Oct. 16, 2025 Highway 100 Interchange Project Bi-Weekly Presentation
Edina City CouncilFriday, October 17, 2025
Watch on original sourceDocument Analysis
Analyze the transcript to extract topics, key quotes, people, and more — then generate focused stories for any topic.
Transcript
[0:00] Okay, we'll get started. Good morning
[0:03] everybody.
[0:04] It is update meeting number 15. Just a
[0:10] reminder that we are recording these and
[0:13] we'll post them to the website after the
[0:15] meeting and the slides will be posted to
[0:17] the website. So, meeting number 15,
[0:20] we're recording October 16th, 2025 for
[0:23] the Vernon Avenue and Highway 100
[0:25] interchange project. Again, thank you
[0:28] for your patience. Businesses are open
[0:30] and accessible. There continues to be
[0:32] noise,
[0:34] dust, vibrations, and other construction
[0:37] related stuff. Be safe. Stuffer
[0:40] pedestrians and crosswalks. Be courteous
[0:42] to fellow drivers. Those mini
[0:44] roundabouts get very busy, especially
[0:46] during school pickup and drop off times.
[0:50] And again, there's some various midblock
[0:53] crossings and other crosswalks within
[0:55] the area. So,
[0:58] use the ones you feel most comfortable
[1:00] using with the increased traffic along
[1:03] Eden Avenue.
[1:06] Goals of the project, improve safety and
[1:09] mobility of all users, create these new
[1:11] separated pedestrian routes, improve
[1:13] traffic operations, consolidate access
[1:16] points on a 100, and improve
[1:19] connectivity and limit construction
[1:21] impacts by merging county and city
[1:24] projects into one.
[1:27] And again, we're all familiar with this,
[1:28] but this is the project area. Starts
[1:30] west of Interlockan Boulevard. Includes
[1:33] the Interlock and Vernon Gus Young
[1:35] interchange.
[1:37] Then the Vernon Avenue bridge over CPKC
[1:41] rail. Continuing to the east, new
[1:45] intersections on each side of Highway
[1:47] 100 with new traffic signals.
[1:50] the new bridge over Highway 100 that
[1:53] will carry Vernon and 50th Street. And
[1:56] then on the east side, it's going to tie
[1:57] into the work that the city did last
[1:59] year on 50th near Graange with a new
[2:03] aligned off-ramp of Highway 100. Instead
[2:07] of exiting on the Graange, you will now
[2:09] exit on 50th Street.
[2:14] We've been communicating in many
[2:16] different methods throughout this
[2:18] project and we will continue to do that
[2:21] through this fall and next year when we
[2:25] start talking about schedule here but
[2:26] better together website is the best
[2:30] location for project updates for
[2:32] documents for maps those sorts of
[2:34] things. So again check it out. We have a
[2:37] couple more bi-weekly meetings coming up
[2:40] in two and four weeks.
[2:43] um and continue to check out the website
[2:44] for more information.
[2:47] Now, we'll get into specific
[2:48] construction schedule details
[2:52] uh and stuff that's occurred and show
[2:54] some pictures and stuff like that. So,
[2:55] if we look at this interchange at
[2:57] Interlock in Vernon and Gus Young, this
[2:59] has been free flowing for for months
[3:01] now. Um the Gus Young has been closed.
[3:04] They are installing a crane there today
[3:07] I think or yesterday but the crane will
[3:09] be going up to to assist with that west
[3:12] abutment work so that Gus Young needs to
[3:14] stay closed while the crane is located
[3:16] there so there'll be no changes in the
[3:19] short term to this intersection
[3:23] we
[3:24] recently over a month ago closed all the
[3:26] on andoff ramps of a 100 that's created
[3:29] some challenging challenges for people
[3:32] traversing through the district. Uh this
[3:35] is stage four and the project is on
[3:38] schedule to open the Highway 100 bridge
[3:40] and these on andoff ramps mid November.
[3:43] We are currently still on track for mid
[3:46] November to re-establish the access on
[3:49] and off Highway 100 at this location.
[3:54] What is not on schedule, which we've
[3:56] been talking about for months now, is
[3:58] the west abutment of the Vernon Avenue
[4:01] Bridge. So we are looking to the west.
[4:04] So you can see the holiday sign, the
[4:06] caribou in the background. They have
[4:09] started work. The old abutman's finally
[4:12] removed. Excel has relocated the power
[4:14] line that was in the way. Um
[4:19] so we did discuss with the contractor
[4:21] over the last couple weeks, could we
[4:23] accelerate this project and get the
[4:25] bridge open?
[4:27] and they came up with various options
[4:30] and cost and they ranged anywhere from
[4:32] half a million to $2.3 million and even
[4:35] at that high end there was only the
[4:38] ability to get the bridge temporarily
[4:40] open for about six weeks in February and
[4:42] March there's just too much concrete
[4:44] work too much work to do that the
[4:47] acceleration really would not provide
[4:50] much benefit be six weeks on some
[4:52] temporary concrete that would have to be
[4:54] removed be very expensive
[4:57] um and then it would have to be shut
[4:58] down again in April to finish the
[5:01] project. So the city and the county did
[5:03] not see this as a reasonable cost
[5:05] escalation for the benefit cost just did
[5:08] not provide enough benefit. So Ames is
[5:11] going to continue to work through the
[5:13] fall as long as weather allows.
[5:16] They will demobilize
[5:19] equipment on that side and then
[5:21] operations will come back in April
[5:24] pending weather. So again, weather
[5:26] dependent. We're throwing April in
[5:27] there. Uh we'll see how the winter is.
[5:31] We are requiring them to reopen Gus
[5:33] Young Lane once there's room to have
[5:36] safe traffic operations. So there will
[5:38] be a temporary traffic signal installed
[5:41] on that corner to allow people from
[5:43] Interlockan heading south to go straight
[5:46] south to access the Grand View parking
[5:49] ramp to access Dean's the Vernon shops
[5:53] area uh Edina Liquor. So we anticipate
[5:58] that to be late November, early December
[6:00] roughly when we know more dates. Again,
[6:02] it's weather dependent.
[6:05] We will let people know and that will be
[6:07] open through the winter and once they
[6:09] got to remob the crane and other
[6:11] equipment in April roughly then we would
[6:15] most likely have to reclose that
[6:17] intersection to create space for them to
[6:18] work.
[6:20] The new bridge is estimated to be
[6:22] complete in the midsummer next year in
[6:25] 2026.
[6:27] Again, how much they can get done this
[6:29] year is weather dependent. When they can
[6:31] start again in the spring is weather
[6:32] dependent. So, we're estimating just
[6:35] saying midsummer at this point. Once
[6:38] those schedules are more locked in next
[6:40] April, we would have much better dates
[6:44] to share with the public. Uh, and we
[6:46] will do that. The other factor on this
[6:49] whole issue is cost. We don't know what
[6:52] the cost impacts are going to be because
[6:54] we're going to track the contractor's
[6:55] work when they restart up in the spring
[6:57] and see what would be typically part of
[7:00] the normal project and what would not
[7:04] and we'll track those things to
[7:06] determine what kind of cost overruns
[7:08] we're going to have related to this
[7:10] power line issue.
[7:13] Other schedule details. So, the
[7:15] northbound
[7:17] high 100 on-ramp, the noise wall planks
[7:19] are going to be starting very soon. Uh,
[7:22] concrete curb, you saw the curb, and
[7:24] I'll show you some pictures. The new
[7:25] curb along the on and off ramps was
[7:28] completed. The curb along Vernon for a
[7:30] big portion of the project was
[7:32] completed. Tie into Arcadia. They're
[7:35] working on a lot of flat work in the
[7:37] medians and sidewalks and stuff like
[7:39] that. Asphalt paving is scheduled for
[7:42] next week. We did determine there's
[7:45] enough room in the medians uh to plant
[7:48] some trees. So on the west side, on the
[7:50] Vernon Avenue side, there is space to
[7:53] stay out of any sighteline issues with
[7:55] the signals and space for maintenance
[7:58] vehicles for both Mindot and the county
[8:00] and the city, all three parties to do
[8:01] maintenance and still plant 10 trees. So
[8:05] we're going to plant 10 trees in the
[8:06] center median on the Vernon side, the
[8:09] west side. The median on 50th Street is
[8:12] a little tighter and smaller and has
[8:15] some sight line issues that we got to
[8:17] make sure we keep open for that new
[8:19] signal system. We have space to plant
[8:21] three trees on that side. So, in total,
[8:24] there's going to be 13 trees planted
[8:26] within the medians on both sides of the
[8:29] Highway 100 bridge.
[8:31] and sidewalks and signal pole bases,
[8:34] stuff like that continues to be
[8:36] installed uh this week, last week, this
[8:39] week, and the week moving forward.
[8:42] And then just some pictures. So again,
[8:44] the intersection here at Interlockan and
[8:46] Vernon has not changed. It's free
[8:48] flowing uh with traffic.
[8:51] The picture on the left is the east
[8:53] abupman of the Vernon Avenue bridge and
[8:55] it's been in that state for a while. And
[8:58] the picture on the right is progress on
[9:00] the west abupment. The old one's been
[9:01] removed. They're protecting the slope
[9:04] from the rain and they will be in there
[9:06] starting to put up forms to build a
[9:09] mirror image of what you're seeing on
[9:10] the left hand picture on the right side.
[9:15] Some more pictures. Here's a signal base
[9:17] being drilled in to install a traffic
[9:20] signal base. You can see the concrete
[9:21] curb was installed. This is next to
[9:25] Washurn McGravy and that landed stone
[9:27] wall that's there. Picture on the right
[9:30] is looking back towards Hawthorne Court.
[9:33] See the new curb there around Arcadia
[9:35] with Devanis in the back left. So
[9:38] continuing to do the curb and the
[9:39] flatwork.
[9:42] This picture is looking north down the
[9:44] new Highway 100 ramp. So again, the curb
[9:47] was installed and they're getting ready
[9:49] for paving next week. And you can see
[9:51] the noise wall posts have been installed
[9:54] along that corridor and those planks
[9:56] will be starting very soon.
[9:59] and then on the highway 100 bridge
[10:01] itself. So they poured the deck, but now
[10:04] they need to construct the barriers on
[10:08] the sides and the median down the
[10:09] center, the sidewalk. So you're looking
[10:11] at the sidewalk here on the south side
[10:13] of the bridge heading towards city hall.
[10:15] There'll be railings installed on top of
[10:17] that barrier uh as we move forward. So,
[10:20] they're doing some of that additional
[10:22] flat work on top of that bridge as we
[10:25] speak.
[10:27] And again, this is the renderings of
[10:29] what it looks like afterwards. The one
[10:31] on the left is looking towards Hawthorne
[10:33] Court in the background. The new
[10:35] sidewalks and bridge and turn lanes. The
[10:38] one on the right is heading northbound
[10:41] 100. What it would look like from the
[10:42] highway side.
[10:47] With that, I'm going to stop sharing.
[10:49] And if there's any questions, please use
[10:53] the chat
[10:55] and we'll work through those questions
[10:56] as they pop up in the chat. Again, we're
[11:00] going to download
[11:02] um these slides. We're going to download
[11:06] this video to the website. So, if
[11:08] there's someone that wanted to see it
[11:10] and
[11:12] need to see it, they can check it out
[11:14] there. Uh John had a question. Where do
[11:17] you hope to be before work stops for the
[11:19] winter?
[11:20] West bridge abutman poured all beam set.
[11:25] Yeah, right. We the abupment will be
[11:27] poured. Then it becomes is it going to
[11:29] be backfilled with aggregate material
[11:33] with frozen ground? Not frozen ground.
[11:35] We would love to get the beam set. So, I
[11:38] guess we will see if that happens or not
[11:42] based on weather.
[11:44] With the rail bridge incomplete, will we
[11:46] be able to get to Vernon Interlockan
[11:50] to the Highway 100 bridge via Arcadia
[11:52] during the winter? Yes, you'll be able
[11:54] to go northbound Arcadia to eastbound
[12:00] Vernon 50th. So, you can go to the new
[12:02] intersection. You'll be able to go
[12:04] straight and access the new northbound
[12:06] on-ramps by taking a lefthand turn.
[12:09] You'll be able to go straight to 50th in
[12:11] France, and you'll be able to take a
[12:13] right to get on the southbound I 100
[12:17] entrance ramp. So, that's where all the
[12:18] access to I 100's going to occur. So,
[12:21] yes, Arcadia will be open
[12:25] northbound to eastbound and then you'll
[12:28] have those extra movements that you can
[12:29] do off the bridge.
[12:32] Great question.
[12:42] Other questions?
[12:50] Continue to check the website. I just
[12:52] put an update on there
[12:54] as we kind of monitor the contractor's
[12:58] schedules and weather. We'll continue to
[13:00] let you know when operations will cease
[13:04] for the winter
[13:06] um and when they'll demo some of their
[13:09] equipment so we can get that Gus Young
[13:10] back open is the key next step here.
[13:14] Next next step here for traffic
[13:16] operations and opening Gus young lane.
[13:20] So Vernon from 100 to the rail bridge
[13:24] will be paved etc before winter. Yeah,
[13:26] they want to basically draw a line just
[13:29] west of Arcadia
[13:31] in that area. They're going to try to
[13:32] finish everything from there to the
[13:34] east. So, all that has to be left is
[13:36] around the bridge, the Vernon Avenue
[13:38] bridge. The movement that will be
[13:41] similar to what was happening earlier
[13:43] this summer is people taking the exit
[13:45] for southbound 100 will go straight
[13:47] across Vernon and exit onto Arcadia and
[13:51] loop around Hilltop. So there really
[13:55] wasn't a good way to have them take a
[13:57] right on Vernon and then take a left
[13:59] through a median to go southbound on
[14:01] Arcadia. So the access from southbound
[14:05] 100, you'll go straight through loop up
[14:07] to Arcadia and access the district like
[14:10] was happening for most of the summer.
[14:14] Great question. We want to get as much
[14:17] done this year as possible, whether it's
[14:19] sidewalks and paving and street and just
[14:22] have that area around the bridge to
[14:24] complete next year.
[14:27] There's another median to fix on Vernon
[14:30] west of the intersection that was used
[14:32] as a transition between east and
[14:34] westbound. They're planning to do that
[14:36] median and get that work done. They're
[14:39] going to pave course up to the edge of
[14:43] the intersection at Interlockan. So then
[14:46] anything paved on Vernon to the west
[14:49] would be done. And then they'll do some
[14:52] temporary asphalt
[14:54] paving right next to the curb to protect
[14:57] the curb from snowplow operations this
[14:59] winter so we don't damage all that. Then
[15:02] they do the workhorse in that
[15:03] intersection the final top layer next
[15:05] year.
[15:16] Um, there's a question there
[15:19] that I don't understand. So, we'll get
[15:21] back to you on that. Whoever that
[15:23] whoever JJ is,
[15:25] send a note to me, email or on the
[15:28] website, and we'll
[15:31] talk to our bridge designers and see
[15:36] what that question's about.
[15:38] Other
[15:45] questions? Throw in the chat.
[15:49] Will the pavement on Vernon in front of
[15:54] Wells Caribou tire place be patched at
[15:58] some point? Lots of potholes. Oh, great
[16:01] question. So, this project has project
[16:04] limits. Wherever those limits end, it's
[16:06] going to be new pavement to the east.
[16:09] The county
[16:11] owns and operates Vernon, so they have a
[16:14] pavement
[16:16] maintenance project scheduled in 2027, I
[16:21] believe. So, not next year, but the year
[16:24] after. So, it'll be one more year of
[16:25] patching, but then they want to go from
[16:27] our construction limits. I think they
[16:29] want to do a mill and overlay through
[16:31] the district out towards the southwest.
[16:35] So, if there's currently
[16:38] big potholes and stuff like that, then
[16:40] we would make that request with the
[16:42] county to come in and continue to do
[16:44] their patching operations until they can
[16:46] come and do that pavement maintenance
[16:49] operation in I believe it is in 27.
[16:54] So, good questions. The city did some
[16:56] patching here earlier this summer just
[16:58] because we were up in that area.
[17:10] Other questions?
[17:14] Again, check out the website. We'll post
[17:16] this material. I'm available if people
[17:20] have other questions. They can come
[17:21] visit if there's questions. You have a
[17:23] bigger group you want to share some
[17:24] information with. Let me know.
[17:27] Can figure that out.
[17:38] Not seeing any other
[17:41] questions or anybody typing.
[17:45] I think we'll end the meeting now and
[17:47] again we'll post it. Go to the website.
[17:50] You have my email, a phone call if
[17:51] there's other stuff. Oh, there's one
[17:53] last question here.
[17:55] Jennifer had a question. To clarify, if
[17:59] you're driving south on a 100, you will
[18:02] be able to exit again at some point on
[18:04] the 50th. So, if you're driving south on
[18:06] 100, yes, that exit ramp will be open
[18:10] mid November. You'll come up to the new
[18:13] intersection at Vernon next to the new
[18:15] bridge. From there, you could either go
[18:18] straight
[18:20] if you're going to access
[18:22] Devan's, Vernon shops, Jerry's, and
[18:25] you'll take the little loop behind
[18:26] Hilltop and get on the Arcadia and then
[18:29] use Arcadia or Eden to access those
[18:32] businesses. If you come off that exit in
[18:34] Hint Vernon and want to take a left to
[18:36] go to 50th and France, you will be able
[18:38] to go across the new bridge to head
[18:41] towards City Hall or 50th in France. So,
[18:45] yes, southbound exit's going to be
[18:48] reopened. Northbound onramp's going to
[18:50] be reopened. The new northbound off-ramp
[18:53] is going to be open. So, there'll be
[18:55] access there both northbound and
[18:57] southbound from
[18:59] right around that new Highway 100
[19:01] bridge.
[19:04] Uh there's a question if the meeting is
[19:06] about more than the bridge project, can
[19:08] you update us on city street projects?
[19:11] Yeah, Bridget, if there's you have a a
[19:14] neighborhood group or an apartment group
[19:16] that's interested in some citywide
[19:19] project updates, I definitely visit
[19:21] condos and apartments and neighborhood
[19:23] meetings to talk about not only this
[19:25] project but bigger city projects. So, I
[19:27] would ask you to send me an email or
[19:29] give me a call and we can figure out
[19:32] what your need is and whether it's
[19:35] during the day, you know, I've I've met
[19:37] over lunchtime or after hours. So, you
[19:40] let me know, give me a call, send me a
[19:42] note, and if there's a need, we can
[19:44] figure out whether it's me or maybe have
[19:45] questions on different city projects
[19:47] that it might be uh somebody else. Ah,
[19:50] Chowan Park, that'd be me or Aaron or
[19:54] Ben would be available to do that. So,
[19:57] yep, please reach out separately and we
[19:58] can figure that out because we do have
[20:00] planned meetings already for that
[20:02] project moving forward.
[20:07] Will the southbound ramp from Eden
[20:10] Avenue onto Highway 100 remain? Uh we
[20:13] have that scheduled for to be closed. We
[20:15] just don't have a schedule because this
[20:17] project we needed that on-ramp. That's
[20:19] one of the highest crash rates in town.
[20:22] All of our traffic studies have stated
[20:24] we don't need that any longer when these
[20:26] new improvements are done. So the plan
[20:28] is to close that southbound on-ramp from
[20:30] Eden Avenue. I don't know whether
[20:32] that'll be 2026 or 2027.
[20:36] really depends on when this project's
[20:37] over and we can look at the funding and
[20:40] the impacts that this project has on
[20:41] funding will determine when that on-ramp
[20:44] can be closed.
[20:52] Good questions. Thanks for the
[20:54] questions.
[21:02] Now we'll see if that was the last
[21:04] question. So, we'll give it another
[21:05] minute.
[21:07] Thank everybody for their time. Again,
[21:10] we'll post this information. If you have
[21:11] specific questions you didn't get
[21:13] answered, just reach out. Happy to
[21:16] assist
[21:18] with any comments or concerns you have.
[21:23] All right. Thanks everybody. Thanks for
[21:25] joining and let me know if you got
[21:26] additional questions.