RecordingTranscript available20:06
July 24, 2025 Highway 100 Interchange Project Bi-Weekly Presentation
Edina City CouncilThursday, July 24, 2025
Watch on original sourceDocument Analysis
Analyze the transcript to extract topics, key quotes, people, and more — then generate focused stories for any topic.
Transcript
[0:00] Meeting number nine already. Man, time's
[0:03] flying. Meeting number nine, July 24th,
[0:06] 2025. We are recording these and posting
[0:09] the videos online, the bi-weekly meeting
[0:12] for the Vernon Avenue Highway 100
[0:15] interchange project. And I'm Chad
[0:17] Milner, engineering director for the
[0:18] city.
[0:20] Again, thank you for the patience.
[0:22] Businesses are open and accessible. Uh
[0:26] we have all the construction related
[0:27] stuff. everyone's well aware of what's
[0:29] going on out there.
[0:31] Continue to be courteous of the fellow
[0:34] drivers. Stop for pedestrians and
[0:35] crosswalks.
[0:38] We're recommending using the crosswalk
[0:39] at Vernon and Eden instead of that Eden
[0:42] Avenue bid block crossing. We just don't
[0:45] feel we can make it as safe as it needs
[0:47] to be with the volumes of traffic that
[0:49] need to use Eden Avenue for this project
[0:51] for the detour. So again, we recommend
[0:54] you use that Vernon Eden crosswalk at
[0:57] the full intersection. Um, and then we
[1:00] also continue to get calls and emails
[1:01] about courteousness of the drivers
[1:04] around the roundabout. Uh, I wish we
[1:07] could change some of those behaviors,
[1:08] but yeah, there's some people that
[1:10] aren't allowing others to get in. So
[1:13] there's somebody driving through there.
[1:14] I would suggest if you see a long line,
[1:16] just slow down. Let one or two cars
[1:19] sneak in. the car behind you honks at
[1:22] you, make sure you wave with all five
[1:23] fingers and uh proceed on. So maybe we
[1:27] can change some of those behaviors going
[1:29] forward.
[1:31] These are our goals again after the
[1:34] project goals, you know, improving the
[1:35] safety and mobility for all users,
[1:37] improving traffic operations,
[1:40] and improving those connections between
[1:42] residential and commercial areas. Then
[1:45] the schedule there is listed again on
[1:46] the bottom. And we've talked at this
[1:48] meeting of continuing to hold to that
[1:51] date for this year, but we got challenge
[1:54] with the west butments of the Verdon
[1:56] Avenue bridge, which we'll discuss and
[1:58] got a slight update in that. And if
[2:01] people aren't aware, this is the project
[2:03] area west of Interlockan Boulevard on
[2:06] Vernon Avenue all the way over to near
[2:10] city hall by Graange Road and 50th
[2:12] Street. So this is the project area. The
[2:15] orange are the two big bridges that take
[2:17] the most amount of work for the project
[2:20] and those are moving along right now.
[2:24] Lots of communications. You continue to
[2:25] see press releases
[2:27] whenever we do a major traffic cha
[2:30] change. So, lots of stuff just went out
[2:32] this week on all these different
[2:34] methods. Continue to have these
[2:36] bi-weekly meetings. You can sign up for
[2:37] the email updates. Go to the better
[2:39] together website. Uh the map on the
[2:42] bottom is the new information and I'll
[2:45] get into that a little bit, but that is
[2:47] the new map for
[2:49] Monday. So starting Monday, the onramp
[2:53] to northbound high 100 from 50th Street
[2:57] will be closed. So there will be no
[3:00] access to northbound 100 from either
[3:04] Graange Road or 50th Street. and we'll
[3:06] show you that a little more detail, but
[3:09] that's the major traffic change for next
[3:11] week. We know it's going to be
[3:12] challenging, people finding their new
[3:14] routes and we'll continue to monitor
[3:17] traffic and see if we need to add
[3:19] signage, speed display signs, other
[3:22] things along those frontage roads
[3:25] heading to the south because there is a
[3:27] on-ramp from Benton Avenue. So, the
[3:30] local detour is using the east and west
[3:33] frontage roads.
[3:35] uh sign detour. The more regional detour
[3:38] is getting onto southbound 100,
[3:42] taking the eastbound 62 exit and then
[3:45] immediately taking the northbound high
[3:47] 100 exit to get on northbound highway
[3:50] 100.
[3:53] Other activities, so interlocking in
[3:56] Vernon, if you've seen it, it is
[3:58] continues to be free flowing there.
[4:00] That's working rather well to have that
[4:02] traffic pushed to the south and east.
[4:05] Thus Young Lane lane continues to be
[4:07] closed near Edina liquor store. Those
[4:10] are the lane shifts we've been doing for
[4:12] underground utility work. And then
[4:14] within that area where the traffic is
[4:16] flowing today, you'll see that curb and
[4:18] sidewalk and paving. Some of those areas
[4:21] are complete. At least the first layers
[4:24] of paving is complete. Um, and then
[4:28] they'll start to work on that other
[4:29] corner on the caribou side when the pipe
[4:32] work is done in that area. So, starting
[4:35] to piece it together. The exception is
[4:37] the median that's west on Vernon. We're
[4:39] going to leave the median out in case we
[4:41] need to do lane shifts as they build the
[4:43] west abutment of the Vernon Avenue
[4:45] bridge. They might need a little bit
[4:46] more space there. So, uh, but they're
[4:49] trying to get done as much as they can
[4:50] now and reopen as much as they can.
[4:55] So, the big thing we've been talking
[4:57] about the last few meetings is this
[4:58] Excel power line that was in a different
[5:00] location horizontally and vertically
[5:02] circled in the picture. It was hit. It
[5:05] was repaired. And then the two agencies
[5:08] CPKC Rail and Excel have been going back
[5:11] and forth having discussions, permits,
[5:13] agreements, all that kind of stuff,
[5:16] figure out when they can move it. So, a
[5:18] permit was submitted by Excel Energy to
[5:21] the railroad
[5:23] to put in a casing pipe and relocate
[5:26] this power line around the bridge
[5:28] foundations. And it is under review by
[5:31] CPKC Rail. We've paid to expedite that
[5:34] review, but we still don't know exactly
[5:37] when that permit's going to be done and
[5:39] hopefully approved. And then Excel has
[5:42] to schedule crews to deenergize that
[5:45] line as our contractor assists with
[5:49] burying that new steel conduit where
[5:51] these lines will be inside of around the
[5:54] bridge foundation. So still got concerns
[5:57] with schedule and ability to catch up.
[6:01] We still have no control because these
[6:03] the energy company Excel and the rail
[6:06] are their own agencies. We don't have uh
[6:09] jurisdiction to force them to expedite
[6:12] their things. We continue to communicate
[6:14] with them every other day. Um and again,
[6:18] we are getting very close to major
[6:20] impacts. So, more to come on that.
[6:24] And then the road closure I mentioned.
[6:25] So, this is a graphic showing that that
[6:27] northbound on-ramp from 50th Street will
[6:29] be closing on Monday, July 28th. We
[6:34] don't have a date when it would open,
[6:36] but for sure to late fall. They're
[6:38] building noise walls, adjusting the
[6:40] ramp, the traffic signals adjacent to
[6:43] the bridge, sidewalks, all that stuff.
[6:46] Uh there is a GIS map on the better
[6:48] together page that shows you that
[6:51] closure and then those detours that I
[6:53] explained earlier, the local detours at
[6:55] Benton and the larger detour down the
[6:58] Highway 62.
[7:01] Preview. At some point, we're going to
[7:03] need to close the southbound off-ramp
[7:06] from 100. So, it's the left X out on
[7:10] this graphic. We don't have an exact
[7:12] date yet, but there's been some
[7:13] discussions mid to late August.
[7:16] Uh, could be that time. So, here the
[7:20] detour to get into the district at this
[7:22] point would be down. Uh, again, there's
[7:24] kind of two. You can take the exit at
[7:26] Benton Avenue, take frontage roads, or
[7:28] the big sign regional detour would be
[7:30] Highway 62. you come back northbound on
[7:34] 100 and use the Graange Road exit.
[7:37] So, that is still being discussed on
[7:39] when that final ramp closure would occur
[7:43] uh for these two ramps. We still have
[7:44] the Graange exit at some point in the
[7:47] future. Um some other project tenative
[7:50] dates, the Highway 100 bridge
[7:52] construction is going really well. Uh
[7:54] girders, the placement is tenatively
[7:56] scheduled for the week first week of
[7:58] September and this would be night work.
[8:00] So you'd really see that bridge starting
[8:03] to take shape after those have been
[8:05] placed. So very tentative at this point.
[8:08] That's roughly what the contractor's
[8:10] thinking.
[8:12] And then back to some pictures that I
[8:13] share every week. So this is looking
[8:16] east towards the Devanis from
[8:20] the Grand View Liquor side. Upper left
[8:23] was six weeks ago. Bottom left was four
[8:26] weeks ago. So the middle two were kind
[8:29] of that last week, two weeks ago time
[8:32] frame and then the bigger one on the
[8:34] right hand side is from this morning. So
[8:37] that's where that abutment for that
[8:39] bridge that work is happening for the
[8:42] Vernon Avenue bridge
[8:45] down liquor store. We were closed for
[8:47] two weeks while work happened. So the
[8:48] photo on the left is mid midstream when
[8:50] some of the concrete was placed. Just
[8:52] gravel parking lot. Picture on the right
[8:55] is the finished parking lot, curb,
[8:59] uh, pedestrian ramps up to the front
[9:01] door, new pavement, new parking stall,
[9:04] paint, and ADA parking stalls.
[9:09] The one on the left was from a couple
[9:11] weeks ago looking east towards city
[9:15] hall, I think across Highway 100. You
[9:18] can see some of the forms. One on the
[9:20] right is that update. So you can see the
[9:23] center median pier is all the forms have
[9:26] been pulled on that structure. Um work
[9:30] progresses in that area.
[9:34] Picture on the left is Hawthorne Court.
[9:36] The apartments see that that retaining
[9:39] wall continues to be built uh in
[9:42] anticipation of the noise wall that'll
[9:44] be going on top of it. And then the
[9:47] photo on the right is again those
[9:48] apartments from a different angle. And
[9:49] you can see that machine in the center.
[9:52] That's a big horizontal directional
[9:53] drilling machine. They are starting to
[9:56] drill under high 100 for a new water
[10:00] mane connection. We don't have a water
[10:02] mane connection that goes through this
[10:04] area. So this will help make our water
[10:06] distribution system more redundant and
[10:09] increase fire flow in the area. So this
[10:11] is a very large drill underneath high.
[10:15] They'll drill underneath. Eventually,
[10:18] there'll be pipe laid out on 50th Street
[10:19] and then they're going to pull that pipe
[10:21] back to this location on the west side
[10:24] underneath the highway and then make
[10:26] those final connections to the water
[10:27] main system.
[10:31] This is that intersection we talked
[10:32] about. So, you can see Holiday in the
[10:34] background in Caribou. Uh this is the
[10:37] corner where they're wrapping up some of
[10:38] those final utility connections to the
[10:41] storm sewer. You can see where the
[10:43] paving's been completed, where the curbs
[10:45] been completed on the south and the east
[10:47] side of that intersection. Once they get
[10:49] this utility work done, they'll be doing
[10:51] the street paving first the concrete
[10:53] work, curbon gutter, then the sidewalks,
[10:57] and then pave the first layer paving in
[10:59] this area. And then that section will be
[11:03] mostly complete or at least enough to be
[11:05] able to shift traffic around as needed
[11:07] with any future operations related to
[11:09] the Vernon Avenue bridge.
[11:12] And then just some other pictures. The
[11:14] one on the left, you see Devon's in the
[11:16] background. That's some of the forms
[11:18] they use. So just some of the areas
[11:21] where most people will never get to. So
[11:23] you can see the the ladders and the
[11:25] stairs and the grade protection with the
[11:27] plastic, some of those supports. So they
[11:30] fill that with concrete and then they
[11:33] peel those forms away. So you can see on
[11:34] the right hand side, that's a a
[11:36] different area. That's the Highway 100
[11:38] bridge. But you can see the finish there
[11:40] as they pull those forms away uh for the
[11:43] the stuff that'll be visible from high
[11:46] 100 for that bridge. And if you note
[11:49] that texture on that right hand picture,
[11:53] you can see in our in our renderings on
[11:56] the right hand side that same texture on
[11:58] the bridge. So that's where we're where
[12:00] that picture here on the right is
[12:02] located is on the right hand side of the
[12:03] I 100 bridge from these renderings. And
[12:06] again, these are the renderings of the
[12:07] finished product.
[12:09] So with that
[12:12] I'll stop sharing and just see
[12:18] there's any questions here
[12:21] chat.
[12:25] Uh I see Brian's typing right now.
[12:28] Otherwise I don't see any other
[12:29] questions this point. We'll give it a
[12:32] little time. If people got questions
[12:34] just put them in the chat.
[12:36] happy to try to answer those. Now,
[12:40] if you can't get them in there, um, you
[12:43] can always contact me by email or give
[12:45] me a call.
[12:48] Will there be beams for or support
[12:51] underneath the new Vernon Avenue bridge
[12:53] like the old one?
[12:57] Um, they're going to span between, so
[12:59] there won't uh there won't be the same
[13:02] ones like the old bridge.
[13:05] Uh Barb had a question. Can you tell me
[13:07] anything is being done about the traffic
[13:09] control on Eden Avenue? Uh we continue
[13:12] to monitor it. If we need additional
[13:13] support, we're going to ask if we need
[13:15] additional signs. Again, it's behaviors.
[13:17] How do you get people to be more
[13:18] courteous when they're driving through
[13:21] with the closure of those on and off
[13:23] ramps coming in the next Well, one's
[13:26] Monday and then the next is, you know,
[13:29] two to four weeks out. Uh I traffic's
[13:32] going to get worse and then school's
[13:34] going to start and it's going to get
[13:35] worse again. So we just all need to work
[13:37] together on the traffic situation on
[13:41] Eden Avenue.
[13:44] Uh another question, when they work on
[13:47] the west side of the rail bridge, where
[13:50] will they have their work area? Yeah,
[13:52] that's where they might use a portion of
[13:54] that interlock and Vernon intersection
[13:58] and that portion of Gus Young that's
[14:00] been closed. So, they might set up some
[14:02] cranes there and have some work areas in
[14:05] there. They do have a a road, a
[14:07] temporary service road coming from the
[14:10] east side that they can go and cross the
[14:12] rail down low and then go back out. So,
[14:14] they have a couple ways to enter and
[14:17] exit down by the rail with equipment.
[14:20] They got permission to cross the rail
[14:23] north of, you know, closer to Holiday.
[14:26] And then I think they also got
[14:27] permission to come from the south
[14:29] underneath the Gus Young Bridge. So,
[14:31] there's some ways they can get in there
[14:33] and stage equipment.
[14:36] Uh Darren had a question. Is there a
[14:38] covered pathway trail with trees looking
[14:40] towards the north heading to that bridge
[14:43] between Holiday and the railroad? Will
[14:45] that trail still be accessible once the
[14:47] new bridge over the rail? That trail is
[14:49] a is a I call it a bandit path, a cow
[14:52] path. It's not a legal trail. People
[14:56] have just created that trail illegally
[14:58] on railroad property. I wanted to make
[15:00] that an actual city trail and sidewalk.
[15:03] The railroad would not give easements or
[15:06] permission to do that. So whether or not
[15:08] that little pathway continues
[15:11] is up to the railroad if they want to
[15:13] put up fences and keep people out or
[15:15] whether the people just establish a new
[15:17] cow path through there. So that is not a
[15:20] fully accessible, not a formal trail at
[15:23] all.
[15:26] Uh Barb had comments about the traffic
[15:28] on even Eden Avenue. Traffic's gotten
[15:30] worse, not better. There about 200
[15:33] families that have no other option but
[15:35] to get in and out of the neighborhood
[15:36] via Eden. What is the trigger you are
[15:40] looking for as you monitor traffic to
[15:43] get something done to create more
[15:44] controls?
[15:46] Uh we continue to see if people can
[15:48] reasonably get back and forth along that
[15:50] east and west corridor. Uh I'm out there
[15:53] every other day or so watching and
[15:55] seeing where the backups are and we look
[15:58] for opt options. our options are
[16:00] limited. Um, is there other things we
[16:02] can do? That's what we'll have to
[16:04] consider. When the ramps are closed, I
[16:07] think a big portion of traffic that
[16:10] currently uses the off-ramp behind
[16:12] Hillside, when that closes, it's going
[16:14] to change operations again. Is that
[16:15] going to make it any better or worse? We
[16:17] won't know until it happens.
[16:20] So, we understand there's a lot of
[16:22] challenges. We need Eden to support as
[16:25] much traffic as we can because there's
[16:26] just not other options in the area.
[16:29] Eventually, we can start to open up when
[16:32] these ramps get built. Some of those can
[16:34] open back up, but we're just starting to
[16:35] close them. So, we got a lot of work to
[16:37] do before any of those could be
[16:38] reopened.
[16:40] Uh Darren, just curious, when
[16:44] were both the old bridges built? Um, I
[16:48] know the high 100 bridge was a 1973.
[16:53] Vernon, I think, was the 50s, but don't
[16:57] quote me on that. We can get
[17:00] I can officially get that one, but that
[17:01] one was much older um much older and
[17:05] needed to be replaced uh as part of the
[17:08] project.
[17:10] Um is there a visual of what the top of
[17:14] the concrete wall will look like? What
[17:16] color and material?
[17:18] Uh Cheryl asked that question.
[17:22] The wall itself will look a lot like the
[17:24] old wall. It'll just be on top of a
[17:25] retaining wall. So what you see along
[17:28] typical mindot walls, we don't have some
[17:30] rendering showing that um because it's
[17:33] going to be matching what's there that's
[17:35] still in place to the east and north
[17:38] where the removals ended.
[17:42] Uh Darren, so you're saying that the
[17:43] Excel power line they would have to dig
[17:46] underneath Gus Young Bridge and do more
[17:49] tree clearing. No, no more tree
[17:51] clearing. I just mentioned that
[17:52] contractors can drive I think and I'm
[17:55] not this is between them and the
[17:57] railroad but I believe they have access
[18:00] from almost the old public works site
[18:03] along the tracks there just to access
[18:06] some of that area. So at this point
[18:09] um don't anticipate more clearing under
[18:12] there that was all done earlier as part
[18:14] of the project. The real work is where
[18:16] that picture is that I've been showing
[18:18] you of that power line hit. You need to
[18:20] be bury steel conduit in that area. Put
[18:23] the new lines in. Go to a power pole
[18:26] that's over by holiday and reestablish
[18:28] that electrical service.
[18:30] And that's happening when we're in the
[18:33] middle of a summer. Hot days are the
[18:35] highest demand for power. So, we don't
[18:37] want that redundant power line to be out
[18:40] of commission for very long. And we're
[18:43] working with Excel on when that work can
[18:45] be done. As soon as the railroad
[18:48] approves that permit that was submitted
[18:50] by Excel.
[18:54] Great questions. Great questions.
[19:02] Other question. Will Devanis have enough
[19:04] room to reopen their patio after?
[19:08] Yeah. Yep. They will be reopening that
[19:11] patio after the bridge is done. That is
[19:14] correct.
[19:23] Other questions?
[19:25] If not here, send me an email, give me a
[19:29] call. Name and numbers on the better
[19:30] together.org
[19:33] website.
[19:35] Please be patient on Monday when we
[19:37] close another ramp. It's going to be
[19:39] challenging in that area.
[19:42] Um,
[19:44] but we'll get through it.
[19:47] Any other questions?
[19:53] Not seeing any and not seeing any
[19:55] typing. Thanks everybody. We'll post the
[19:58] video, post the PowerPoint slides, and
[20:01] if you got questions, reach out to me.
[20:03] Thank you.