StoryBudget constraints limiting bridge features in Edina's Highway 62 pedestrian bridge replacement projectJune 23, 2025

Edina Bridge Project May Skip Stairs Due to Budget

Meeting date: Jun 23, 2025
Published Aug 5, 2025

The City of Edina's planned pedestrian bridge replacement over Highway 62 will likely not include stairs due to budget constraints, according to a recent city update.

The $6 million in state funding allocated for the new ADA-compliant bridge at Rosland Park covers only basic construction with ramps, Engineering Director Chad Milner said at a city council meeting earlier this month. The project architect Snow Kryik has designed a steel truss bridge clad in wood slats.

We're right at that budget number right now with just a little bit of contingency for those unknown things that we always find during construction," Milner said. "We're still going to get a great product at the end with bridges and ramps and most likely not stairs or buried power lines.

The current bridge, built in the 1960s and owned by the Minnesota Department of Transportation, was closed for most of 2022 after being struck twice by trucks. The structure does not meet Americans with Disabilities Act requirements. Under the replacement plan, the state will transfer ownership and maintenance responsibilities to the city.

Design work is approximately 30 percent complete, allowing the city to begin detailed discussions with MnDOT about construction specifications including height, location and staging. If final approvals are secured this year, the city could begin accepting construction bids in 2026.

Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.

Go deeper on this topic

Research related meeting documents and build a brief — without rewriting the story.

Full analysis

Votes (1)

Update on Pedestrian Bridge Project over Minnesota Highway 62

Project Update and Discussion. No formal vote taken; planning continues towards securing final approvals and obtaining bids for construction in 2026.

The city council reviewed the current status of the pedestrian bridge project, noting the $6 million state funding. Key challenges include budget limitations preventing the inclusion of stairs and the burial of overhead power lines. Emphasis was placed on ensuring ADA-compliant ramps and leveraging architectural design to create an iconic gateway. The city is preparing to discuss specifics like height and cladding with Mindot, with bids for construction expected in 2026 pending final approvals.

Notable Quotes (1)

We're right at that budget number right now with just a little bit of contingency for those unknown things that we always find during construction. Could be soils, could be other construction contingencies that we see. A little bit more expensive than we had liked, but we're still going to get a great product at the end with bridges and ramps and most likely not stairs or buried power lines.

— Chad Milner/Engineering Director
Update on Pedestrian Bridge Project over Minnesota Highway 62

Ordinances & Resolutions (2)

Americans with Disabilities Act (ADA)Other

Federal requirements for accessibility that the new bridge's ramps will meet, and which the old bridge did not.

Project DesignsPlan

Designs for the new pedestrian bridge, featuring a steel truss clad in wood slats, currently 30% complete.

Source document

Was this story helpful?

Other Topics from This Document

  • Pedestrian Bridge Project over Minnesota Highway 62

Want to know when new stories arrive?

Enter your email to receive updates.

We will not use your email for any other purpose. You can unsubscribe at any time.