RecordingTranscript available11:08
Nov. 13, 2025 Highway 100 Interchange Project Bi-Weekly Presentation
Edina City CouncilFriday, November 21, 2025
Watch on original sourceDocument Analysis
Analyze the transcript to extract topics, key quotes, people, and more — then generate focused stories for any topic.
Transcript
[0:00] Vernon Avenue and Highway 100
[0:02] interchange project update. This is
[0:04] meeting number 17.
[0:07] This will be our last meeting of the
[0:08] year for these virtual meetings and then
[0:12] we'll determine over the winter if we
[0:13] continue these next year and if we do
[0:16] we'll make updates to the better
[0:17] together page and let people know. Just
[0:20] a reminder that we are recording
[0:22] presentation is going to be recorded and
[0:24] then we post it to the better together
[0:26] page
[0:28] very soon after. I also post all the
[0:30] slides from the meeting. So, meeting 17,
[0:33] last one for this year, uh, November 13,
[0:37] 2025. I am Chad Milner, engineering
[0:39] director.
[0:43] And I think the big shout out is just
[0:46] thank you. Thank you for the patience.
[0:48] Uh, and we'll get into some big project
[0:50] updates here, what it looks like
[0:53] starting Saturday morning versus in
[0:56] 2026. But just a big thank you for
[0:59] attending these meetings and being part
[1:01] of our project.
[1:03] Our goals, which we talk about every
[1:05] time, improve safety, mobility of all
[1:07] users, create new separated pedestrian
[1:10] routes, improve traffic operations,
[1:12] consolidate those access points. You're
[1:14] going to see that on Saturday morning
[1:16] when this facilities opened around
[1:19] Highway 100. Um to name a few of the
[1:22] goals that we have for the project. This
[1:25] is the project again. It it started west
[1:27] of Interlockan Boulevard on Vernon
[1:29] Avenue.
[1:31] Had two bridges. One is at the CP
[1:35] Railroad junction with Vernon Avenue,
[1:37] that bridge. The other bridge is over
[1:39] Highway 100 and the on andoff ramps and
[1:42] it ends just west of Graange Road on the
[1:46] east side of Highway 100.
[1:50] We have been communicating in many, many
[1:52] methods. So, thank you for receiving
[1:54] those, participating. Again, the best
[1:57] area to get future updates is the better
[1:59] together.org
[2:02] backernonhire
[2:04] 100. Again, this is the last bi-weekly
[2:07] virtual meeting that we'll have this
[2:09] year and then we'll think about next
[2:11] year going forward.
[2:15] What did we tell you in September, early
[2:17] September, we said that on stage four,
[2:20] we're going to close all the off-ramps
[2:22] on and off ramps to Highway 100. And we
[2:25] said that we were going to close those
[2:26] until mid November. And we are indeed
[2:30] going to reopen those Saturday morning,
[2:33] Friday night into Saturday morning this
[2:36] week. So, we met that promise or at
[2:39] least a big portion of the project with
[2:41] the Highway 100 bridge and the on and
[2:43] off ramp. So starting Saturday morning,
[2:45] you will be able to use the bridge. You
[2:48] can see arrows that were
[2:51] added to the graphic. So if you're
[2:54] coming southbound on 100 and you take
[2:56] the exit ramp, there'll be a stop sign
[2:59] at the top, you can go straight through
[3:01] the intersection and loop around Hilltop
[3:03] to get Arcadia Avenue. You can take a
[3:06] left and head towards the 50th and
[3:08] France district
[3:10] or you can get back on the highway.
[3:12] You're heading northbound Highway 100.
[3:14] You can take the new exit alignment here
[3:17] and you can take a right heading towards
[3:19] City Hall and 50th and France district
[3:22] or left and that'll send you onto that
[3:25] on-ramp where I assume you'll want to
[3:27] take the hilltop exit to get to Arcadia
[3:30] Avenue. And then what we told you last
[3:32] week is we didn't or two weeks ago that
[3:35] there was an opportunity that this
[3:38] northbound onramp to 100 was not going
[3:42] to be open. It will also be opened.
[3:44] There is work that needs to be done with
[3:46] the noise while planking contractor can
[3:49] do some of that work under traffic.
[3:51] There's a portion towards the end of
[3:54] that ramp where it gets very narrow and
[3:56] they are coming up with options on how
[3:58] to do that work and also detail if
[4:01] there's going to be traffic impacts at
[4:03] that time. So everything to the
[4:06] basically the east of Arcadia Avenue
[4:08] will be open Saturday morning. Stop
[4:11] signs are going to be the traffic
[4:13] control to start and then traffic
[4:16] signals will be continued to be placed
[4:19] the power all that stuff over the next
[4:23] uh few weeks to a couple months
[4:25] depending on the power needed to supply
[4:28] those traffic signals
[4:31] west of Arcadia Avenue at the big X that
[4:33] will be closed for the winter and then
[4:37] the intersection of Interlockan
[4:39] Boulevard, Gus Young, and Vernon Avenue
[4:42] on the very west side of the project.
[4:45] Eventually, that intersection is going
[4:47] to be open so people can access from
[4:49] Interlock and right to Gus Young Lane
[4:51] and access many of those businesses
[4:53] within Grand View near Dean's, the
[4:56] Starbucks, and some of the other
[4:59] businesses in that area.
[5:02] I look for Saturday morning opening the
[5:04] on andoff ramps making it much easier to
[5:06] access 50th and France and the Grand
[5:08] View District.
[5:11] Uh Vernon Avenue bridge, we've talked
[5:13] about the delays there, but work has
[5:15] started on that west abupment. Ames will
[5:18] continue to work as weather allows.
[5:21] Uh the operations will stop until spring
[5:23] pending weather. I already mentioned Gus
[5:26] Young will reopen that with a temporary
[5:28] signal is what the plan is at this
[5:30] point. The new bridge is estimated to be
[5:33] complete in midsummer and the cost
[5:35] impacts are still unknown. So two weeks
[5:37] ago I showed you the picture in the
[5:39] bottom bottom left. They were forming a
[5:42] bunch of stuff. Picture on the top right
[5:45] is what it looked like yesterday. So
[5:46] they got a lot of that poured. They have
[5:49] a big pore plan for tomorrow to finish
[5:51] the abupment.
[5:53] After it gets enough strength, they can
[5:55] start back filling up to a point where
[5:58] they build retaining walls on each side
[6:00] and the foundations for those retaining
[6:01] walls. We'd really like and if weather
[6:04] allows to get the foundations for the
[6:06] retaining walls in and a portion of this
[6:09] backfilled before a big freeze up so
[6:13] then they could place the beams across.
[6:16] uh this winter at some point. So once
[6:19] the beams are crossed, then they could
[6:21] really start operations without load
[6:23] restrictions next spring to start to
[6:26] form up the forms to pour the deck. So
[6:30] there's a great opportunity if think if
[6:32] they can get that far with weather would
[6:34] really expedite the operations next
[6:38] spring and they won't be impacted by
[6:40] load restrictions or less impacted.
[6:44] Uh what else is going on? So, the noise
[6:46] wall planks at multiple locations, still
[6:48] an unknown schedule. Those will start
[6:51] going up along Vernon in that northbound
[6:54] on-ramp at some point. Still don't know.
[6:56] The materials haven't showed up. Ames
[6:59] will do site cleanup uh as they're doing
[7:01] now, especially where the road's going
[7:03] to be reopened on Saturday. So, that is
[7:06] happening. Uh they're going to continue
[7:08] to work again trying to build enough to
[7:10] place those beams either now or over the
[7:12] winter to avoid those load restrictions
[7:16] in the spring. And the contractor or
[7:19] Ames will continue to use
[7:22] the old public work site 5146 Eden
[7:25] Avenue as a stockpile area over the
[7:27] winter. They will tidy it up, clean it
[7:30] up, but there will be equipment and
[7:31] materials stored stockpiled there over
[7:34] the winter.
[7:36] Then some pictures. So this is a picture
[7:38] of Interlock and Vernon. You can see the
[7:41] new crosswalk markings are there and see
[7:44] the signal pole base ready for the
[7:46] signal when that comes. Um and the final
[7:50] paving is complete basically through
[7:52] this intersection.
[7:55] Picture on the left is looking east
[7:57] towards the new bridge. You can see the
[7:59] turn lane markings, pavement markings,
[8:02] light poles are installed, sidewalks are
[8:04] done. a lot of the stuff ready to get
[8:07] open to traffic is complete. Picture on
[8:11] the right, uh, we planted three trees on
[8:14] the median on the east side of the
[8:15] bridge on the 50th street side. So,
[8:17] those trees went in yesterday. You can
[8:20] see the pavement markings are done,
[8:22] light poles, um, and a few of that
[8:25] miscellaneous stuff is still happening.
[8:28] Picture on the left is eastbound with
[8:31] the two new left turn lanes on to
[8:35] northbound Highway 100. So the pavement
[8:37] markings, the arrows, that's done. And
[8:41] the picture on the right is looking back
[8:43] down the new on-ramp alignment. So
[8:46] you're looking south, which would be the
[8:49] northbound off-ramp. So you can see the
[8:52] lane designations, the new crosswalks.
[8:55] Um, can't quite see the push button
[8:59] thing. That's not up yet. Those will be
[9:01] installed with the signals, new light
[9:03] poles, but this is something, this will
[9:06] be the new offramp that'll be open on
[9:08] Saturday morning.
[9:11] And then we want to compare the
[9:12] rendering on the left is something we've
[9:14] been showing you the whole time. So, the
[9:16] railings, the new pad crossings,
[9:18] crosswalks, pedestrian push buttons,
[9:22] median turn lanes, and this is
[9:24] approximate location of that yesterday.
[9:27] Still a lot of equipment, but you can
[9:28] see the crosswalks,
[9:30] ped ramp, the light pole. Like I
[9:33] mentioned, the push button isn't in yet.
[9:35] See the medians, turn lanes. So, it's
[9:38] looking very similar to the renderings
[9:40] that were completed a long time ago. And
[9:44] then similar to the rendering that down
[9:46] on the highway what the bridge will look
[9:47] like. Note that the forms are still need
[9:50] to be stripped from the bridge. But you
[9:52] can see the finish on this side matches
[9:55] the finish
[9:57] adjacent on the rendering. Various two
[10:00] light poles. There's the two light poles
[10:02] that were shown in the rendering. Kind
[10:04] of the feel for that structure. So we
[10:07] are right there matching those
[10:10] renderings with the actual construction.
[10:14] And with that, I'll stop sharing. Again,
[10:16] if there's questions, please put it in
[10:17] the chat. There's my email if you wanted
[10:19] to email me separately.
[10:22] Let me get out of the PowerPoint and
[10:25] check the chat.
[10:28] So, if you got any questions, please
[10:30] type it into the chat and I can help
[10:32] answer those at this time.
[10:35] Otherwise, give me a call, send me an
[10:37] email, check the website. New update was
[10:40] just done this morning.
[10:46] Any questions?
[10:56] Okay, I see a lot of people dropping
[10:58] off. So, if you got specific questions,
[10:59] send me an email. Appreciate your
[11:01] patience with the project. And we'll
[11:03] post these details
[11:05] uh later this week. Thanks, everybody.