Oct. 2, 2025 Highway 100 Interchange Project Bi-Weekly Presentation
Edina City CouncilThursday, October 2, 2025
Watch on original sourceDocument Analysis
Analyze the transcript to extract topics, key quotes, people, and more — then generate focused stories for any topic.
Transcript
[0:01] Okay, good morning everybody.
[0:04] Uh, reminder we are recording. This is
[0:07] meeting number 14 for the Verdon Avenue
[0:09] and Highway 100 interchange project
[0:12] October 2nd, 2025.
[0:16] Again, thank you for your patience.
[0:18] Businesses are open and accessible. Uh
[0:20] we have some various
[0:23] programs going on right now to support
[0:25] the local businesses in the Grand View
[0:27] District and at 50th in France worth the
[0:30] detour passport. Uh restaurant week was
[0:34] last week so that one's uh over but
[0:36] Saturday morning family movies continue
[0:38] October and November. So visit the
[0:41] better together.org
[0:43] backworththed detour for more
[0:45] information on that.
[0:48] still having a lot of construction
[0:49] related stuff, noise, dust, vibrations.
[0:53] Continue to ask people to stop for
[0:55] pedestrians in the crosswalks and be
[0:57] courteous to fellow drivers. Again, if
[1:00] you're not comfortable with that
[1:01] crosswalk, uh the midblock crossing on
[1:03] Eden, uh we would recommend using the
[1:06] crosswalk at Vernon. That's a fully
[1:10] controlled traffic signal system.
[1:13] These are the project goals. Again,
[1:15] improve safety and mobility for all
[1:17] users. to create those separated
[1:18] pedestrian routes, improve traffic
[1:20] operations,
[1:22] consolidate the high 100 access points,
[1:26] uh, and create limited limit impacts
[1:28] with greater efficiency by combining the
[1:31] city and the county projects. So, we'll
[1:33] talk about the dates, uh, a little bit
[1:36] more as we get through this
[1:37] presentation. So, again, this is the
[1:39] project overview. Starts west of
[1:42] Interlockan Boulevard. It has the Vernon
[1:45] Avenue bridge over CP KC rail. Pink are
[1:49] the big wide sidewalks that are being
[1:50] constructed through the entire project.
[1:53] Uh and then the highun bridge that
[1:56] supports Vernon Avenue from the west and
[1:58] 50th Street from the east. And then the
[2:01] newly constructed and aligned on and off
[2:03] ramps on each side of that new bridge.
[2:09] Lots of communications have been
[2:11] happening throughout the duration of
[2:14] this project and will continue until the
[2:16] project is complete. Uh they are listed
[2:18] here. The main source of information
[2:20] again is the better together.org
[2:24] website.
[2:25] That is your best spot to check out
[2:28] information.
[2:30] Construction details, schedule details.
[2:32] Where are we at today? So this
[2:34] intersection has been and continues to
[2:37] be free flowing at Vernon in Interlockan
[2:40] Boulevard. Gus Young Lane lane is closed
[2:43] at the Dino Liquor Store and it's going
[2:46] to stay closed because the contractor
[2:48] needs that space for equipment and
[2:50] materials and cranes while they start on
[2:54] that west abutment work very soon.
[3:00] And speaking of that, the permit and
[3:02] agreements between the railroad and
[3:04] Excel Energy have been approved a week
[3:08] and a half ago. Excel has deenergized
[3:11] the power line and Ames is starting to
[3:13] work in this area next week. So, Ames
[3:16] will start removing the west the
[3:18] existing bridge abutman on the west
[3:20] side. They'll create space for Excel to
[3:22] come in with big steel conduit and
[3:25] casing and then Excel will run a new
[3:27] line inside that steel casing pipe. So,
[3:30] they are working together to get this
[3:31] work completed and it sounds like Ames
[3:34] is starting next week.
[3:37] These ramps closed a few weeks ago,
[3:39] continue to be closed uh until they're
[3:42] on schedule to reopen mid November. Um
[3:45] everything on this side of the project
[3:48] on the east side is continues to be on
[3:50] schedule for opening on that mid
[3:52] November is the is the schedule.
[3:57] Other schedule stuff, the Highway 100
[3:59] bridge deck, the entire thing was poured
[4:01] last Wednesday night. Um pretty
[4:04] interesting thing. 15 trucks roughly an
[4:07] hour from about 900 p.m. to 4 in the
[4:10] morning. So now the deck is ready to
[4:12] have the concrete median poured, the
[4:15] curbon gutter poured, the sidewalks,
[4:17] that's all happening next week. So the
[4:19] contractors getting ready to continue
[4:21] those concrete pores on that Highway 100
[4:23] bridge.
[4:25] The northbound Highway 100 on-ramp, the
[4:28] noise wall planks are starting. So
[4:30] you'll start to see those going up to
[4:32] finish that noise wall. The noise wall
[4:35] at Hawthorne Court, they're pouring the
[4:37] concrete noise wall posts. We started
[4:39] that yesterday. I have a picture of
[4:41] that. Uh we did ask the contractor to
[4:44] create multiple schedules and cost
[4:46] options.
[4:48] We asked if there was any way possible
[4:50] to open this bridge this year, the
[4:51] Vernon Avenue bridge. And if not, we
[4:54] asked them to create schedules and
[4:56] options to get Gus Young Lane open uh
[5:00] while that bridge is closed if we can't
[5:02] continue working through the winter. So,
[5:04] a lot of unknowns yet. They stated they
[5:07] would get us some of those schedule and
[5:08] cost options by the end of this week. Uh
[5:12] I should note that the Henipin County
[5:14] and the city will coordinate decisions
[5:16] on how to handle what schedules and what
[5:20] costs come forward. But most of the
[5:23] funding for the Vernon Avenue bridge is
[5:24] Henipin County. So they have to go
[5:26] through their processes to approve any
[5:28] change orders or change of schedules or
[5:30] any of that kind of stuff even though
[5:32] the city holds a contract. So there's
[5:35] processes by both agencies once we have
[5:37] that information to get those approvals
[5:40] to move forward. Once we know something,
[5:42] we will be sharing it out during these
[5:45] meetings on the website, emails, all
[5:47] those sources.
[5:50] So pictures, we'll just share some where
[5:52] we at today kind of pictures. Again,
[5:54] this intersection hasn't changed.
[5:56] Interlockin and Vernon Avenue free
[5:58] flowing.
[6:00] Uh this is the Vernon Avenue bridge
[6:02] area. You can see picture on the left is
[6:04] the east abupment. It's been done and
[6:07] ready. In the background, they're
[6:08] starting to form the wall next to
[6:10] Hawthorne Court. And then flipping
[6:14] around and looking from that abutment to
[6:16] the west, this is where this work is
[6:18] going to start next week. That power
[6:20] line's been deenergized and Excel and
[6:23] Ames are going to coordinate the work to
[6:25] start to build the abupment on the west
[6:27] side.
[6:30] Starting to get ready to pour the
[6:31] sidewalk along Vernon Avenue 2. So this
[6:34] is on the south side of Vernon near the
[6:36] Devonti as you can see in the
[6:37] background, but getting ready to pour
[6:39] the concrete curbon gutter and the wide
[6:41] sidewalk from that east abutment
[6:47] at Hawthorne Court. This is looking at
[6:49] the apartment. You can see the noise
[6:52] wall post installed adjacent to the new
[6:55] retaining wall which starts near the
[6:58] apartments and heads west. And in the
[7:00] background, which is the picture on the
[7:03] right, you can see they're starting to
[7:05] form and actually pour those noise wall
[7:08] posts that are on top of that retaining
[7:10] wall. So that wall continues to be
[7:13] constructed.
[7:15] And here's some pictures from that
[7:17] Wednesday night pour from just over a
[7:19] week ago. as very large crews got out
[7:22] there and were doing this work, pouring
[7:25] lots and lots of concrete finishing it,
[7:28] broom, finishing it, working on that
[7:30] deck. You look at the rebar here on the
[7:33] bottom lower of the right hand pitcher.
[7:36] That's where the concrete curve and
[7:37] sidewalk will be poured next week.
[7:42] So, they're tying into that exposed
[7:44] rebar there for the curb and the
[7:45] sidewalk.
[7:47] Again, more pictures of that night. The
[7:49] one on the left, you can see the smooth
[7:51] gutter line that'll be adjacent to the
[7:54] curb when it's complete. And the one on
[7:57] the right, again, just a big big pumper
[8:00] arm concrete pumping truck to place that
[8:03] concrete on that deck during those
[8:05] overnight hours.
[8:10] Picture of the bridge again from a
[8:12] different angle. You can see Highway 100
[8:14] in the background on the left. And then
[8:16] again on the right hand picture is
[8:18] showing the the new off-ramp
[8:22] alignment where that dozer is in the
[8:24] background. That'll be northbound high
[8:27] 100. You'll come up go under the Eden
[8:29] Bridge and come straight up to the 50th
[8:32] Street intersection. So that braiding
[8:34] work is well underway and nearly
[8:37] complete and they'll soon be installing
[8:40] concrete curbs and all the paving along
[8:43] those on and off ramps within the
[8:45] project. Again,
[8:48] these are the renderings that we've
[8:49] showed throughout these meetings. The
[8:51] one on the left is the the bridge from
[8:53] the top. It's getting closer to that
[8:55] view every every day. And then the one
[8:58] on the right is the view from northbound
[9:01] I 100, which is starting to look very
[9:03] much like the rendering also.
[9:09] So, stop sharing here and see if there's
[9:12] any questions in the chat. So if you
[9:15] have any questions, please type it in
[9:18] in the chat and we can answer those
[9:20] questions. Now the meeting will be
[9:23] posted, these slides will be posted to
[9:24] the website. The recording will be
[9:26] posted to the website. If you got
[9:28] questions, just reach out directly to
[9:30] me. Uh we can help answer those
[9:33] questions. Once we know more on the
[9:35] schedules, those will be posted and
[9:36] provided to everybody. Um,
[9:41] see anybody typing in no questions.
[9:46] Again, we'll be posting this
[9:48] information. Updates will be to the
[9:50] better together.org
[9:53] website. If you have specific questions,
[9:55] feel free to call or email and happy to
[9:58] answer those.
[10:01] Still don't see anybody typing, so I'm
[10:02] going to call it a meeting. Thanks,
[10:04] everybody.