these new
[6:43] ramps.
[6:45] What has been happening and will
[6:46] continue to happen this week is the
[6:48] Highway 100 bridge uh the gurners are
[6:50] going up the beams. So this first week
[6:52] of September been happening overnight.
[6:55] Northbound happened
[6:58] Tuesday and Wednesday night. Now
[7:00] southbound will happen Thursday and
[7:02] Friday night. So hopefully all the beams
[7:04] will be placed uh by this weekend.
[7:10] Uh again, we're going to create those
[7:12] detour maps for that stage four, but
[7:14] Benton Avenue, we've seen more traffic.
[7:15] We know the schools started Mindat
[7:18] turned the timing off on the on-ramp
[7:20] signal, so that helped a lot with some
[7:22] of those impacts. Uh the detours are
[7:24] going to be up to Excelsier and east and
[7:27] west down the highway 62 in east and
[7:30] west kind of the regional detours and
[7:32] there's going to be some more local
[7:33] detours. So look for those maps coming
[7:35] very soon on that stage 4 which starts
[7:38] in about a week and a half.
[7:41] We know there's a project going on
[7:43] Highway 100. This is a mindot
[7:44] maintenance project. They're doing
[7:46] overhead sign work. Um they closed the
[7:49] inside lanes. It's been closed for
[7:51] weeks. It's creating traffic issues.
[7:54] We ask when they're going to be done. It
[7:56] was anticipated to be done yesterday. I
[7:58] can't find anything whether it is or
[8:00] isn't done. Go to their website and that
[8:03] website hasn't been updated until August
[8:05] 12th. So, I haven't driven up there
[8:07] today. I don't know if it's closed or
[8:09] still underway. I'm hoping it's done um
[8:12] because that was creating some issues,
[8:14] but again, that's not related to our
[8:16] project at all. Um the timing is just
[8:19] unfortunate and MDOT's doing their
[8:21] maintenance work there on those overhead
[8:23] signs.
[8:26] Other things in the area. So 5100 even
[8:29] Eden Avenue. This was a development
[8:31] project. Last time or last couple
[8:33] meetings we talked about the sidewalk
[8:35] detour that's shown on the lefthand
[8:37] side. They built a temporary sidewalk on
[8:39] the west side of Arcadia and closed the
[8:41] sidewalk starting at the historic
[8:43] properties on the east side of Highway
[8:45] 100. The blue dash line is that detour
[8:48] for the sidewalks. They started demo on
[8:51] Tuesday. So, here's a picture where
[8:52] they're starting to bring that building
[8:54] down. That work has started this week to
[8:58] demo that existing 5100 building.
[9:03] In other pictures, uh this is the you're
[9:06] looking east
[9:08] by the Devanis. This is the Vernon
[9:10] Avenue bridge. You can see the east
[9:12] abupman is done and ready. Here's that
[9:15] west side. The old one is still in
[9:16] place. So that's a Excel power line and
[9:18] we're just waiting for that. So uh this
[9:21] is the major concern right now with
[9:23] schedule. This is a updated picture of
[9:26] that area.
[9:28] This is that free flowing intersection
[9:30] at Interlockan in Vernon that stays the
[9:32] same.
[9:34] This is the retaining wall at Hawthorne
[9:36] Court near the Hawthorne Apartment. So
[9:38] the picture on the left was from a few
[9:40] weeks ago. Picture on the right was a
[9:42] recent picture from this week. So, the
[9:44] wall construction keeps going forward.
[9:48] And then the overnight work that
[9:50] started, these are pictures from Tuesday
[9:52] night. So, uh, the left picture is, it's
[9:55] hard to see, but the crane is hoisting
[9:57] up those beams. This was the first one.
[10:00] Middle bottom picture is it's almost in
[10:03] place. And then a closeup of as they
[10:05] literally touch that down onto the
[10:07] abupments uh for that first first beam
[10:11] on Tuesday night.
[10:13] And then picture on the left is number
[10:15] two coming into place. You can see how
[10:17] they were hoisting that up with the
[10:18] crane in the background.
[10:20] Some other pictures where there's almost
[10:22] eight of them in place that night. So
[10:24] you can see the different all of them
[10:27] spanning northbound 100.
[10:32] And here's how they brought them in.
[10:33] They brought them in with a big long
[10:34] truck. The crane picks them off and then
[10:38] places them onto those abupments. So,
[10:42] northbound should be done. I haven't
[10:43] heard here this morning. Southbound,
[10:46] it's going to happen tonight, tomorrow
[10:47] night.
[10:50] Then here's what it looks like during
[10:51] the day. So, the picture on the left is
[10:53] those first eight placed on Tuesday
[10:56] night. And then the picture on the right
[10:59] is just a different view of showing
[11:00] those in place. And it's good to see
[11:03] shadows on the highway. That means the
[11:04] deck is starting to be constructed.
[11:09] The other major thing that's going on is
[11:10] that noise wall along the
[11:13] northbound on-ramp from 50th Street. So
[11:16] the picture on the left was from a few
[11:17] weeks ago. They were just getting
[11:18] started. Picture on the right, you can
[11:20] see all those concrete posts that are
[11:22] going to support that noise wall
[11:24] basically from Miniha Creek up to 50th
[11:26] Street. So they are continuing to put
[11:29] the poles in and then the planking will
[11:30] be coming in a few weeks and they'll
[11:33] start installing the planking on that
[11:35] noise wall.
[11:38] And then just another picture of the
[11:39] operations of installing those concrete
[11:42] noise wall posts.
[11:46] And then the graphics and rendering of
[11:47] what this will look like. So it's
[11:49] getting closer and closer all the time.
[11:51] You're getting to this for the high 100
[11:52] bridge. The picture on the left is a
[11:54] view of the of the deck of the Highway
[11:57] 100 bridge. The picture on the right is
[12:00] from the Highway 100 itself. as you
[12:03] would pass underneath the bridge heading
[12:04] northbound. You can start to see the
[12:06] beams that were placed the other night.
[12:08] Um, and this will be completely placed
[12:11] here over the next couple nights. So,
[12:12] we're starting to get to this image for
[12:14] the project.
[12:19] So, with that, I'll look at the chat. If
[12:21] people have questions, please enter them
[12:24] into the chat. I'm happy to answer those
[12:26] questions. You can always call me and
[12:28] email me or Derek. We're happy to answer
[12:30] questions, come visit with you, whatever
[12:32] the case may be. So, any questions?
[12:37] And I just remind any of the businesses
[12:40] if there's interest in participating in
[12:42] that worth the detour passport thing,
[12:45] may remember to fill out that survey
[12:48] so we know you're interested and we'll
[12:50] work with communications and get that
[12:52] started.
[12:57] Any questions?
[13:08] quiet group.
[13:10] See somebody type typing. So just wait a
[13:13] second.
[13:27] Uh looked like somebody was typing.
[13:28] Maybe not. Oh, look like it might be
[13:30] coming back.
[13:34] Uh even though let's see here's a
[13:36] question. Crane on Gus Young will wait
[13:40] and to agree then work will begin on the
[13:43] western abupment. Yeah, we no work can
[13:45] start. I mean, if we could have started,
[13:46] we would have had Excel move that line
[13:48] and we asked them to do it in May, just
[13:50] temporarily do something, but railroad
[13:53] wouldn't let them do it, and they
[13:54] weren't willing to work without a permit
[13:56] in the railroad. So, yeah, Gus Young
[13:58] will be for crane and other heavy
[14:00] equipment to build that western abupment
[14:02] soon as that permit is in hand between
[14:05] those two parties. Um,
[14:14] and even though that bridge may not be
[14:17] ready by November 15th, our intention is
[14:19] still to open up the Highway 100 bridge,
[14:22] the on andoff ramps there, the get
[14:24] everything active and operational along
[14:26] Highway 100 and open up as much as we
[14:28] can,
[14:30] as soon as we can. And then we'll deal
[14:32] with the Vernon Avenue Bridge and those
[14:34] schedules and that impact once we've
[14:37] finally learn more here between Excel
[14:39] and the railroad.
[14:46] Other questions,
[14:49] comments?
[14:53] Visit the website. We'll be updating
[14:54] some maps. Every time we do a big stage
[14:56] detour change, we send out specific maps
[15:00] to the businesses right at the area
[15:04] there. So, look for some of those emails
[15:05] coming from me. All those maps are
[15:07] posted on the website if other
[15:08] businesses just want to print those and
[15:10] give them to customers. Um, look for
[15:12] that passport program that we're
[15:15] creating right now for the businesses in
[15:17] both districts, Grand View and 50th in
[15:20] France.
[15:21] Um, but September 15th, it's going to be
[15:24] a big day when those ramps close early
[15:27] in the morning. People are going to have
[15:29] to find different routes to access this
[15:31] area. Benton Avenue will still have
[15:33] those the one off-ramp for southbound
[15:37] and on-ramp for northbound.
[15:40] But to get into these areas, you're
[15:41] going to have to come from Highway 62
[15:43] and either use the Valley View exit,
[15:46] France Avenue, or on the west side,
[15:48] Tracy Avenue or Gleon. Um on the north,
[15:52] Excelsier Boulevard coming down Wooddale
[15:55] or Brookside. So you're just going to
[15:57] have to use some other avenues. Blake
[15:59] Road and Interlockan from Hopkins is an
[16:01] option.
[16:05] So let your employees and customers and
[16:07] yourself find some routes there for
[16:10] September 15th.
[16:17] Other questions? I see somebody typing.
[16:21] Why wouldn't we open Gus Young until we
[16:22] have some kind of timing? Because we'd
[16:24] have to install a temporary signal andor
[16:28] four-way stops. And we think that would
[16:30] really gnarly up traffic even worse when
[16:34] we know that the hope is that there's a
[16:36] crane there very soon. So if it starts
[16:39] to become more long-term, then we'll
[16:41] look at potentially opening up Gus
[16:43] Young. But at this point, our hope and
[16:46] intention and the draft language we got
[16:48] from those two pe two agencies is that
[16:50] this is going to have a permit any day
[16:53] now. So um so it comes to
[16:58] construction needs for space and traffic
[17:01] operations of that intersection.
[17:04] Thanks for the question.
[17:12] Okay, again my info is on the website.
[17:16] There's further questions just send me
[17:17] an email or give me a call. Appreciate
[17:20] everybody's time. We'll get this posted
[17:22] and we'll post the slides on the website
[17:24] if you want to share that out with
[17:25] anybody at your organization.
[17:29] Thank you.