[0:00] So, I guess uh it's just after 11, so I
[0:03] guess we'll get going with this week's
[0:05] update. I'm sharing my screen. So,
[0:08] welcome to the update on the Fernon
[0:10] Avenue and Highway 100 interchange
[0:12] project meeting number 11. And we're
[0:14] recording this and it'll be posted uh
[0:17] later on. So, no Chad this week. He's
[0:20] out on PTO, but my name is Derek
[0:22] Houston. Uh I'm the project
[0:24] representative for this
[0:31] So once again, just want to thank
[0:33] everyone for their patience. Uh we know
[0:35] there's a lot of traffic out there. Just
[0:37] want to remind everyone businesses are
[0:39] open and accessible. Uh there's going to
[0:41] be noise, dust, vibrations, and other
[0:43] construction related stuff going on. And
[0:46] please, please, please stop for
[0:47] pedestrians in the crosswalks and be
[0:49] courteous to fellow drivers.
[0:52] Um, just a reminder, we recommend using
[0:54] the crosswalk at Vernon and Eden instead
[0:56] of the Eden midblock crossing. Could be
[0:59] safer when there's busy traffic.
[1:02] So, project goals and timeline. I go
[1:05] over this every week, but it's always
[1:06] nice to touch on. Uh, improved safety
[1:08] and mobility for all users. uh separate
[1:11] pedestrian routes, improve traffic
[1:13] operations, consolidate Highway 100
[1:16] access points,
[1:18] uh improve connectivity between
[1:20] residential and commercial areas of the
[1:22] district, uh and enhance viability with
[1:27] improved access.
[1:31] So here once again, it's just an
[1:32] overview of the project. We've got over
[1:35] here on the left hand side of the
[1:37] screen, uh this is the Interlock and
[1:38] Vernon intersection. over the railroad
[1:42] uh all the way over 100 ramps associated
[1:45] with that and over towards the green
[1:47] road.
[1:51] And so, right, if you're here, uh,
[1:52] you're with us on some communications.
[1:55] Um, but there's a bunch of other good
[1:56] resources we have like better together.
[1:59] Um,
[2:01] and we've been doing press releases,
[2:03] different email updates,
[2:06] updating our website.
[2:11] So, getting into construction. So, the
[2:14] intersection at Interlockan and Vernon
[2:16] is largely done right now. Uh traffic is
[2:20] flowing about how was described on here.
[2:22] There's they poured back concrete median
[2:25] in this area. Um so right now on Vernon
[2:29] it's separated depending if you're going
[2:31] eastbound or westbound, but it's still a
[2:33] free flowing turn here.
[2:40] And now I know this is an update that
[2:41] lots of people are interested in. Uh the
[2:44] Excel power line update. Um, long story
[2:48] short is there's not a whole lot of
[2:49] progress on this. Um,
[2:52] we know that Excel and the railroad and
[2:55] their permitting are communicating, but
[2:59] there's still no permit to the state.
[3:01] So, it is it is a major impact to the
[3:04] schedule and cost and it's something the
[3:06] project team is very concerned about.
[3:08] Um, so we're trying to keep you in the
[3:10] loop with the best we know and that
[3:12] really is all we know at this point.
[3:14] Great. original agreement was for an
[3:16] overhead line and this is obviously
[3:19] buried here. This was from back in May.
[3:23] So, it's big concern of the project. Um,
[3:27] we're going to keep moving forward and
[3:29] we're still pushing them, doing
[3:30] everything we can, but it's really
[3:31] between Excel and the railroad that we
[3:36] don't have much much we can do there.
[3:42] So, moving on to what our configuration
[3:45] is right now. So, this is uh 28th. We
[3:49] closed the northbound ramp onto 100 off
[3:52] of Graange and it's still like that
[3:54] today. They're working over there and
[3:56] installing noise post, noise wall posts
[3:58] as we speak.
[4:01] [Music]
[4:05] And so, we've been getting a lot of
[4:06] concerns about the traffic over at
[4:09] Benton Avenue. It's uh how a lot of
[4:11] people are getting on to northbound
[4:14] and we've heard your concerns and we are
[4:15] taking steps to address it.
[4:19] The Benton Avenue ramp. So there's a
[4:21] meter right here and we initially two
[4:24] weeks ago we updated it to increase the
[4:26] volume that it would allow onto the
[4:28] freeway.
[4:30] And we just call I talked to MDOT again
[4:32] this morning. They're going to up it
[4:33] again today. And with school starting
[4:36] next week, we're going to continue to
[4:37] monitor and see if we can make any
[4:39] adjustments.
[4:42] Um,
[4:45] I understand that traffic is backing up
[4:47] a lot into the neighborhoods and we are
[4:49] exploring anything we can do
[4:52] over there to to alleviate some of that
[4:54] congestion.
[4:59] Another topic we've been hearing a lot
[5:00] about is the construction on Highway 100
[5:03] between oops, I should say 77th and 50th
[5:06] Street. I just want to iterate that this
[5:09] is a Mindot project and it's not related
[5:11] to our work at the Vernon interchange.
[5:13] Uh they're doing some overhead sign work
[5:16] and they've reduced the lanes. They've
[5:19] taken the center lane out uh northbound
[5:21] and southbound. Part of that is because
[5:23] it's an overhead sign, it's sitting on
[5:25] the median. So in order to get at it
[5:29] and they need to have the lane going
[5:30] both way closed.
[5:33] So this is a mindot project and it's
[5:35] anticipated to last until September 3rd.
[5:38] You can see updates from that from mind
[5:41] 511. Got their website here.
[5:44] And
[5:47] if you want to reach out to Mindot, you
[5:48] can reach out to their public affairs um
[5:50] and they might be able to give you u
[5:53] more updates.
[5:56] Oh, one thing I did want to touch on is
[5:58] I know people are saying, you know, the
[6:00] lane is up, the lane closure is up all
[6:02] the time. Something to keep in mind is
[6:04] that it costs money every time you put
[6:06] it up and take it down. So, I'm sure
[6:08] that's one of their considerations in
[6:10] leaving it up.
[6:15] So this week we've got the 50th and
[6:19] Graange intersection closed right here
[6:21] and it's just for Wednesday through
[6:23] Friday this week. They're doing a big
[6:26] pull for the water man, new water man
[6:28] that's going under Highway 100. So this
[6:32] intersection is closed, but everyone can
[6:34] take the detour on Eden. If you're
[6:36] coming off the northbound ramp, you're
[6:38] just going to be funneled straight over
[6:39] to Eden to get where you're going. And
[6:42] you can see in this picture in the
[6:44] bottom right here, this is actually HDP
[6:48] casing that's laid out all the way past
[6:51] city hall that they're going to pull
[6:53] through with directional bore. So
[6:56] they're going to pull it from this side
[6:57] over all the way on the other side of
[6:59] 100.
[7:01] And that'll go through Friday.
[7:05] It'll be up to normal normal operations
[7:08] after that.
[7:10] City Hall is still accessible. Please
[7:12] use the Eden Avenue or Graange
[7:15] entrances.
[7:20] I think we alluded to this a little bit
[7:21] last time, but we're getting ready to do
[7:23] some more ramp work and ramp closures.
[7:25] Uh so we're still trying to nail down
[7:27] the date with the contractor, but it' be
[7:29] either September 8th or 15th is the
[7:31] tenative plan. That'd be closing the
[7:34] northbound off-ramp and the southbound
[7:36] off-ramp. Um, so we're expecting a lot
[7:40] of traffic to get diverted elsewhere,
[7:42] including Benton Avenue. We're going to
[7:44] continue to monitor that situation, see
[7:46] if there's anything we can do to improve
[7:48] it.
[7:50] Um, one thing to note is that the
[7:53] southbound ramp, southbound on-ramp will
[7:56] remain open.
[7:59] And coming up in the first week of
[8:01] September, there's some night work
[8:03] planned. Uh, they're going to be setting
[8:05] beams for the bridge. So, that's really
[8:06] exciting.
[8:08] Uh they're thinking they'll do
[8:09] northbound first. Uh so it take two
[8:12] nights for them to set the girders and
[8:14] then they'll switch over and do the
[8:16] southbound for another two nights. Uh
[8:18] it's notable that that'll be a regional
[8:21] detour where it'll go instead of going
[8:24] through Highway 100, you'll go 169 to
[8:27] 394 and 62.
[8:34] So going on this week in the area as
[8:37] well. This is not related to our
[8:38] project. It's related to building here
[8:41] at 5100 Eden. It's being redeveloped by
[8:44] the Opus. Um they are putting up jersey
[8:48] barrier and fencing along this side of
[8:50] the street. And so the pedestrian detour
[8:53] is going around and along Arcadia
[8:56] they're adding a temporary sidewalk
[8:58] there. So I saw them this morning. their
[9:00] paving. I'm expecting that to get
[9:02] wrapped up soon.
[9:07] Now, on to some pictures. Uh, it's my
[9:09] favorite part, showing you all the
[9:10] updates. I know upper left here, this
[9:13] was back when they were still forming
[9:16] the footing maybe two months ago. And
[9:20] then down here at the bottom,
[9:22] it's as if it's partially completed. And
[9:25] over at the right here, this was taken
[9:26] yesterday.
[9:28] uh abutment is substantially complete
[9:31] here. Uh they've stripped all their
[9:32] forms. You can see the retaining wall in
[9:34] the background. Got Dean over here on
[9:36] the right. Hawthorne Court over here.
[9:40] They're starting to backfill. You can
[9:42] see this excavator is actually right
[9:44] behind the abupman.
[9:46] Um so it's really coming up.
[9:50] And here's the intersection at Vernon
[9:52] and Interlockan. You can see we still
[9:54] got our free turns going here. Vernon on
[9:57] the left, interlocking on the right,
[9:59] Caribou in the background, and we can
[10:02] see the median here that splitting
[10:04] traffic
[10:09] over here on the left. Just want to
[10:10] highlight the Adana liquor store again.
[10:13] Uh it's back open for business. We've
[10:15] got our bike racks installed there. Hope
[10:18] everyone goes and visits
[10:21] over on the right hand of the side here,
[10:23] right hand side of the page here. Uh
[10:25] this was from two weeks ago at the
[10:27] bottom. This is a retaining wall coming
[10:29] off the wing wall at the east side of
[10:31] 100. You can see Washurn McCree in the
[10:34] background. And this was yesterday up at
[10:36] the top. They've poured the retaining
[10:38] wall. And as of today, they're starting
[10:41] to back fill up here, adding in dirt and
[10:43] compacting it, bringing it up to grade.
[10:47] Very exciting.
[10:51] over here. This is a retaining wall.
[10:53] This is the Hawthorne Court condos.
[10:56] This was several weeks ago when they
[10:59] were still they poured every other and
[11:01] this was yesterday. They poured the last
[11:03] segment of the retaining wall. Uh which
[11:07] is very exciting. They've got on top of
[11:10] this these posts here are dowels for the
[11:12] noise wall. Um
[11:16] so that's steel reinforcement that will
[11:18] go up and beyond. I know you might want
[11:21] to look at these to get a a visual idea
[11:22] of how tall the noise wall will be. Um,
[11:25] just know that the noise wall will go
[11:26] taller than that. Probably about 15
[11:28] feet, give or take, from the top of
[11:31] these these steel dowels.
[11:38] So, here's over at the west abutment of
[11:40] the Highway 100 bridge. This was two
[11:43] weeks ago. Footing for the re um for the
[11:46] retaining wall over here. And then this
[11:49] was yesterday. Fully constructed.
[11:53] Really moving along. They're getting on
[11:55] back fill in here today as well.
[12:02] Here's the railroad bridge again. Uh
[12:05] some of the back fill I was talking
[12:06] about. You can see down at the bottom
[12:09] here where it started and they do it in
[12:12] lifts and compact it, move it all the
[12:13] way up and now they're starting to back
[12:15] fill along that retaining wall along the
[12:17] Hawthorne Court Apartments.
[12:20] Over here is the Debanis
[12:22] and the Holiday Store Caribou background
[12:26] for a little bit of perspective.
[12:31] And here we're looking at the northbound
[12:33] ramp that's closed under construction.
[12:35] Uh you can see they have a stockpile
[12:37] over here on the left side. On the right
[12:39] side they've created this kind of they
[12:41] call it a bench. That's where they're
[12:42] kind of where their work zone is. Uh so
[12:45] they can get their equipment over
[12:48] down here there's a crane and a drigging
[12:52] equipment which is hard to see in this
[12:54] picture but over here you can see this
[12:55] was the first noise wall post that was
[12:57] installed.
[12:59] And so this area it's down by Minihaha
[13:02] Creek and they're going to work their
[13:04] way up towards 50th and city hall.
[13:11] I just wanted to wrap up again. Here's
[13:13] some of the initial renderings and it's
[13:15] really exciting to see that the project
[13:17] looks just like these. It's fun to see
[13:19] it actually coming along. Um
[13:24] so yeah, with that, uh open up to
[13:26] questions. Again, my name is Derek
[13:28] Houston. I've got my email here and
[13:31] we've got our next meeting in two weeks
[13:33] and Chad should be back for that. So,
[13:36] I'll start going through the chat, read
[13:38] any questions. I'll do the best I can.
[13:44] First question I'm seeing uh from
[13:46] Darren, will there be pillars, beams for
[13:49] support underneath the new Vernon Avenue
[13:51] bridge like the old one, or will be
[13:52] abutments, retaining walls on each side?
[13:55] Uh, so I'd say there's abutments on each
[13:58] side. Um, it's a single span. So if
[14:01] we're looking at this bridge here over
[14:03] 100, I think what you're getting at is
[14:06] this thing in the center is called a
[14:07] pier. And on the railroad bridge, there
[14:11] will not be a pier. So it'll just be an
[14:13] abupment on each side and then beams
[14:15] going across that will hold up the deck.
[14:21] Can you tell me anything that's being
[14:23] done about the traffic control on Eden?
[14:28] Uh, well, so I think you're probably
[14:29] getting at backups and traffic there.
[14:32] There's going to be a lot of traffic,
[14:33] unfortunately. Um, it's one of the
[14:36] necessary evils of having construction,
[14:38] but we all want nice roads. Uh, you
[14:40] know, if you have any ideas, we're we're
[14:42] all ears. We're monitoring it and we're
[14:45] going to be taking an extra deep look at
[14:47] it next week with school starting.
[14:55] When they work on the west side of the
[14:56] rail bridge, where will they have the
[14:59] work area?
[15:01] Well, a large part of their area is
[15:04] going to be right on top of the abupment
[15:06] uh next to the holiday center or the
[15:09] holiday gas station.
[15:12] Um, that's why if you walk over there,
[15:14] there is a decent amount of area that's
[15:16] untouched and they left a little bit
[15:17] extra to give themsel room. Um, so that
[15:20] and that closed area of Gus Young is for
[15:22] the contractor to be working in.
[15:28] There is a covered pathway trail with
[15:30] trees looking towards the north leading
[15:32] up to Vernon Avenue Bridge between
[15:34] Holiday Drive and that gorge where the
[15:37] railroad sits below. Will that trail
[15:39] still be accessible once the new bridge
[15:41] over the train tracks is complete? Um,
[15:45] so I believe that's that's the trail I'm
[15:47] thinking of coming up from 49th and kind
[15:50] of Brookside area. Uh, that's not an
[15:53] officially sanctioned trail and that is
[15:55] on railroad property. So that is
[16:00] nothing the city can do about that.
[16:09] Um, from Barb,
[16:12] traffic's getting worse on Eden.
[16:19] What is the trigger you're looking for
[16:20] as you monitor that would indicate
[16:22] something will be done to create more
[16:24] controls?
[16:27] Well, I guess if you have ideas, we're
[16:29] all ears. Um, to an extent, there's only
[16:32] so much we can do. That is a major
[16:33] detour on Eden from Vernon and there's a
[16:37] lot of traffic there with school.
[16:40] So if you have any ideas, we're all
[16:42] ears. Please let us know.
[16:44] Hey Derek,
[16:46] I don't want to interrupt you, but I
[16:49] think you're looking at questions from
[16:51] something.
[16:52] Yeah. Can you hear me?
[16:56] Can you hear me?
[16:57] Anything?
[16:57] Okay, I'll do it in the chat.
[17:00] Just curious. When were you both the old
[17:03] Vernon Avenue and Highway 100 bridges
[17:05] built?
[17:06] I want to say around the 50s, but don't
[17:08] quote me on that.
[17:10] Is he looking at old questions?
[17:12] I think so.
[17:12] Yeah, I think I think he's reading
[17:15] I didn't realize I scrolled too far up
[17:16] in the meeting.
[17:17] Yeah,
[17:17] I'm sorry.
[17:18] It's okay.
[17:18] Okay,
[17:19] that was what I was trying to tell him.
[17:21] Got the first question from today.
[17:22] It was John Crab. Hold
[17:24] with me one second.
[17:32] Okay, believe John Crabtree question
[17:34] from today
[17:39] whether we plan to finish the project in
[17:40] 2025.
[17:42] Uh if we do, what is the drop dead date
[17:44] for an agreement between Excel and CPKC?
[17:48] Um well, I'd say we're going to do
[17:49] everything we can to finish it this
[17:50] year. Uh that's what we want to do.
[17:54] Everybody does contractor included. I
[17:57] wouldn't say we have a drop dead date.
[17:59] Um it's once we have more information,
[18:02] that's when we can really evaluate our
[18:04] options, which unfortunately
[18:06] as I shared earlier, there's not a whole
[18:07] lot of an update.
[18:12] So curious to know, will the Graange
[18:16] Road 50th stop light be removed?
[18:20] And will one be put where highway 100
[18:23] north exists on the 50th?
[18:28] So the light at range will remain and
[18:32] yes I believe one's added at the
[18:34] on-ramps over there.
[18:41] All the traffic shifted onto Eden
[18:43] midepptember.
[18:45] What is the traffic control planet?
[18:54] So, Bill's question about all the
[18:56] traffic on Eden and with school
[18:58] starting. Um, you know, it's something
[19:00] we're going to take a look at with
[19:02] schools starting and with the ramps
[19:04] closed. We're not totally sure how it's
[19:06] going to be impacted. Um, looking into
[19:10] manual control is
[19:12] something we will look at. Uh, but I
[19:14] don't have an answer on if that will
[19:16] happen. Um, we definitely say if you're
[19:19] traveling in the area, give yourself
[19:21] extra time and expect there to be
[19:22] traffic and please be patient.
[19:32] Can the city provide marketing promotion
[19:34] efforts to encourage people to patronize
[19:36] local businesses despite all the
[19:38] construction going on?
[19:41] Um, that's something I can bring up with
[19:43] Chad and other members of the city. Um,
[19:47] but I don't have an answer for that
[19:48] right now.
[19:52] Yeah, we can look at some of the
[19:54] roundabout controls too with the
[19:55] traffic.
[20:03] So, yes, Roy's asking about drop dead
[20:07] date and when the contract how much time
[20:09] the contractor would need. Um, right.
[20:12] There's a lot of options though. it's
[20:16] asking the contractor to work more hours
[20:18] or different winter conditions. Um, but
[20:21] it's something we really don't want to
[20:23] hypothesize about this far in advance um
[20:26] without with all the unknowns kind of
[20:28] getting the buggy in front of the horse.
[20:35] All really great questions.
[20:41] Give a few more minutes. If anyone's got
[20:44] any other questions, put them in the
[20:45] chat.
[20:47] Thanks, Bill. Yep. We enjoy these
[20:49] updates, too. It's fun getting all the
[20:51] progress out to everyone,
[20:53] keeping everyone in the loop.
[21:00] All righty. So, I guess with that, not
[21:01] seeing any other questions.
[21:04] Feel free to reach out to me or or Chad
[21:06] with any other questions. He's on PTO
[21:08] for this week and next week. Uh, but
[21:11] we're happy to help and answer any
[21:13] questions you have. So, thanks everyone.