Edina Council Reviews $28M Interchange Project, Assessing Services Transition
The Edina City Council reviewed progress on the Vernon Avenue and Highway 100 interchange project and discussed transitioning city assessing services to Hennepin County during a work session Tuesday.
The $28.2 million interchange project is set to begin construction in late April after months of delays caused by railroad easement negotiations, according to Director Milner. Ames Construction submitted the winning bid and committed to substantial completion by November 15, 2025, to minimize impacts on holiday shopping in the Grand View and 50th and France districts. The city will hold the contract and seek reimbursement from partners, with funding coming from federal sources ($11.2 million), county contributions ($12.4 million), and city sources ($15.5 million) including bonding, utility funds, and tax increment financing.
The council also examined a proposal from Hennepin County to absorb the city's assessing services at no direct charge. County Administrator David Huff explained the county recently incorporated $5.4 million in assessing costs into its general levy to serve 37 smaller cities and is now offering the same arrangement to larger municipalities. Only Edina and Maple Grove have expressed interest among the eight cities that currently provide their own assessing services.
City Assessor Sheila Stozinger raised concerns about service quality under county management, citing examples of residents needing in-person assistance and the complexity of Edina's high-value properties. She noted Edina generated 114 tax court petitions in 2024 compared to 510 for all 37 cities currently served by the county. The transition would require converting to new computer systems and could affect the specialized knowledge assessors have developed about local neighborhoods and market conditions.
The council requested additional information about service level agreements and customer experience profiles before making a decision. County officials indicated they need responses by May 1 for budget planning purposes, though they suggested the deadline could be flexible. The council will consider both items at their April 16 meeting.
Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.
Other Topics from This Document
Vernon Avenue and Highway 100 Interchange Project Update
Traffic Management and Communication Strategy for Highway 100 Project
Project Funding and State Legislative Request
Transition of City Assessing Services to Hennepin County
Also from this meeting
Want to know when new stories arrive?
Enter your email to receive updates.
We will not use your email for any other purpose. You can unsubscribe at any time.