RecordingTranscript available20:27
Aug. 7, 2025 Highway 100 Interchange Project Bi-Weekly Presentation
Edina City CouncilThursday, August 7, 2025
Watch on original sourceDocument Analysis
Analyze the transcript to extract topics, key quotes, people, and more — then generate focused stories for any topic.
Transcript
[0:00] Okay, we'll get started. But we're here
[0:02] for the Vernon Avenue Highway 100
[0:03] interchange project. This is update
[0:05] meeting number 10, August 7th, 2025.
[0:10] Again, thanks for the patience. Uh
[0:12] businesses, again, a reminder, they're
[0:14] open and accessible. There's routes to
[0:16] get to them. We have all the
[0:18] construction related stuff, noise, dust,
[0:19] vibrations.
[0:21] Uh please stop for those pedestrians in
[0:23] the crosswalks. Be courteous to fellow
[0:25] drivers in the roundabouts. Truck is
[0:28] heavy. Uh so please take your time and
[0:31] again if you're not comfortable using
[0:33] that midblock crossing Eden we would
[0:35] recommend using the crosswalk at Vernon
[0:37] in Eden instead of the fully signaled uh
[0:42] intersection there of the crosswalk.
[0:46] Yeah, we always share the project goals.
[0:49] Uh we're here to improve safety and
[0:50] mobility of all users, improve traffic
[0:53] operations, create those pedestrian
[0:55] separated pedestrian routes, and improve
[0:58] connectivity in the area. Uh we'll talk
[1:00] a little bit about schedule here uh as
[1:03] we go through the presentation today.
[1:06] And this is the project starts west of
[1:08] Interlockan Boulevard. We have the
[1:10] Vernon Avenue bridge over CP Rail,
[1:13] Casey, CP Casey Rail, and then we have
[1:16] the bridge over Highway 100. This is the
[1:18] project and the interchange at 100 is
[1:21] called a tight diamond interchange.
[1:25] Lots of ways to communicate. We have
[1:27] this bi-weekly meeting every other week
[1:31] 11 a.m. Thursdays. We have a better
[1:33] together website betterto
[1:35] togetherdina.org/veron-hwy00.
[1:42] We also been doing press releases,
[1:43] Friday reports, email updates. Uh people
[1:46] were signing up for those when the
[1:47] project started. Direct mailers, lots
[1:50] and lots of different ways to
[1:51] communicate with both people in the
[1:54] area, traveling in the area, businesses,
[1:56] and a lot of information posted to the
[1:58] website. So if you're looking for more
[1:59] info, check out the website. If you
[2:02] haven't signed up for emails, do we also
[2:07] some specific details of where the
[2:09] project is at this point. So, if we
[2:11] start at the Vernon interlocking
[2:13] intersection, uh that is and continues
[2:16] to be free flowing. There's no signal
[2:18] there today. Uh Gus Young is still
[2:21] closed by Dina Liquor Store. Most of the
[2:24] work is complete or will be complete
[2:26] this week, next week. Then they'll be
[2:28] shifting traffic back to the west
[2:32] here, the corner, kind of what I have
[2:33] drawn here. and they'll continue to be
[2:36] free flowing there as long as they need
[2:38] it to complete the rest of the work to
[2:41] the east of this intersection.
[2:44] So, look for some slight changes there
[2:46] as they wrap up this work in the next
[2:47] week or so.
[2:50] Uh the power line, we've talked about
[2:52] this for at least 6 weeks, I believe.
[2:55] So, the Excel power line is horizontally
[2:57] and vertically different in the field
[2:59] than what we thought. Uh it was shown on
[3:02] the plans. It was struck and repaired.
[3:05] There's no agreements. Uh both parties
[3:07] are working on permits and agreements.
[3:09] There has been no
[3:12] construction movement on this. So what
[3:14] you see in the picture is still today.
[3:16] Uh that concrete is from the old bridge.
[3:20] Uh I'm having major concerns, major
[3:23] impacts to schedule and cost are coming
[3:25] and we don't even know what that is yet
[3:27] until we can actually get Excel and CP
[3:29] to get a permit to move this stuff
[3:32] around. So,
[3:34] uh, I'm very concerned on how this is
[3:37] going to impact the entire project cuz
[3:39] this has been 3 months and it's still
[3:41] sitting in the same spot.
[3:44] Um, and neither agency was willing to do
[3:46] any kind of temporary moves and stuff
[3:47] like that. So, more to come on this when
[3:50] we actually know
[3:52] when the permits will be done, when the
[3:54] contractor could potentially assist with
[3:56] some of the work. Once we know that,
[4:00] then we can actually put together some
[4:02] contractor could put together some
[4:03] schedules and some potential cost
[4:07] implications to the project.
[4:11] Uh last week on Monday, July 28th, the
[4:14] northbound on-ramp from 50th Street was
[4:17] closed. It's closed until the fall so
[4:20] they can build the ramp, realignment of
[4:22] the ramps and the noise wall from
[4:24] Minihana Creek up to 50th. And again,
[4:26] there's GIS mapping. There's a link
[4:28] there that shows the different mapping
[4:31] for the detours. One is along Highway
[4:34] 100. You would exit on eastbound 62 and
[4:37] then stay and exit right away again to
[4:40] northbound 100. The other detour is the
[4:42] local frontage roads on each side of 100
[4:44] down to Benton Heaven.
[4:48] So, we know Benton Avenue shown here is
[4:51] experiencing more traffic. There's more
[4:53] delays at that location. We have been
[4:56] working with MDOT. They did ret time the
[4:58] on-ramp signals for that northbound
[5:00] exit. We'll continue to look at that,
[5:03] work with MDOT, but just know that
[5:06] Benton Avenue is has had a big increase
[5:09] in traffic and it's going to get worse.
[5:12] School starts August 25th. So, we got
[5:15] the Dina schools right at this location
[5:16] and we have OG on Eden and Arcadia area.
[5:20] So, in a couple weeks, we're going to
[5:22] have all the school traffic back at both
[5:24] these locations.
[5:27] What's coming up? Uh, at some point, we
[5:29] need to do the stage 3A part two, which
[5:32] is the westbound ramps or the southbound
[5:36] off-ramps.
[5:37] Sometime in September. We don't have a
[5:39] hard date yet. Um, sometimes in
[5:42] September, that is going to close. And
[5:44] then we also need to do stage 3B, which
[5:47] is the northbound
[5:51] exit to Graange. They have to build that
[5:54] ramp there, too. So, that one will need
[5:56] to change. So, we have two ramp closures
[5:59] still to conduct sometime in September
[6:03] when we know those dates. We'll be
[6:04] sharing those out. Um, so Benton Avenue
[6:07] will get worse with those closures also.
[6:09] So, it is going to get
[6:12] worse before it gets better from a
[6:14] traffic standpoint within this area.
[6:17] Uh some cool things, the bridge is going
[6:19] to start to really take shape for the
[6:21] first week of September. If everything
[6:23] goes according to schedule, the gerters
[6:25] are going to show up overnights.
[6:27] Uh two nights for northbound, two nights
[6:30] for southbound, placing those girders uh
[6:33] over the highway. So that's really going
[6:35] to start to take shape that Highway 100
[6:36] bridge is moving forward very nicely.
[6:42] Another thing that's going to start to
[6:43] impact stuff is the 5100 Even Eden
[6:46] Avenue. It was a development project
[6:48] approved by the city council. They are
[6:51] going to start work uh some temporary
[6:53] work starting August 18th. So, as shown
[6:56] in this graphic, uh they're going to
[6:58] build a temporary sidewalk along the
[7:01] west side of Arcadia Avenue from just
[7:04] north of the roundabout at Arcadia and
[7:06] Eden up to the crosswalk
[7:09] near the Vernon shops. During this work,
[7:12] the parking will be removed along the
[7:14] west side and they'll have flaggers out
[7:16] there. Once that work is complete, the
[7:18] parking will be reestablished. Also
[7:21] during that week, they'll install jersey
[7:22] barriers and fencing around their
[7:25] property uh as they get ready to start
[7:28] doing demo and grading operations for
[7:30] their project. Then that blue dash line
[7:33] is the sidewalk detour. So, there'll be
[7:35] signs placed uh over at the roundabout
[7:38] at Graange to use that crosswalk and use
[7:42] the south sidewalk along Eden Avenue
[7:46] around the Eden Arcadia roundabout and
[7:48] then use this new west temporary
[7:51] sidewalk up the west side of Arcadia
[7:54] where there is no sidewalk today. So,
[7:56] they're building that. They need to
[7:58] close the sidewalk adjacent to that
[8:00] parcel on both Eden and Arcadia so they
[8:03] can safely work on that parcel.
[8:08] And then some pictures. Uh we always go
[8:10] through some pictures and provide some
[8:11] updates. Uh this picture is again
[8:13] looking at the Vonnies on the right hand
[8:16] side from various weeks of construction.
[8:18] And the one on the right is what it
[8:19] looks like today. So that bridge
[8:23] foundation and bridge support is is
[8:25] coming along very very nicely there on
[8:28] the east side of the CPKC rail with the
[8:31] B bridge.
[8:34] Uh this is the intersection. The one on
[8:35] the left was from two weeks ago where
[8:37] they were still doing utility work.
[8:39] Photo on the right is what it looks like
[8:41] today. So they have curb and gutter in.
[8:43] They're pouring sidewalks. You can see
[8:45] the signal base is in and then they'll
[8:47] be paving next week and then shifting
[8:50] this traffic back over to that side in
[8:53] that intersection like I discussed
[8:55] earlier.
[8:58] Uh the area in front of the Dino liquor
[9:01] store is complete. So this is a picture
[9:02] of that and we got the bike racks
[9:04] installed uh in this photo on the left.
[9:08] Then on the right is a photo looking
[9:10] west. That's Washurn McCree funeral
[9:14] chapel in the background. And this is
[9:16] the east side of the high 100 bridge. So
[9:19] just seeing some of the work taking
[9:21] shape there on the east side of Highway
[9:23] 100.
[9:26] This is near Hawthorne Court, Hawthorne
[9:28] Apartments. The one on the left was a
[9:30] photo from a couple weeks ago. And the
[9:31] one on the right is from this morning as
[9:33] they continue to pour that retaining
[9:36] wall before the noise wall gets
[9:38] installed on top of that retaining wall.
[9:44] This is looking east towards city hall.
[9:48] You can see the green traffic signals in
[9:50] the background. Photo on the upper left
[9:52] was from four weeks ago. Bottom left was
[9:56] from two weeks ago. And the bigger photo
[9:59] on the right is from this morning
[10:01] showing all the bridge supports
[10:03] foundation work that's happened as they
[10:05] get ready for those gvers here in a few
[10:07] weeks of that first early September.
[10:12] Then a couple zoomed in more give you
[10:15] some scale of the bridge and the work
[10:17] these guys are doing. So both left and
[10:20] right are both on the Highway 100
[10:22] bridge. I think they're both on the west
[10:24] side of Highway 100, but just giving you
[10:26] an idea of the work they're doing, the
[10:29] scale there.
[10:32] And the again are renderings of the
[10:33] finished bridge at 100. Left photo is
[10:37] showing those wide sidewalks, new
[10:39] traffic signals, and new turn lanes. One
[10:43] on the right is the rendering of the
[10:46] bridge from Highway 100 heading
[10:47] northbound. And you're seeing all those
[10:49] supports are nearly complete. And those
[10:52] girders will be coming in just a few
[10:54] weeks as this thing really starts to
[10:55] take shape. Uh so we do this meeting in
[10:58] two every two weeks. In two weeks Derek
[11:01] Houston, our rep with TKDA is going to
[11:04] be hosting this meeting and sharing
[11:05] additional information as I will be out
[11:07] at the office. So for Derek to host the
[11:11] next meeting here in two weeks.
[11:14] So I'll stop sharing and see there's any
[11:17] questions
[11:19] in the chat. Any
[11:26] questions
[11:31] for people to type in questions?
[11:34] Diana staff
[11:36] unmute and ask questions if you have it.
[11:40] Uh, question one, will there be new
[11:42] trees planted and if so, where and what
[11:44] kind? Um, most likely not. We took a few
[11:49] trees down that were volunteer trees.
[11:54] Most of the bridges are wider than they
[11:56] were before. So, we needed that space
[11:58] for either the bridge structures or the
[12:00] sidewalks. There was really not a lot of
[12:03] space left for trees. Other than some
[12:07] promises we made to Hawthorne apartments
[12:10] there on their on their property behind
[12:13] the new noise. So, in that area, there
[12:15] will be some trees. We look if there's
[12:18] other space, but right now it doesn't
[12:19] look like there'll be too many new trees
[12:20] just because we needed the space for
[12:22] these new facilities.
[12:26] Will mulch borders be replaced by my
[12:29] road sign?
[12:31] Uh, and Ryan, the holiday manager,
[12:35] we can meet with you and talk through
[12:38] restoration of your property as part of
[12:40] this project. So, uh, typically we want
[12:42] to put stuff back the way it was before
[12:44] we got there. So we can definitely work
[12:46] with you. We'll have Derek reach out. We
[12:49] can have a conversation.
[12:53] Brian had a question. Any more
[12:54] commentary to offer about why Rail and
[12:56] Excel don't seem to care about time,
[12:57] cost, or inconvenience?
[13:00] I have a lot of commentary, but I don't
[13:02] think it's appropriate for this meeting
[13:06] on on the lack of urgency by both
[13:08] parties. The why a great question. I
[13:10] have no idea why. We've communicated
[13:13] with them multiple times for three
[13:16] months every week. What are we doing?
[13:18] This is the major issue. Um, stuff like
[13:22] that. Uh, Mr. Crabtree, doesn't the 1968
[13:26] agreement cover? It covers an aerial
[13:28] line, not a buried line is what we got
[13:30] confirmation from those parties. So,
[13:33] buried line got hit. It technically
[13:36] wasn't covered in any agreements between
[13:38] the parties. And again, that's between
[13:40] them.
[13:43] I have a question regarding the east
[13:44] side of the new Vernon Avenue bridge
[13:47] adjacent to Devanis.
[13:50] Will there be an open gap between the
[13:52] new bridge structure and the Devan's
[13:54] building or will that space be filled
[13:56] with new concrete and other landscaping?
[13:59] Uh very detailed question Darren. I
[14:02] think we would check in with you offline
[14:05] and we can show you some plans and the
[14:07] verific
[14:13] have a conversation and help answer that
[14:15] question.
[14:17] Uh Mr. crab tree again and who's
[14:19] responsible for any cost over on the
[14:21] city, the county, the mindot. Great
[14:24] question. We don't know yet. I would add
[14:27] additional parties to that list. Excel
[14:28] and rail, but how would what's our
[14:31] ability to get those from them? That's a
[14:34] good question. So, there's cooperative
[14:36] agreements that lay out cost
[14:38] responsibilities for the Hannipan County
[14:40] Bridge, the Highway and Hinder Bridge,
[14:42] and everything in between. And so
[14:44] typically if items overrun those cost
[14:46] share agreements, operative agreements
[14:49] would dictate where those additional
[14:51] costs go. Feel like this bridge side is
[14:54] a different conversation that uh
[14:58] potentially attorneys would get involved
[15:00] in that discussion.
[15:02] I live near Hawthorne Court near the
[15:05] Atra crossing going through West 49th
[15:08] Street. It appears the recent concrete
[15:10] patching down on the street top of the
[15:12] tracks were too high. Seems like every
[15:14] time the train cut these massive scrapes
[15:16] against the grout.
[15:19] Uh we could take a look at what you're
[15:21] talking about. So it sounds like the
[15:22] crossing at 49th Street, the Buminous
[15:24] was recently repaired.
[15:26] Um we can take a look.
[15:30] Will there be any tree clearing done
[15:32] around 5100 building and the bridge that
[15:36] connects to the other side?
[15:40] Good question.
[15:42] The map here and look at that site.
[15:45] Nothing is being done to the Eden Avenue
[15:47] bridge.
[15:51] I don't think they have any trees on
[15:53] their site. There's a few trees and
[15:56] landscaping above that big retaining
[15:58] wall. There's a few trees along Eden by
[16:04] their east driveway.
[16:07] those would get removed but then the
[16:09] other trees are mostly in mind rightway.
[16:11] So that's a question for
[16:14] the developer and whether they worked
[16:16] out any agreements with Mindot and those
[16:18] trees that are outside their property
[16:20] line in the Mindot right away on the
[16:22] east or the north side of this port.
[16:29] At a previous update you mentioned that
[16:32] CPKC was paid to expedite a decision on
[16:35] the line. Who paid to expedite the
[16:37] decision and how was it paid?
[16:40] Uh it's a project expense. So it's split
[16:43] between all the parties
[16:45] and paid as such.
[16:55] Great questions.
[16:57] Great questions.
[17:01] What will replace the 5100 Eden
[17:04] building? Uh it's going to be a
[17:07] corporate headquarters, so commercial
[17:10] building
[17:12] uh for Opus, the Opus Development
[17:15] Company, and then have a little retail
[17:20] space on the first floor.
[17:22] Those can be found, those were in
[17:24] council packets earlier this year if
[17:26] you're interested in seeing all those
[17:28] renderings
[17:29] of the project that was approved by the
[17:31] city council.
[17:39] questions.
[17:41] Uh, I didn't answer. So, Justin, on that
[17:45] decision to expedite, that was a $2,000
[17:49] fee if you want to know. We felt like
[17:51] that was justified for a $20 million
[17:54] project to try to keep it on schedule as
[17:57] best we could because we felt like that
[17:58] could be the hangup of this. my opinion
[18:02] it's been more Excel has been the hang
[18:04] up on this matter.
[18:14] Um and Bill just put a link in from
[18:16] better together.org the Opus 5100 Eden
[18:19] development. So there's a link if you're
[18:22] interested in looking at that
[18:24] development project. Thanks, Bill, doing
[18:26] that.
[18:31] Other questions? So, I think there's a
[18:34] lot of unknowns, unknown schedule on the
[18:36] ramp closures coming up, unknowns on
[18:40] when two parties are going to figure out
[18:43] the power line.
[18:46] So then that creates an unknown on just
[18:48] the overall project schedule and
[18:50] potential costs.
[18:52] When we know more, we'll be sharing more
[18:55] specifics out on these meetings, on the
[18:57] website, and all those other
[18:59] communication channels that we discussed
[19:01] earlier.
[19:08] Uh Darren, where can I reach out to you
[19:10] about a question space? Uh go to the
[19:12] better together.org
[19:14] website, find the project page, and
[19:16] Derek and I's phone number and emails
[19:18] are on there. So then you can just ping
[19:22] us that way, share your info and we can
[19:24] reach out and meet you probably the best
[19:26] is meet you out at Devanis and review
[19:29] the area you're concerned about.
[19:31] Derrick's out there every day for the
[19:33] most part and can meet with you to have
[19:35] those discussions.
[19:39] Check out the website for emails and
[19:41] phone numbers.
[19:48] Anything else?
[19:52] Great questions.
[20:00] We will post the slides. We'll post this
[20:04] recording to the website
[20:07] as soon as we can. So, if you know of
[20:08] others that want to see or hear this
[20:10] information, send them there. If you got
[20:12] specific questions, just reach out to me
[20:14] or Derek. Be appreciated. For a
[20:17] reminder, in two weeks, Derek will be
[20:18] presenting information on where we're
[20:20] at. So,
[20:22] thanks everybody. Appreciate your time
[20:25] and interest.