RecordingTranscript availableAnalysis ready2:35

Agenda: Edina - Vernon Ave./Highway 100 Construction Begins - Late April 2025

Edina City CouncilFriday, May 16, 2025
Watch on original source

Vernon Avenue and Highway 100 Interchange Project

Public Engagement and Project Communication

Full Document Analysis

Votes (2)

Vernon Avenue and Highway 100 Interchange Project – Contract Award

Scheduled for April 16th City Council meeting; no vote result recorded in transcript.

The City Council is scheduled to award the construction contract at its April 16th meeting. If approved, Phase 1 construction would commence as early as April 21st and conclude by mid-November. The project represents a multi-year collaborative effort between Hennepin County, Minnesota Department of Transportation, and the City of Edina. Key infrastructure components include two new bridges (one over Canadian Pacific Railroad, one over Highway 100), elimination of redundant Highway 100 access ramps, construction of noise walls, and significant pedestrian and bicycle infrastructure enhancements including wide sidewalks and dual turn lanes. Street closures on Vernon Avenue and West 50th Street between Interlockan Boulevard and Graange Road are planned for April 23rd, though Highway 100 on/off ramps will remain operational.

Public Engagement and Project Communication Strategy

No formal vote recorded; communication strategy presented as operational procedure.

The city has established multiple communication channels to keep residents, businesses, and visitors informed throughout the project lifecycle. Email updates are available via subscription at bettertogether.org/veronhwy100. Bi-weekly online project talks are hosted by Milner every other Thursday at 11:00 a.m. until project completion, accessible at edinan.gov/highway talks. These engagement mechanisms are designed to ensure transparency and facilitate community participation.

Notable Quotes (4)

Construction should begin this month on the Vernon Avenue and Highway 100 interchange project, one that will improve safety and mobility throughout the Grand View District.

— Unknown [Timestamp]
Vernon Avenue and Highway 100 Interchange Project – Contract Award

When the project started, it was just a county project, but the city added on to again improve the walking, the biking, and traffic operations within the district.

— Unknown [Timestamp]
Vernon Avenue and Highway 100 Interchange Project – Contract Award

Once the project's complete, you're going to have big wide sidewalks for both bikes and pedestrians for walking and cycling. There's going to be additional dual turn lanes, lefthand turn lanes on both east and westbound 50th in Vernon and a new lefthand turn lane when you're heading westbound to get to Edina Liquor where you usually get backed up if you're making that left-hand turn.

— Unknown [Timestamp]
Vernon Avenue and Highway 100 Interchange Project – Contract Award

Keep up to date by signing up for email project updates at bettertogether.org/veronhwy100. Milner is also hosting online project talks every other Thursday at 11:00 a.m. until the project is complete. Anyone interested in the project, including residents, businesses, and visitors, are welcome to join online at edinan.gov/highway talks.

— Unknown [Timestamp]
Public Engagement and Project Communication Strategy

Ordinances & Resolutions (3)

Vernon Avenue and Highway 100 Interchange ProjectPlan

$28 million infrastructure project including two new bridges, intersection improvements, noise walls, and enhanced pedestrian/bicycle facilities.

bettertogether.org/veronhwy100Other

Email subscription portal for project updates and communication.

edinan.gov/highway talksOther

Online platform for bi-weekly project discussion sessions hosted by Milner.

Transcript