StoryHighway 100 bridge and ramp reopening timeline and traffic impactsOctober 30, 2025

Highway 100 Bridge, Ramps to Reopen Mid-November

Published Nov 3, 2025

The Highway 100 bridge and on- and off-ramps at Vernon Avenue will reopen in mid-November after being closed since Sept. 15, Engineering Director Chad Milner announced during Thursday's project update meeting.

The reopening marks a major milestone in the Vernon Avenue Highway 100 interchange project, which has created significant traffic challenges in the district for more than two months. Eden Avenue has experienced heavy congestion during school pickup and drop-off times, while Benton Avenue has seen increased traffic volumes.

The bridge will initially operate with stop signs before potentially transitioning to temporary traffic signals, depending on traffic flow. Drivers exiting northbound Highway 100 will be able to turn left or right, while southbound traffic will continue using the loop around Hilltop Restaurant to access Arcadia Avenue due to median installation.

Construction on the Vernon Avenue bridge over the railway has begun with footings poured last week, but work will halt for winter and resume in April 2025. The city plans to install a temporary traffic signal at the Interlocken Boulevard and Gus Young Lane intersection in early December, reopening three of four legs of that intersection.

Final asphalt paving and bridge railing installation are scheduled for next week. The project, which runs from west of Interlocken Boulevard to west of Graange Road, aims to improve safety and mobility while creating separated pedestrian routes. One final bi-weekly meeting is scheduled for Nov. 13 before the city determines next year's communication plan.

Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.

Go deeper on this topic

Research related meeting documents and build a brief — without rewriting the story.

Full analysis

Summary

This was the 16th bi-weekly update meeting for the Vernon Avenue Highway 100 interchange project. Engineering Director Chad Milner provided updates on construction progress, upcoming reopenings, and winter work plans. The major milestone is the mid-November reopening of Highway 100 bridge and on/off ramps after being closed since September 15th. The Vernon Avenue bridge over the railway will not be completed this year and work will resume in April 2025.

Key Highlights

03:03

Highway 100 bridge and ramps reopening mid-November

04:14

Vernon Avenue bridge work delayed until 2025

05:38

Construction schedule and winter operations

11:42

Eden Avenue ramp closure planned for future

13:12

Safety concerns about Eden Avenue ramp

Action Items

Create and post stage 4 traffic map

Responsible: Engineering DepartmentDue: 2025-11-15

Install temporary traffic signal at Interlocken/Gus Young intersection

Responsible: ContractorDue: 2025-12-01

Complete final asphalt paving layer

Responsible: ContractorDue: 2025-11-07

Install railings on Highway 100 bridge

Responsible: ContractorDue: 2025-11-07

Resume Vernon Avenue bridge construction

Responsible: ContractorDue: 2025-04-01

People, Places & Organizations

Chad Milner · PersonVernon Avenue Highway 100 Interchange Project · Infrastructure ProjectHighway 100 · HighwayVernon Avenue · StreetEden Avenue · StreetInterlocken Boulevard · Street50th Street · StreetGus Young Lane · StreetGraange Road · StreetHilltop Restaurant · BusinessHawthorne Apartments · Residential ComplexMDOT · Government Agency

Was this story helpful?

Want to know when new stories arrive?

Enter your email to receive updates.

We will not use your email for any other purpose. You can unsubscribe at any time.