StoryMidyear budget review showing successful implementation of 2025 budget amendmentsAugust 5, 2025

Minneapolis Budget Committee Reviews Midyear Progress on 2025 Spending

Meeting date: Aug 5, 2025
Published Aug 23, 2025

The Minneapolis Budget Committee received updates Monday on dozens of budget amendments and earmarks totaling millions of dollars across city departments, with nearly all items reported as on track or complete.

Chief Operating Officer Margaret Anderson-Kelliher led the midyear review of 2025 budget change items, presenting alongside department heads who detailed progress on hiring, contracting and program implementation. The items included council-directed spending, earmarks and budget amendments enacted in December 2024.

"These change items from 2025 are almost 100% on track," Anderson-Kelliher told the committee, thanking staff teams for their work on implementation.

Major progress was reported across departments. The Office of Community Safety hired positions for police audit compliance and training oversight required under the MPD settlement agreement. The Health Department allocated $4.78 million across lead poisoning prevention, opioid response and climate programs, with 637 school-based clinic visits completed for 74 students. Community Planning and Economic Development managed 31 items totaling over $18 million, including affordable housing programs and business development initiatives.

Public Works reported all 11 budget items on track, including traffic safety cameras scheduled for September deployment and neighborhood traffic calming projects covering 49 locations. The department purchased equipment for unsheltered homelessness response and hired staff for lead service line replacement assistance. Anderson-Kelliher noted that performance metrics for many programs require six to 12 months of data before effectiveness can be measured, with a follow-up memo promised to connect progress to budget goals and objectives.

Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.

Go deeper on this topic

Research related meeting documents and build a brief — without rewriting the story.

Full analysis
  • Potential funding shortfall for 15 firefighters as SAFER grant ends in April 2026.
  • Data gap issues as the administration struggles to provide meaningful 6-month performance metrics for 2025 budget items.
  • Internal confusion over whether BCR funding is one-time or ongoing, impacting contract negotiations.
  • Stalled progress on the 'Safe Working Pilot Project' pending outdoor parking ordinances.
  • Status of the 5th Precinct crime prevention specialist position remains unclear despite budget allocation.

Performance management is a process that needs data... at this point in time, we really need six months to 12 months of data to be able to know if the performance metrics are working.

Margaret Anderson-Kelliher
Performance ManagementExplaining the lack of current data for 2025 budget items.

If you view ELFA's community presentation... MPD be able to audit itself, so you'll see that there were two FTEs for 2025, and then we're asking for two in 2026.

Commissioner Barnette
MPD ComplianceExplaining staffing for audit compliance.
Source document

[0:18] >> GOOD AFTERNOON. I'M EM EMILY KOSKI AND I'M GOING TO BE

[0:23] THE CHAIR OF THE BUDGET COMMITTEE MEETING. I'M GOING TO CALL TO ORDER THE BUDGET MEETING FOR AUGUST 4th, 2025.

[0:29] BEFORE WE BEGIN THE MEETING I HAPPENED TO OFFER A FRIENDLY REMINDER TO ALL MEMBERS, STAFF, AND THE PLU PUBLIC THAT

[0:34] THESE MEETINGS ARE BROADCAST LIVE TO ENABLE GREATER PUBLIC PARTICIPATION. THESE BROADCASTS INCLUDE REALTIME CAPTIONING AS A

[0:41] FURTHER METHOD TO INCREASE THE ACCESSIBILITYF OUR MEETINGS TO THE COMMUNITY. THEREFORE, ALL SPEAKERS NEED TO BE MINDFUL OF

[0:46] THE RATE OF THEIR SPEECH SO THAT OUR CAPTIONERS CAN FULLY CAPTURE AND TRANSCRIBE ALL COMMENTS FOR THE BROADCAST. WE ASK ALL

[0:53] SPEAKERS TO MODERATE THE SPEED AND CLARITY OF THEIR COMMENTS. AT THIS TIME, I'LL ASK THE CLERK TO CALL THE ROLL TO VERIFY THE

[0:59] PRESENCE OF A QUORUM. >> COUNCILMEMBER PAYNE. >> PRESENT. >> WONSLEY IS ABSENT.

[1:06] RAINVILLE. >> PRESENT. >> VETAW. >> PRESENT. >> ELLISON IS ABSENT. OSMAN IS

[1:13] ABSENT. CASHMAN IS ABSENT. JENKINS IS ABSENT. CHAVEZ.

[1:20] >> PRESENT. >> CHOWDHURY. >> PRESENT. >> PALMISANO.

[1:26] >> PRESENT. >> VICE CHAIR KOSKI. >> PRESENT. >> AND CHAIR CHUGHTAI IS ABSENT. THERE ARE SEVEN MEMBERS PRESENT.

[1:33] >> LET THE REPORT REFLECT THAT WE HAVE A QUOR -- RECORD REFLECT THAT WE HAVE A QUORUM. I'LL ALSO REMIND MY COLLEAGUES --

[1:39] I'LL ALSO -- REMIND MY COLLEAGUES THAT WE'RE USING SPEAKER MANAGEMENT TODAY, SO PLEASE MAKE SURE THAT YOU SIGN

[1:47] IN. THE SINGLE ITEM ON OUR AGENDA TODAY IS AN UPDATE REGARDING MUD YEAR CHANGE ITEMS TO THE BUDGET. THERE WILL BE

[1:53] SEVERAL STAFF MEMBERS SPEAKING, BUT I WILL INVITE OUR COO

[2:02] MARGARET ANDERSON-KELLIHER TO START US OFF. WELCOME. >> GOOD AFTERNOON, VICE CHAIR KOSKI, MEMBERS OF THE COMMITTEE.

[2:08] IT'S GOOD TO BE WITH YOU. THESE ITEMS ARE ITEMS FROM 2025 THAT

[2:20] WERE IN THE BUDGET. THEY ARE EARMARKS, THEY ARE COUNCIL

[2:25] DIRECTED SPENDING IN SOME CASES. WE HAVE NOTED PARTICULARLY THE EARMARKS IN THIS. I JUST WANTED TO NOTE THAT. VICE CHAIR KOSKI,

[2:30] LATE ON FRIDAY, YOU ASKED ABOUT METRICS, SO I THOUGHT IT WOULD BEGOOD TO GET A COUPLE THINGS

[2:36] OUT OF THE WAY ABOUT THE METRICS AND PERFORMANCE MANAGEMENT OF THESE PARTICULAR ITEMS. SO

[2:44] PERFORMANCE MANAGEMENT IS A PROCESS THAT NEEDS DATA TO GO WITH US, AND WHAT YOU'RE GOG -- WITH IT, AND WHAT YOU'RE GOING

[2:50] TO SEE IN THIS PRESENTATION IS A STATUS UPDATE ON THESE 2025 BUDGETED ITEMS. AS EVERYONE CAN

[2:57] REMEMBER, THE BUDGET WAS ENACTED IN DECEMBER OF LAST YEAR, SO IN

[3:04] MANY CASES, THERE IS NO DATA AVAILABLE YET FOR THESE ITEMS. WE WILL TRY TO NOTE THAT FOR YOU

[3:10] WHERE THERE IS DATA AVAILABLE AND METRICS AVAILABLE THAT GIVE

[3:15] US SOME IDEA, BUT WE WILL FOLLOW UP WITH A MEMO ON THAT SO THAT

[3:20] THE COUNCILMEMBERS CAN HAVE THAT. AT THIS POINT IN TIME, WE

[3:26] REALLY NEED SIX MONTHS TO 12 MONTHS OF DATA TO BE ABLE TO

[3:31] KNOW IF THE PERFORMANCE METRICS ARE WORKING. NOW THERE ARE OTHER PERFORMANCE METRICS THAT

[3:37] ARE AVAILABLE TO THE PUBLIC, TO ALL OF YOU AS WELL. AND RIGHT NOW ONE OF THE BEST PLACES TO

[3:43] LOOK AT THE MAYORAL DASHBOARD OF PRIORITIES THAT HAS ON IT ALREADY COMMUNITY SAFETY,

[3:48] UNSHELTERED HOMELESSNESS RESPONSES, CLIMATE ACTION,

[3:55] RECRUITMENT, OPIOID RESPONSE, AND ECONOMIC RECOVERY. AND THERE'S A NUMBER OF MEASURES OUT ON THAT. SOME OF THOSE

[4:00] CORRESPOND TO THESE ITEMS, BUT THESE ITEMS ARE DISTINCT FROM LAST YEAR'S BUDGET. AND JUST

[4:10] WANTED TO MAKE SURE EVERYONE'S AWARE OF THAT. SO TODAY'S ORDER IS THE CITY ATTORNEY'S OFFICE, AND I'M ACTUALLY GOING TO TAKE

[4:15] THAT SLIDE BECAUSE THE CITY ATTORNEY HAD NO CHANGES TO THEIR BUDGET LAST YEAR. AND THEN

[4:23] COMMISSIONER BARNETTE WILL COME UP AND SPEAK TO YOU ABOUT THE OFFICE OF COMMUNITY SAFETY. I WILL THEN RETURN AND TALK ABOUT

[4:29] A NUMBER OF ITEMS THAT HAD EITHER ONE TO FOUR OR FIVE

[4:36] CHANGES SM. AND THEN I'LL BE JOINED BY MY COLLEAGUES

[4:43] COMMISSIONER CHAPLAIN SWEGZ DEPUTY CEO HJELLE SINCE DIRECTOR

[4:49] HANSEN IS ON A MUCH EARNED VACATION, AND THEN DIRECTOR SEXTON IS ALSO HERE. SINCE THOSE THREE ITEM AREAS, HEALTH,

[4:58] AS WELL AS CPED AND THE PW LINE

[5:04] ITEM, PUBLIC WORKS LINE ITEM HAVE MANY, MANY ITEMS, WE ASK THE DEPARTMENT HEADS TO BE HERE

[5:09] TO PRESENT IN PERSON. SO WE WILL GET STARTED. AGAIN, THE

[5:18] CITY ATTORNEY HAD NO CHANGES TO THEIR BUDGET OTHER THAN WHAT WAS

[5:25] RECOMMENDED. IT WAS RELATIVELY FLAT BUDGET FOR THE CITY ATTORNEY'S OFFICE. NO INCREASES. AND I'M GOING TO

[5:30] TURN THIS OVER TO MY COLLEAGUE, COMMISSIONER BARNETTE.

[5:38] >> WELCOME, COMMISSIONER. >> THANK YOU, CHAIR KOSKI AND

[5:43] OTHER COUNCILMEMBERS. GOOD

[5:48] AFTERNOON. I WILL START WITH

[5:57] EMERGENCY MANAGEMENT. AS YOU CAN SEE, THERE ARE NO BUDGET ITEMS THERE FOR EMERGENCY

[6:04] MAPPING LT -- MANAGEMENT AND THAT IS THE SAME FOR EMERGENCY COMMUNICATIONS CENTER, 9-1-1 AS

[6:11] WELL. POLICE OF COURSE HAVE

[6:17] SEVERAL ITEMS THAT I WILL GO THROUGH. AS YOU KNOW, THE AUDIT COMPLIANCE CAPACITY IS IMPORTANT

[6:24] FOR THE SETTLEMENT AGREEMENT. IF YOU VIEWED ELEFA'S COMMUNITY

[6:31] PRESENTATION OR WERE PRESENT FOR THAT PRESENTATION, THERE THEY

[6:38] GOT A QUESTION ABOUT AUDIT AND THE IMPORTANCE OF IT IS THAT MPD BE ABLE TO AUDIT ITSELF, SO

[6:43] YOU'LL SEE THAT THERE WERE TWO FTEs FOR 2025, AND THEN WE'RE

[6:53] ASKING FOR TWO IN 2026. THOSE TWO IN 2025 ARE COMPLIANCE

[7:00] SPECIALISTS. THE NEXT BOX DOWN, THE FIVE FTEs THERE IS FOR THE

[7:11] CURRICULUM INSTRUCTION ANALYSIS EVALUATION AND MONITORING OF OUR TRAINING COMPLIANCE. OUT OF

[7:16] THOSE FIVE POSITIONS, WE'VE HIRED ONE CURRICULUM DEVELOPMENT

[7:23] SPECIALIST, THREE CIVILIAN INSTRUCTORS, THE JAQ IS COMPLETED, AND WE'RE WORKING ON

[7:30] AN LOA WITH THE UNION. ONE OTHER POSITION, THE TRAINING

[7:36] COORDINATOR POSITION, THE JAQ HAS BEEN COMPLETED, AND THE POSTING HAS BEEN UP SINCE

[7:43] JULY 21st ON THAT ONE. AS FAR AS THE NEXT ITEM, THE TWO FTEs

[7:49] THERE HAVE BEEN HIRED. THOSE WERE TO BACKFILL TWO CIVILIAN

[7:56] INVESTIGATOR POSITIONS, AND THEY HAVE BEEN HIRED. ONTO THE NEXT

[8:04] SLIDE. AS YOU KNOW, IN 2025 THE CITY TOOK AN APPROACH SIMILAR TO

[8:10] HENNEPIN COUNTY TO REPLICATE

[8:15] SOME OF THE GOOD THINGS THEY DID IN RESPONSE TO UNSHELTERED RESIDENTS, AND SO THE POLICE

[8:23] DEPARTMENT GOT SOME MONEY I BELIEVE ALSO REC SERVICES AND

[8:28] PUBLIC WORKS IN THEIR PUBLIC SOLID WASTE GOT SOME IN

[8:34] COORDINATION TO OUR RESPONSE HERE, AND THE MONEY THAT WAS USED IN MPD WAS TO GET SOME

[8:42] MOBILE LIGHTS AND CAMERAS THAT ARE NOW AVAILABLE TO MPD. NEXT

[8:50] IS AN FET. WE'VE HIRED

[8:56] THAT POSITION, AND THAT WAS FOR

[9:01] THE CRIME SPECIALIST THERE. THE LAST BOX THERE, THE FIVE FTEs

[9:07] FOR CIVILIAN INVESTIGATORS, THREE ARE THOSE POSITIONS HAVE

[9:15] BEEN INTERVIEWED, TWO ARE PENDING A RESOURCE EVALUATION. AS YOU KNOW, TWO POSITIONS WERE

[9:22] TAKEN OUT AT MPD I BELIEVE TO FUND THE AUDITOR'S OFFICE OR MOVE TO THE AUDITOR'S OFFICE, SO

[9:32] WE'RE LOOKING AT WHAT WE CAN DO ABOUT THAT LOSS. THEN WE MOVE ONTO THE FIRE DEPARTMENT. AS YOU KNOW, A BEHAVIORAL CRISIS

[9:40] RESPONSE PROGRAM WAS TRANSFERRED TO FIRE. THAT TRANSFER HAS BEEN

[9:47] COMPLETE. I THINK COMING UP THIS THURSDAY TO FULL COUNCIL, THEY'LL BE THE BCR CONTRACT

[9:55] EXTENSION THROUGH AUGUST OF 2026, AND SO THAT WILL COME BEFORE YOU. NEXT FOR FIRE IS

[10:08] THE SAFER GRANT. THAT GRAMENT AS -- AS YOU KNOW THAT GRANT IS FOR THREE YEARS. THAT GRANT

[10:15] WILL END IN APRIL OF 2026 SO WE'LL NEED FUNDING FOR THOSE 15 FIREFIGHTERS THAT THE GRANT HAS

[10:22] FUNDEDED FOR THE LAST THREE YEARS AND THAT'LL BE IN THE MAYOR'S 2026 BUDGET. MOVING ON

[10:30] TO NEIGHBORHOOD SAFETY. AS YOU KNOW IN NEIGHBORHOOD SAFETY,

[10:36] BECAUSE I BELIEVE SEVERAL CONTRACTS HAVE COME THROUGH AS PART OF THE MASTER CONTRACT, SO

[10:42] THOSE FIRST COUPLE THAT YOU SEE THERE, WHITTIER, PUBLIC SAFETY

[10:47] RESPONSE, THE MID-TOWN PHILLIPS BALANCE PREVENTION AND SAFETY SERVICES, THE LONGFELLOW

[10:54] NEIGHBORHOOD SAFETY INITIATIVE, AND THE HIAWATHA NEIGHBORHOOD SAFETY INITIATIVE, ALL OF THOSE

[10:59] ARE PART OF THAT MASTER CONTRACT

[11:06] IN THE LAST MONTH OR TWO. THE LAST TWO ITEMS THERE, LET EVERYONE ADVANCE WITH DIGNITY,

[11:13] THAT CONTRACT -- THAT HAS BEEN DONE. ALSO THE STAFF CAPACITY

[11:18] WHERE YOU SEE TWO FTEs WERE TRANSFERRED TO NEIGHBORHOOD SAFETY. THOSE POSITIONS HAVE BEEN HIRED. THAT WAS THE

[11:24] BUSINESS DATA ANALYSIS -- ANALYST AND ALSO THE CONTRACT

[11:33] ADMINISTRATOR. FOR THE OFFICE OF COMMUNITY SAFETY, ON THUS

[11:44] SLIDE YOU'LL SEE AT THE START, THE SAFE AND THRIVING COMMUNITIES WORK GROUP

[11:54] $25,000 THERE HAD COME FROM ALSO -- WELL LET ME BACK UP MAYBE EXPLAIN IT BETTER. IF YOU LOOK AT THE SECOND BOX WHERE IT SAYS CAPACITY BUILDING, THERE WE

[12:04] WOULD ASK FOR $50,000 IN THE 2025 BUDGET BECAUSE WE HAD SPENT

[12:10] ABOUT $100,000 IN 2024 AROUND

[12:19] ENGAGEMENT, WE DID LOT OF ENGAGEMENT AROUND THE SAFETY CENTERS WITH AMANDA HARRINGTON BEING THE DIRECTOR OF DESIGN AND

[12:25] IMPLEMENTATION. SO OUT OF THAT, $25,000 WAS APPROPRIATED TO THE

[12:30] SAFE AND THRIVING COMMUNITY WORK GROUP. THAT WORK GROUP I

[12:36] BELIEVE WILL HAVE THEIR FIRST MEETING THIS MONTH, AND THE

[12:42] REMAINDER OF THE 25 -- OF THE $50,000 WILL CONTINUE TO USE IN

[12:48] THE OFFICE OF COMMUNITY SAFETY FOR THOSE THINGS THAT ARE NOTED

[12:55] THERE, WE'LL DO SUPPLIES AND SOME OPERATION EXPENSES AND PRINTING MATERIALS AND THINGS

[13:00] LIKE THAT, LIKE WE'VE DONE BEFORE. THE BACKGROUND CHECK,

[13:07] WE CONTINUE DOING THOSE THINGS WITH BACKGROUND CHECKS. WE

[13:14] MOVED AND PURCHASED SOFTWARE AND IMPLEMENTED THAT SOFTWARE. IF YOU OR YOUR STAFF HAVE DONE ANY

[13:19] OF THOSE BACKGROUND CHECKS, YOU USED TO GET A NICE SIZE BINDER

[13:26] PAPER BINDER TO FILL OUT. WE'VE MOVED THAT SO THAT IT CAN BE DONE ELECTRONICALLY. WE CAN

[13:35] CAPTURE THAT DATA, COLLECT IT, STORE IT AND COMMUNICATE WITH THE MPD APPLICANTS THAT WAY.

[13:43] NEXT TWO POSITIONS THAT WERE TAKEN LAST YEAR WERE BACKFILLED FROM THE OFFICE OF COMMUNITY

[13:48] SAFETY. THAT'S DONE. THE LAST

[13:54] ITEM HERE IS THE NIGHTTIME SAFETY STRATEGIES. WHAT WE DID THIS YEAR WAS WE WORKED WITH MINNEAPOLIS DID TO SCALE BACK OR

[14:03] SCALE DOWN THE WAREHOUSE DISTRICT LIVE. WE'VE WORKED

[14:11] WITH OUR INSPECTORS IN UPTOWN AND DINKY TOWN TO INCREASE SOME

[14:19] PATROLS THERE. ALSO WE'RE LOOKING WITH THE U ON SOME OF THEIR SAFETY INITIATIVE AS WELL.

[14:25] THAT COMPLETES MY PORTION. >> THANK YOU, COMMISSIONER. I'M GOING TO JUST, JUST DO QUESTIONS

[14:32] FOR YOU AT THIS TIME, SO THAT WAY YOU DON'T HAVE TO -- >> THAT'S FINE. >> -- HANG AROUND FOR A BIT. I

[14:38] SEE COUNCIL PRESIDENT PAYNE IS IN QUEUE. >> THANK YOU, VICE CHAIR KOSKI. YEAH, I WAS CURIOUS ABOUT THE

[14:45] SUPPLEMENTAL FUNDING FOR BCR. I KNOW THAT THE CONTRACT WAS UNDER ACTIVE NEGOTIATION. IT WAS KIND

[14:51] OF UNCLEAR ON HOW WE MIGHT IMPLEMENT THAT AMENDMENT. CAN YOU JUST UPDATE, YOU KNOW, ARE

[14:57] WE INCORPORATING THOSE PROGRAM COSTS INTO THE NEW CONTRACT? WERE WE ABLE TO DO AN

[15:03] APPROPRIATION MIDSTREAM? I JUST WANT TO KNOW THE TECHNICAL PLACE WE'RE AT ON THAT.

[15:09] >> CHAIR KOSKI, COUNCIL PRESIDENT PAYNE, WHAT WE DID WAS

[15:16] THE CONTRACT FOR BCR HAD A MAXIMUM AMOUNT FOR EACH YEAR, SO

[15:24] IT'LL COME TO YOU I THINK THURSDAY IN WHICH WE TOOK THE

[15:30] $945,000 TO INCREASE THE CONTRACT AMOUNT SO THAT WE COULD EXCEED THE FUNDING FOR BCR. IN

[15:39] OUR DISCUSSIONS WITH BCR, THEY ARE IN THE PROCESS OF LOOKING AT

[15:46] WHAT CAN THEY PRESENT FOR ONE TIME FUNDING. I THINK THERE WAS MAYBE SOME MISUNDERSTANDING OR

[15:53] CONFUSION THAT THIS WAS ONE-TIME FUNDING, AND SO WE'RE WORKING TO

[15:58] FIGURE THAT OUT RIGHT NOW. IF THAT'S HOPEFULLY THAT ANSWERS YOUR QUESTION. >> OKAY. I'LL JUST KEEP AN EYE

[16:04] ON WHAT THAT ACTION LOOKS LIKE IN THE NEXT CYCLE OR SO. >> YES, YES.

[16:09] >>> THANK YOU. COUNCILMEMBER CASHMAN? >> THANK YOU, VICE CHAIR KOSKI. APOLOGIES I GOT HERE LITTLE BIT

[16:15] THROUGH YOUR PRESENTATION, COMMISSIONER, SO I'M WONDERING IF YOU CAN JUST REMIND ME WHAT HAPPENED WITH THE FIFTH PRECINCT

[16:20] CRIME PREVENTION SPECIALIST THAT WAS BUDGETED FOR. I DO SEE ONE FETHIRED HERE IN THE CHART.

[16:26] THIS IS ON PAGE 8. HOWEVER. YOU KNOW, I, YOU KNOW, LIVE IN THE FIFTH PRECINCT AND HAVE

[16:33] CHECKED THE WEB SITE OFTEN AND TALKED TO CRIME PREVENTION

[16:38] SPECIALIST AND SEEN THAT A NEW CRIME PREVENTION SPECIALIST HAS BEEN LISTED OBAMA WEB SITE OR INTRODUCED IPCOMMUNITIES SO I'M

[16:45] JUST WONDERING WHERE THAT'S AT. >> LET ME BOW GO BACK TO

[16:51] THAT ONE. >> YES. >> I KNOW THAT MY NOTES, I'M

[16:57] SORRY, CHAIR, CHAIR KOSKI. COUNCILMEMBER CASHMAN, MY NOTES

[17:04] JUST SHOWS THAT THAT POSITION HAS BEEN FILLED. I WILL TRY TO GET THAT INFORMATION FOR YOU

[17:10] BECAUSE IT SAYS CRIME PREVENTION SPECIALIST, THAT POSITION'S BEEN

[17:15] HIRED FOR. SO. >> CAN YOU SHARE THEIR NAME OR CONTACT INFORMATION WITH ME? >> THAT'S ALL I HAVE FOR

[17:21] RIGHT NOW. >> NOT TODAY BUT NOTE THAT ONE FOR FOLLOW-UP SO THAT WE CAN START TO WORK WITH THIS

[17:29] INDIVIDUAL. YES. >> OKAY. ANY OTHER QUESTIONS FROM COLLEAGUES FOR THE

[17:34] COMMISSIONER? I AM NOT SEEING ANY, SO THANK YOU SO MUCH.

[17:40] APPRECIATE IT. AND I'LL JUST NOTE BECAUSE IF YOU MIGHT BE LEAD, I'LL ADD TO THE MEMO --

[17:48] LEAVE, I'LL ADD TO THE MEMO THE COO INDICATED THAT WOULD JUST LIKE TO CONNECT THE PROGRESS TO THE GOALS, OBJECTIVES OF METRICS

[17:55] THAT WERE IN THE BUDGET BOOK. ANY AND ALL THAT YOU HAVE AND UNDERSTANDING THE, MONTH 8.

[18:07] UNDERSTANDING AND SOME THINGS GOT STOPPED LAST MONTH SO IF WE COULD GET AN UPDATE PER EACH OF

[18:13] THESE CHANGE ITEMS ON THAT THAT WOULD BE GREAT. >> YES, CHAIR. >> I'LL MAKE SURE I GET THAT MEMO TO THE -- THANK YOU.

[18:18] THANK YOU SO MUCH. >> THANK YOU. >> VICE CHAIR KOSKI, I'M RETURNING UP HERE. I DID WANT

[18:26] TO TALK ABOUT THE CODE THAT YOU HAVE. SO ANYTHING GREEN IS IN

[18:32] PROGRESS. IT IS STILL ACTIVELY IN PROGRESS, IN SOME CASES IT'S IN CONTRACTING, IN OTHER CASES IT'S PARTWAY THROUGH A PROJECT.

[18:39] IF YOU SEE A STAR OVER THE GREEN, THAT MEANS WE CONSIDER THAT ITEM COMPLETE. IT MAY NOT

[18:47] HAVE A LOT OF DATA WITH IT YET, BUT IT IS COMPLETE FROM THE STANDPOINT OF EITHER HIRE HAS

[18:52] BEEN MADE, OR AN ITEM HAS BEEN PURCHASED. WHATEVER'S BEING

[18:58] NOTED. YELLOW WOULD INDICATE THAT WE ARE RUNNING INTO SOME ISSUES ON BUDGET ITEM FROM LAST

[19:05] YEAR, AND RED WOULD MEAN THAT WE HAVE SOMETHING THAT LOOKS LIKE

[19:10] IT'S NOT GOING TO GET ACROSS THE FINISH LINE IN 2025. SO I WILL

[19:16] CONTINUE ON FOR EVERYONE, THAT

[19:22] LITTLE KEY IS ACTUALLY IN THE FRONT OF THE PRESENTATION AS WELL. SO YOU KNOW, CATCH US UP,

[19:28] SORRY THAT WAS LITTLE FAST. THANK YOU FOR $30,000 IN

[19:35] CAPACITY BUILDING IN THE OFFICE OF PUBLIC SERVICE. WE'VE BEEN USING THAT FOR LEADERSHIP

[19:40] DEVELOPMENT FOR OUR TEAM AS WELL AS COACHING IN SOME CASES AS,

[19:47] AND THEN ALSO MAKING SURE THAT WE HAVE THE TOOLS WE NEED TO DO OUR WORK FOR THE CITY. SO WE,

[19:55] WHEN THESE OFFICES WERE SET UP, I CAN YOU CAN SEE A THEME THERE BETWEEN OCS, OFFICE OF COMMUNITY

[20:01] SAFETY, AND OPS, THEY DID NOT HAVE A LOT OF THOUGHT ABOUT THE

[20:07] OTHER AUXILZY BUDGET ITEMS THEY WOULD NEED. 3-1-1 SERVICE

[20:14] CENTER HAD TWO POSITIONS BUDGETED FOR THE NEW SOUTH MINNEAPOLIS COMMUNITY SAFETY

[20:20] CENTER. THIS HAS A LITTLE BUT OF A DIFFERENT CODE BECAUSE IT'S ON TRACK BUT THAT IS NOT GOING

[20:26] TO OPEN THIS YEAR, SO WE ARE HOLDING THAT. THOSE RESOURCES, AND JUST HANGING ONTO THEM UNTIL

[20:34] WE ARE READY TO HIRE FOR THOSE POSITIONS. THIS IS PART OF WHAT MAKES THIS A FULL SERVICE CENTER

[20:41] IS HAVING THE 3-1-1 SERVICES AVAILABLE TO THE PUBLIC. ARTS

[20:50] AND CULTURE HAD A FEW PROGRAMS THAT WERE FUNDED LAST YEAR. THE CIVIC ARTS PROGRAM AND THAT HAS

[20:57] BEEN DISBURSED FOR A NUMBER OF THINGS, INCLUDING ARTS

[21:03] LEADERSHIP CONFERENCE, STATE OF BLACK DESIGN, NATIONAL INDEPENDENT VENUE ASSOCIATION

[21:08] CONFERENCE, AND OTHERS. AND WE CAN GET A BREAKDOWN OF THAT FOR YOU IF YOU WOULD LIKE THAT IN

[21:14] TERMS OF EACH OF THOSE THINGS. WE ALSO HAD THE MUCH LOVED

[21:19] VIBRANT STOREFRONTS AND CULTURAL DISTRICTS FUNDING, AND THAT HAS BEEN GOING VERY WELL.

[21:27] $700,000 OF THAT HAS BEEN DISBURSED AT THIS POINT. WE RECEIVED OVER 275 APPLICANTS FOR

[21:33] THE PROGRAM FOR THAT $700,000, AND OBVIOUSLY WE COULDN'T FUND

[21:39] ALL OF THOSE PROPOSALS. THERE

[21:45] ALSO IS JUST A LITTLE UNDER $500,000 THERE THAT IS GOING TO BE REMAINING FUNDS THAT THE ARE

[21:50] GOING TO ALSO BE ARTS ACTIVATIONS, VIBRANT STORE FRNTSZ RELATED WORK. AND THEN

[21:57] ALSO THE ART PRESERVATION AT GEORGE FLOYD SQUARE THAT'S BIP GOING ON ONGOING. JUST GIVE ME

[22:05] ONE SECOND TO CATCH MYSELF UP.

[22:11] ONE MORE ITEM FOR ARTS AND CULTURE. AND THAT IS THE COALS

[22:17] CENTER OPERATIONS AND PROGRAMMING AND I KNOW YOU, THE COUNCIL JUST ACTED ON CONTRACT FOR A NEW OPERATOR, BUT WE DO

[22:23] HAVE SOME OTHER EXPENSES RELATED TO THAT. OBVIOUSLY HOLDING THE

[22:30] BUILDING FOR THE YEAR. MAKING SURE IT SAID SECURE AND SAFE AND ALL OF THOSE THINGS AS WELL AS

[22:36] WORKING WITH THIS PROJECT OF MAKING SURE THAT WE HAVE

[22:43] CONTINUED DANCE PROGRAMS AND PROJECTS IN DOWNTOWN MINNEAPOLIS AND SURROUNDING AREA, AND THEN

[22:50] THE VERY MUCH APPRECIATED BY THE PUBLIC THE PUBLIC SCHOOL FUNDING FOR THE DANCE PROGRAM THAT WAS

[22:56] PART OF THE ORIGINAL AGREEMENT WHEN COLE'S OPENED. THIS

[23:02] FUNDING WENT TOWARD -- $350,000 OF THIS WENT TOWARDS KEEPING THAT GOING DURING THIS

[23:11] YEAR. LET'S SEE. ASSESSING THERE WERE NO CHANGES.

[23:18] COMMUNICATIONS, CULTURAL MEDIA PROGRAMMING, AND THIS IS

[23:23] UNDERWAY. THIS WAS AN INCREASE MEANT TO MAINTAIN THE EXPANSION OF THE EAST AFRICAN CULTURAL

[23:29] MEDIA FUNDING, AND THAT IS ONGOING. WORK. CIVIL RIGHTS

[23:35] HAD A NUMBER OF ITEMS. WE'RE GOING TO START WITH BACKGROUND

[23:42] CHECKS. THE BACKGROUND CHECKS WERE PARTICULARLY FOR AND THAT

[23:48] CONTRACT WAS EXECUTED IN MARCH. FOR OPCR STAFF TO WORK WITH HR

[23:55] FOR INCOMING STAFF MEMBERS. THERE'S ALSO THE SMALL BUSINESS HIGH ROAD LABOR STANDARDS

[24:02] PROGRAM AND PROJECT, AND THAT CONTRACT WAS EXECUTED AND

[24:08] AMENDED IN FEBRUARY OF THIS YEAR. WE ARE UNDER CONTRACT WITH THE NEIGHBORHOOD

[24:14] DEVELOPMENT CENTER FOR THAT. EIGHT SMALL BUSINESSES HAVE BEEN SERVED ALREADY, AND WE CAN GET

[24:19] YOU MORE DETAIL ON THAT. CIVIL RIGHTS TRAINING AND ADMINISTRATIVE SUPPORT. THIS OF

[24:26] COURSE HAS BEEN VERY IMPORTANT FOR OPCR AS WELL AS MAKE SURE

[24:32] THAT WE ARE WORKING WITH -- MAKING SURE THAT WE ARE WORKING WITH THE NATIONAL PARTNER, THE NATIONAL ASSOCIATION OF CIVIL

[24:39] RIGHTS OVERSIGHT OF LAW ENFORCEMENT TRAININGS THAT WE BROUGHT IN AFTER THE RESET OF

[24:45] THE CIVIL RIGHTS DEPARTMENT. AND THEN THERE'S A NUMBER OF FUTURE TRAININGS ALSO PLANNED TO

[24:51] BE DONE WITH THESE RESOURCES. AND THEN OF COURSE WE HAVE THE

[24:57] LABOR STANDARDS DIVISION AND THE COENFORCEMENT WORK THAT IS ONGOING WITH CTUL, AND MORE THAN

[25:06] 1,000 HOURS HAVE BEEN LOGGED ON THAT, AND 500 HOURS LOGGED IN

[25:14] NAVIGATION SERVICES FOR CONCERNS TO CONNECT THEM WITH THE LABOR STANDARDS DIVISION OF CIVIL

[25:20] RIGHTS. FINANCE AND PROPERTY SERVICES HAD TWO ITEMS. THE

[25:25] MOBILE SECURITY TEAM, AND THOSE

[25:31] FOUR EMPLOYEES HAVE ALL BEEN HIRED AND ARE WORKING WITH US, AND THE FIRST PRECINCT CUSTODIAL

[25:37] STAFFING, WHICH AS YOU ALL KNOW, WHEN WE BRING A NEW BUILDING ONLINE, WE ALSO HAVE TO ACCOUNT

[25:42] FOR THE SERVICES THAT GO WITH IT, LIKE CUSTODIAL, AND SO THAT IS WHAT THIS IS GOING TOWARDS.

[25:50] THE FIRST PRECINCT IS JUST GETTING UP AND RUNNING, SO THAT CUSTODIAL STAFFING IS GETTING

[25:55] ROLLING RIGHT NOW. HUMAN

[26:01] RESOURCES HAD A CAPACITY BUILDING POSITION THAT THEY NEEDED, AND THAT POSITION IS THE

[26:07] LABOR RELATIONS REPRESENTATIVE, AND ADDITIONAL LABOR REP THAT

[26:14] WAS CREATED, AND THAT POSITION HAS BEEN HIRED AND THAT PERSON IS WORKING WITH US. I WANT TO GO BACK ON JUST ONE

[26:21] ITEM. I, WHEN I READ IT I DID THINK I HAD SEEN SOMETHING FROM

[26:26] KAYLA ON THIS THAT ACTUALLY 37 BUSINESSES HAVE BEEN ASSISTED

[26:32] UNDER THE SYBIL RIGHTS SMALL BUSINESS PROGRAM NOW, AND I THINK THOSE ARE STRONG NUMBERS.

[26:40] WHEN WE WERE FIRST WRITING THIS, WE BELIEVED IT WAS EIGHT BUT IT ACTUALLY IS 37. INFORMATION

[26:47] TECHNOLOGY. SO DATA SAFETY PUBLIC SAFETY DATA

[26:53] TRANSFORMATION PROJECT. THIS POSITION, ONE OF THESE POSITIONS IS IN THE JAQ PROCESS RIGHT NOW.

[27:00] SO THREE ARE IN PROCESS. ONE WILL BE SLATED OUT INTO 2027. SO THREE PEOPLE WILL START IN

[27:07] 2025. AND THEN THERE'LL BE A 2027 START DUE TO KIND OF WHERE

[27:13] THE WORKLOAD IS IN THAT TRANSFORMATION. AND THEN AS WELL AS ENTERPRISE-WIDE

[27:19] CONFERENCE ROOM MODERNIZATION AND SUPPORT, THAT FTE IS IN PROGRESS RIGHT NOW. IGR HAD

[27:29] VERY SMALL ADJUSTMENT FOR THE CLIMATE LEGACY INITIATIVE. THIS, AND STILL IMPORTANT TO US

[27:36] BECAUSE THERE ARE STILL DOLLARS THAT HAVE BEEN AVAILABLE THROUGH THE IIJA, AND WE ARE ROLLING

[27:46] THAT INTO OUR EXISTING CONTRACT WITH OUR CONTRACTOR WHO DOES WORK TO HELP US FIND THOSE

[27:53] DOLLARS THAT ARE OUT THERE.

[28:00] NCR. THERE ARE A FEW ITEMS HERE. AND I'M GOING TO DO THIS ONE TOO JUST BECAUSE I THINK THIS IS OUR LONGEST SLIDE OF

[28:07] ANYTHING OTHER THAN THE ONE THAT HAS, YOU KNOW, LIKE 20 ITEMS OR 30 ITEMS. SO THE LABOR WELCOME

[28:14] CENTER. WE ARE WORKING WITH PARTNERING ORGANIZATIONS. THE RFP WILL BE RELEASED IN

[28:19] SEPTEMBER OF THIS YEAR. WHICH IS JUST NEXT MONTH. BLUE LINE

[28:26] LRT ANTI-DISPLACEMENT WORK, THE RFP IS STILL SET YET FOR THIS SUMMER. IT'S GOING TO BE RELEASED IN THE MONTH OF AUGUST

[28:34] YET. SENIOR SERVICES AND COMMUNITY NAVIGATORS. EIGHT

[28:39] ORGANIZATIONS WERE SELECTED FOR CONTRACT AWARDS THAT WERE AUTHORIZED BY THE COUNCIL.

[28:45] IMMIGRATION LEGAL SERVICES, THIS ADDED ADDITIONAL FUNDING TO OUR

[28:52] CAPACITY, AND IS WELL UNDER CONTRACT. AND THEN DRIVERS

[28:58] LICENSE EDUCATION AND ACCESS, TWO ORGANIZATIONS WERE SELECTED FOR CONTRACT AWARDS TO ASSIST US

[29:04] WITH THAT WORK. PMI, PERFORMANCE MANAGEMENT AND

[29:11] INNOVATION, HAD BOTH THE SAFE AND THRIVING COMMUNITIES GAP ANALYSIS. THIS IS A, THIS IS

[29:20] FUNDING FOR ONE YEAR OF THE EMBEDDED SOCIAL WORKER AS WELL AS OTHER WORK AROUND THE SAFE

[29:28] AND THRIVING COMMUNITIES, THE PROJECT TEAM SPECIFICALLY MADE A

[29:35] TRIP TO CHARLOTTE, NORTH CAROLINA, TO SHADOW THE

[29:40] SIBILLION CRASH INVESTIGATORS THERE. AND THAT HAPPENED IN JULY. SO MORE INFORMATION WILL BE COMING ON THAT. AND THEN WE

[29:47] HAD A NUMBER OF PSA BACKFILL POSITIONS HERE AS WELL THAT

[29:53] NEEDED TO BE ACCOUNTED FOR FROM PREVIOUS BUDGET ACTIONS. NO

[30:01] INCREASED TO RACIAL EQUITY INCLUSION AND BELONGING. REG

[30:07] SERVICES. REGULATORY SERVICES HAD THREE ITEMS. THE UNSHELTERED HOMELESSNESS

[30:12] RESPONSE, THERE WAS AN FTE HIRED THERE. ANOTHER IS IN PROCESS

[30:18] CURRENTLY. AND THEN THE AFFORDABLE HOMEOWNERSHIP PRESERVATION PROGRAM, CONTRACT

[30:25] HAS BEEN AWARDED IN JUNE, AND THEN WE WILL START THE RFP

[30:30] PROCESS ON ANOTHER PORTION OF THIS MONEY GOING FORWARD THAT IS

[30:36] A CROSSOVER THAT WILL INCLUDE

[30:41] CDBG FUNDS AS WELL AS FINANCES WORKING ON A PORTION OF THIS.

[30:49] SAFE WORKING PILOT PROJECT HAS NOT STARTED PENDING COUNCIL ORDINANCE AMENDMENT THAT WILL

[30:54] ALLOW FOR OUTDOOR PARKING.

[31:01] DELEGATED AUTHORITY TO TRAFFIC CONTROL. SO THAT IS WHY THAT IS ONE OF THE VERY FEW YELLOWS IN THIS WHOLE REPORT IN TERMS OF

[31:08] BUDGET ITEMS.

[31:14] NEXT I'M GOING TO HAVE THE COMMISSIONER OF HEALTH COME UP TO DO HIS PORTION OF THE

[31:20] PRESENTATION. THANK YOU, VICE CHAIR. >> THANK YOU. WELCOME,

[31:26] COMMISSIONER. >> GOOD AFTERNOON, VICE CHAIR KOSKI AND COUNCILMEMBERS. THANK

[31:32] YOU, CHIEF OPERATING OFFICER KELLIHER. MY NAME IS DAMON CHAPLAIN, HEALTH COMMISSIONER OF

[31:38] MINNEAPOLIS HEALTH DEPARTMENT.

[31:43] AT MIDYEAR THE HEALTH DEPARTMENT CONTINUES TO MAKE SIGNIFICANT PROGRESS ACROSS PRIORITY

[31:48] INITIATIVES WITH THE 2025 BUDGET ADDITIONS AND EARMARKS TOTALING

[31:56] $4.78 MILLION AND SUPPORTING 10.8 FTEs. MAJOR INVESTMENTS FOCUS ON CHILDHOOD LEAD

[32:03] POISONING PREVENTION, OPIOID RESPONSE, AND HARM REDUCTION. CLIMATE RESILIENCE AND COMMUNITY

[32:08] HEALTH PROGRAMS. WHILE MOST INITIATIVES ARE ON TRACK, SOME

[32:13] HIRING AND CONTRACTING ACTIVITIES REMAIN IN PROGRESS. SCHOOL BASED CLINICS RECEIVED

[32:21] $349,000 APPROXIMATELY AND 2.8 FTEs TO PROVIDE ON-SITE MENTAL

[32:27] HEALTH SERVICES IN MINNEAPOLIS PUBLIC SCHOOLS. TO DATE 637 VISITS FOR 74 STUDENTS HAVE BEEN

[32:34] COMPLETED, INCLUDING ADDITIONAL CARE COORDINATION AND STAFF CONSULTATIONS. SUSTAINABILITY

[32:39] HEALTHY HOMES AND ENVIRONMENT HAS THE LARGEST ALLOCATION AT

[32:45] $3.1 MILLION ACROSS SEVEN FTEs, WHICH FUNDS LEAD REMEDIATION, CLIMATE RESILIENCE, AND SUSTAINABILITY INITIATIVES.

[32:52] LEAD POISONING PREVENTION RECEIVED $1.6 MILLION, SUPPORTING WORK IN 102 DWELLING

[32:59] UNITS, 44 OF WHICH HAVE ACTIVE REMEDIATION CONTRACTS WITH

[33:07] $302,000 ENCUMBERED FOR SERVICES. OUR OPIATE RESPONSE INITIATIVES RECEIVE

[33:12] $1.03 MILLION TO EXPAND HARM REDUCTION AND TREATMENT. THE OPIOID SETTLEMENT PROGRAM

[33:19] LAUNCHED -- MEDICATION ASSISTED TREATMENT PILOT WITH 80 PATIENTS ENROLLED. WE ALSO INSTALLED A

[33:25] NARCAN VENDING MACHINE AND PROCURED ESSENTIAL SUPPLIES FOR THE MEDICAL MOBILE UNIT. THE

[33:34] SUSTAINABILITY HEALTHY HOMES AND ENVIRONMENT CONTINUES TO STRENGTHEN CLIMATE PROGRAMS.

[33:40] THE GREEN JOBS AND TRAINING INITIATIVE AWARDED $175,000 TO FOUR ORGANIZATIONS FOR YOUTH

[33:47] CAREER DEVELOPMENT. THE CLIMATE INCENTIVES PROGRAM IS MANAGING $7 MILLION IN INCENTIVES THAT

[33:53] WILL IMPACT 800 TO 1,000 PROPERTIES THIS YEAR. COMMUNITY

[33:58] OUTREACH HAS CONTINUED FROM 2024 WITH A FOCUS ON GREEN COST SHARE

[34:05] AND THE MINNEAPOLIS TREE PROGRAM. NINE COMMUNITY BASED ORGANIZATIONS HAVE PARTNERED TO

[34:11] INCREASE AWARENESS AND PARTICIPATION IN WEATHERIZATION INCENTIVE PROGRAMS. URBAN

[34:23] FORESTRY PROGRAMS HAVE DISTRIBUTED OR PLANTED 1,609 TREES REPRESENTING ABOUT 46% OF

[34:31] THE 2025 GOAL AND EXECUTED FOUR OUTREACH CONTRACTS. THE BIOCHAR

[34:36] FACILITY PROJECT HAS ENTERED PHASE 2, AND IS UNDER CONTRACT WITH COMPLETION EXPECTED IN FALL

[34:43] OF 2025. POLICY AND HEALTHY COMMUNITIES HAS ISSUED AN RFP FOR THE URBAN FARMS PROGRAM AND

[34:51] EXECUTED SIX FOOD WASTE PREVENTION CONTRACTS TO SUPPORT SUSTAINABILITY AND FOOD SECURITY

[34:57] EFFORTS. OPIOID RESPONSE

[35:03] EXPANDED THROUGH NEEDLE CLEAN-UP EFFORTS FUNDED AT $127,900. THIS INCLUDES FINALIZING A HARM

[35:10] REDUCTION POSITION TO SUPPORT SOUTHSIDE GREEN ZONE AND THE HIAWATHA CORRIDOR. POLICY AND

[35:18] HEALTHY COMMUNITIES INVESTED $25,000 IN MANY GRANTS FOR THREE ORGANIZATIONS SERVING TRANSYOUTH

[35:25] AND PARTNERED ON THE TRANS EQUITY SUMMIT TO ENSURE YOUTH

[35:32] PARTICIPATION SWRIERMTAL HEALTH LAUNCHED THE STREET VENDOR ENTREPRENEUR PROGRAM GRANT PROGRAM WITH $150,000 IN

[35:38] ALLOCATIONS, A NEW CONTRACT WITH THE HEALTHY ROOTS INSTITUTE WAS EXECUTED, AND FOUR VENDOR

[35:44] COHORTS ARE SCHEDULED TO BEGIN, BEGAN LAST MONTH, JULY OF 2025.

[35:54] POLICY AND HEALTHY COMMUNITIES CONTINUES TO WORK WITH THE CITY OF LAKES COMMUNITY LAND TRUST TO MANAGE THE URBAN FARM COMMUNITY

[36:00] OWNERSHIP AND OPERATIONS PROGRAM WITHIN THE SUSTAINABILITY HEALTHY HOMES AND ENVIRONMENT.

[36:05] THE CARBON FEES PROGRAM IS ADVANCING CLIMATE GOALS BY REDUCING EMISSIONS IN THE

[36:11] INDUSTRIAL AND COMMERCIAL SECTORS. THE

[36:17] $274,617 ALLOCATION SUPPORTS STAFFING AND CONTRACTUAL EFFORTS TO EVALUATE COMPLIANCE AND

[36:22] PROMOTE GREENHOUSE GAS REDUCTIONS. THE CARBON FEE PROGRAM IS ADVANCING CLIMATE

[36:29] ACCOUNTABILITY WITH EFFORTS FOCUSED ON HIRING AN INDUSTRIAL OUTREACH SPECIALIST AND

[36:34] ASSESSING COMPLIANCE FOR INDUSTRIAL FACILITIES. THE

[36:41] DEPARTMENT IS ON TRACK TO MEET

[36:46] ITS CORE OBJECTIVES, LEAD HAZARD RE MEDIATION, OPIOID TREATMENT EXPANELS, AND CLIMATE

[36:52] INITIATIVES -- EXPANSION AND CLIMATE INITIATIVES ARE PROGRESSING WELL. THOUGH SOME POSITIONS REMAIN UNFILLED AND

[36:59] CERTAIN PROCUREMENT PROCESSES ARE ONGOING, YEAR END PROJECTIONS INDICATE FULL UTILIZE OPTION OF FUNDS WITH

[37:05] MEASURES COMMUNITY IMPACT AND PUBLIC HEALTH AND SUSTAINABILITY

[37:12] OUTCOMES. >> THANK YOU. >> MM-HMM.

[37:23] >> WELCOME, DEPUTY DIRECTOR. >> GOOD AFTERNOON, VICE CHAIR KOSKI AND COMMITTEE MEMBERS. MY NAME IS BRETTE HJELLE AND I'M

[37:29] A DEPUTY CITY OPERATIONS DEVELOPER FOR DEVELOPMENT, HEALTH, AND LIVEABILITY. I'M SUBBING FOR ERIC HANSEN WHO IS

[37:35] ON A WELL EARNED VACATION WITH HIS FAMILY. THE NEXT SEVEN SLIDES ENCOMPASS 31 CPED ITEMS

[37:43] FOR A TOTAL OF JUST OVER $18 MILLION IN 2025 SPENDING. ALL ITEMS ARE ON TRACK RIGHT NOW

[37:50] MEANING THEY ARE EITHER IN PROGRESS OR IN QUEUE WITH A PROJECTED COMPLETION OR CONTRACT

[37:56] EXECUTION IN 2025. THE FIRST

[38:04] SLIDE IS A COLLECTION OF FIVE DEVELOPMENT PROJECT LOANS. THESE KIND OF JUST GENERALLY

[38:09] SPEAKING, THESE PROJECTS GO THROUGH KIND OF THREE BIG STEPS, NEGOTIATING THE TERMS BETWEEN THE CITY AND THE DEVELOPER, THEN

[38:16] THE TERMS ARE APPROVED BY THE CITY COUNCIL AND EVENTUALLY THE PROJECTS GO TO CLOSING SO YOU

[38:22] CAN SEE ALL FIVE PROJECTS ARE ON THAT JOURNEY RIGHT NOW WITH A COUPLE THAT HAVE GONE THROUGH

[38:27] THE CITY COUNCIL. SLIDE 35, THE

[38:35] FIRST ITEM IS THE OWNERSHIP AND OPPORTUNITY FUND. THIS PROGRAM

[38:41] ENSURES THAT WE CAN CONTINUE TO MAKE LOANS AVAILABLE TO EMERGING DEVELOPERS AND SMALL BUSINESSES TO OWN COMMERCIAL REAL ESTATE.

[38:48] CPED BUSINESS DEVELOPMENT TEAM IS WORKING THROUGH LOAN APPLICATIONS ON A ROLLING BASIS. IN 2025 YEAR TO DATE, TWO LOANS

[38:56] FOR $900,000 HAVE BEEN APPROVED AND THREE OTHERS FOR APPROXIMATELY $700,000 ARE IN

[39:02] CONVERSATION. THE BUSINESS TECHNICAL ASSISTANCE PROGRAM, 2025 CONTRACTS ARE GENERAL BTAP

[39:08] SERVICE PROVIDERS WERE APPROVED IN EARLY MAY TO 22 SERVICE PROVIDERS FOR A TOTAL OF

[39:15] $450,000. CONTRACTS WILL RUN FROM MAY '25 TO MAY 2026.

[39:20] WITHIN THAT, THERE WERE UPTOWN SPECIFIC CONTRACTS, AND FOR TOTAL OF $75,000. ITEM 3, THE

[39:29] GREAT STREETS PROGRAM, FOUR UPTOWN SPECIFIC GREAT STREETS BUSINESS DISTRICT SUPPORT CONTRACTS WERE AWARDED FOR A

[39:38] TOTAL OF $100,000. MAINTAINING THE ADULT WORKFORCE PROGRAM AND THE FIFTH ITEM, THE ECONOMIC

[39:45] DEVELOPMENT TEAM CONTINUATION OF SERVICES, BOTH OF THESE HAD THE

[39:52] COMMON ELEMENT OF MOVING EXPENSES OFF OF THE DEVELOPMENT FUND AND ONTO A MORE SUSTAINABLE

[39:58] GENERAL FUND TO MAINTAIN THOSE

[40:04] SERVICES. SLIDE 36, THE YOUTH WORKFORCE DEVELOPMENT PROGRAM.

[40:10] THIS ALLOCATION, THIS IS A 2026 ALLOCATION. AND IT PROVIDES CONTINUED FUNDING FOR YOUTH

[40:16] WORKFORCE PROGRAM THAT FUNDS THE YOUTH WAGES AND PROGRAMMING FOR THE STEP-UP PROGRAM. NICOLLET

[40:25] PROGRAMMING. THIS IS $150,000 FOR THE EXPLORATION OF FAMILY CENTERED ACTIVATIONS ON NICOLLET MALL, SPECIFICALLY TO

[40:31] CONDUCT A FEASIBILITY STUDY TO ASSESS THE VIABILITY OF DEVELOPING AN INDOOR PLAY

[40:36] FACILITY FOR CHILDREN AND FAMILIES ON OR NEAR NICOLLET MALL. THIS, THE PLANNING TEAM

[40:41] IS WORKING ON THAT SCOPE OF SERVICES. CLIMATE LEGACY

[40:47] INITIATIVE GREEN JOBS TRAINING.

[40:53] THIS FUNDING IS FOR GREEN JOBS TRAINING AND IT GOES THROUGH THE CAREER PATHWAYS PROGRAM. THE EMPLOYMENT AND TRAINING STAFF IS

[40:58] WORKING ON THE PROJECT DETAILS TO HAVE THE ALLOCATION OUT FOR CONTRACT THIS YEAR. LAST YEAR THE TEAM COORDINATED AND FUNDED

[41:05] EMERGE TO GET PEOPLE TRAINED AND READY FOR JOBS. TEXAS ITEM

[41:12] IS -- NEXT ITEM IS FOR PEOPLES WAY PROPERTY MANAGEMENT. THIS IS TO PAY FOR THE HOLDING COSTS AND MAINTENANCE ASSOCIATED WITH

[41:19] THE PEOPLE'S WAY PROPERTY AT 38th AND CHICAGO. THE SMALL

[41:24] BUSINESS SUPPORT FOR CONSTRUCTION AND HARDSHIP. THIS IS A COMPLICATED PROJECT. ONE OF THE MORE COMPLICATED PROJECTS

[41:30] ON THIS LIST. AND THE TEAM HAS BEEN WORKING THROUGH THE VARIOUS LEAGUE AND ADMINISTRATIVE

[41:37] QUESTIONS THAT NEED TO BE ANSWERED AS THEY PUT TOGETHER A

[41:42] PROGRAM TO MEET THE INTENT OF

[41:47] THIS $900,000. THE EARLY

[41:53] CHILDHOOD EDUCATION WORKFORCE DEVELOPMENT. THIS WAS UPDATE ON THIS ONE WAS PRESENTED AT PUBLIC HEALTH AND SAFETY COMMITTEE ON

[42:00] THE 30th OF JULY, AND THIS IS INTENDED TO PROVIDE EARLY

[42:05] CHILDHOOD EDUCATION FOR PARTICIPANTS WHO LIVE IN MINNEAPOLIS AND WHO TEND -- INTEND TO WORK IN EARLY

[42:11] CHILDHOOD EDUCATION. THE TECHNICAL ASSISTANCE FOR UPTOWN REVITALIZATION, THIS IS UNDER

[42:16] CONTRACT WITH THE URBAN LAND INSTITUTE. AND THIS IS A PROJECT TO WORK THROUGH THE

[42:21] URBAN LAND INSTITUTE TO MAKE RECOMMENDATIONS FOR THE UPTOWN

[42:28] AREA. LITTLE EARTH COMMUNITY OUTREACH SAFETY PROGRAM. THESE

[42:33] DOLLARS ARE UNDER CONTRACT WITH TWO ORGANIZATIONS, LITTLE EARTH

[42:39] PROTECTORS AND AIM PATROLS.

[42:51] INAFFORDABLE HOUSING TRUST FUND, $3.8 MILLION. THE REQUEST FOR PROPOSAL

[42:57] TASUPPORT THE PRESERVATION AND CREATION OF AFFORDABLE RENTAL HOUSING IN MINNEAPOLIS IS UNDERWAY RIGHT NOW. THE 2025

[43:04] BUDGET IS A TOTAL OF ALMOST $18 MILLION WITH $3.8 MILLION

[43:10] MADE UP OF THE SALES TAX REVENUE A.K.A. LAHA, AND $295,000 OF

[43:18] CDBG PROGRAM INCOME. THE MINNEAPOLIS AFFORDABLE RENTAL

[43:26] STABILIZATION FUNDING IS FOR DESIGN TO SUPPORT STRUGGLING AFFORDABLE RENTAL PROJECTS IN

[43:33] MINNEAPOLIS. THE PILOT WAS FUNDED WITH $1 MILLION IN COLLABORATION WITH

[43:38] PEN 00 COUNTY AND FOUR PROJECTS HAVE BEEN FUNDED, AND WE EXPECT THAT TO BE FULLY EXPENDED IN

[43:43] 2025. THE MINNEAPOLIS HOMES PROGRAM IS DESIGNED TO SUPPORT

[43:49] THE PRESERVATION AND CREATION OF AFFORDABLE HOUSING OWNERSHIP IN

[43:57] MINNEAPOLIS. THE 2025 BUDGET IS $3.8 MILLION. THE FUNDS WERE

[44:04] COMMITTED THROUGH A COUNCIL ACTION AND WILL BE FULLY FUNDED THROUGH THE END OF 2025. THIS

[44:10] REPRESENTS 35 NEW AFFORDABLE OWNERSHIP UNITS ACROSS 23 PROJECTS. THE HERITAGE PARK

[44:15] $500,000 IS A DEVELOPMENT IN WARD 5 WITH 440 AFFORDABLE RENTAL UNITS. THE CITY'S

[44:22] $500,000 IS BEING USED AS A CRITICAL MATCH IN A APPLICATION

[44:28] BY THE DEVELOPER FOR STATE STABILIZATION FUNDS. AVIVEO

[44:39] VILLAGE STABILIZATION SHELTERS, $1.6 MILLION. THE AVIVEO WAS PREPARING A SCOPE BUDGET BREAKDOWN OF HOW THE FUNDS WILL

[44:45] BE USED BY CATEGORY BETWEEN STABILIZATION AND OPERATIONS.

[44:53] AND THIS IS BEING FUNDED BY CPED. EMERGENCY HOUSING

[45:00] VOUCHERS, $1.8 MILLION. THIS IS A PARTNERSHIP BETWEEN THE CITY AND PUBLIC HOUSING AUTHORITY. THERE HAS BEEN EXTENSIVE AMOUNT OF WORK BETWEEN MPHA AND THE

[45:06] CITY OF MINNEAPOLIS TO WORK OUT THE DETAILS OF THE THIS PROGRAM SCOPE, AND CHAT WILL BE USED TO DEVELOP -- THAT WILL BE USED TO

[45:11] DEVELOP THE CONTRACT. SENIOR

[45:17] HOUSING CODE ABATEMENT, $810,000. THIS PROGRAM IS PART OF MINNEAPOLIS HOMES SUSTAINS

[45:23] PROGRAM. IT'S INTENDED TO ASSIST SENIORS TO AGE IN PLACE. TWO PROJECTS HAVE CLOSED IN

[45:29] 2025, AND WE ANTICIPATE THERE'S $525,000 OF CONTRACT OF WORK

[45:35] BEING PROCESSED RIGHT NOW. TWO PROJECTS HAVE CLOSED, ASSISTING 15 HOUSEHOLDS. STABLE HOMES

[45:44] STABLE SCHOOLS EXPANSION, $830,000. THIS IS A PARTNERSHIP BETWEEN THE MPHA, THE CITY OF

[45:50] MINNEAPOLIS, HENNEPIN COUNTY, AND MINNEAPOLIS PUBLIC SCHOOLS. WORKING TO REDUCE HOMELESSNESS

[45:55] AMONG FAMILIES WITH ELEMENTARY AGED KIDS IN MINNEAPOLIS. THE

[46:04] ALL PARTNERS ARE PLANNING FOR THE FUTURE AND WITH AN

[46:10] ANTICIPATED FICKLE CLIFF IN 2026, AND SO CONVERSATIONS -- FISCAL CLIFF IN 2026 SO

[46:16] CONVERSATIONS ARE ONGOING ON HOW TO BEST MOVE FORWARD WITH THE PROGRAM. THE 2050 COMPREHENSIVE PLAN, THIS IS A 2026 BUDGET

[46:24] ALLOCATION. AND THAT WORK WILL BEGIN IN 2026. THE LATINO

[46:30] CULTURAL DESIGNATION, THIS IS FUNDING TO ESTABLISH CULTURAL

[46:38] DESTINATION AND OUR STAFF TEAM IS WORKING ON PROGRAM GUIDELINES. THE DEVELOPER

[46:46] TECHNICAL ASSISTANCE PROGRAM 3 DISPIFT THOUSAND, THIS PROVIDES NO CHOUGHS TRAINING TO EMERGING

[46:52] REAL ESTATE DEVELOPERS. FUNDS ARE EXPECTED TO BE EXPENDED BY THE END OF THE CONTRACT TERM IN

[46:57] THE SPRING OF 2026. AND LAST, BUT NOT LEAST, WAS

[47:02] EARMARK FOR LATINO BUSINESS WEEK, THAT'S IN OCTOBER OF 2025

[47:08] FOR $70,000. PROPOSALS ARE IN AND WILL BE REVIEWED HERE IN THE

[47:13] NEXT MONTH OR SO, EXPECTING GOOD RESPONSE WE HAD A VERY

[47:19] SUCCESSFUL BLACK BUSINESS WEEK. AND FINALLY, ALLOCATION FOR

[47:28] COWLES CENTER FOR UTILITY, GRAFFITI, ALL PROPERTY MAINTENANCE, THAT IS IN PROGRESS AND ON TRACK. THAT CONCLUDES

[47:38] CPED. >> THANK YOU. WE HAVE A FEW COUNCILMEMBERS IN QUEUE, BUT I

[47:45] I THINK I'LL JUST WAIT UNTIL PUBLIC WORKS FINISHES AND THEN I'LL GO TO QUESTIONS FOR EVERYONE. WELCOME, DIRECTOR.

[47:53] >>> THANK YOU, VICE MAYOR KOSKI, COUNCILMEMBERS. MY NAME IS TIM SEXTON. SERVE AS DIRECTOR OF

[47:58] PUBLIC WORKS. SO WE HAVE IN PUBLIC WORKS FOR THE 2025 BUDGET

[48:04] WE HAD 11 CHANGE ITEMS TO WORK THROUGH. I'M HAPPY TO SHARE THAT ALL 11R ON TRACK. THEY

[48:10] WERE A COMBINATION OF GENERAL FUND, ENTERPRISE FUNDS, AND CLIMATE LEGACY INITIATIVE FUNDED

[48:17] ITEMS. OOPS. THERE WE GO. ALL RIGHT, SO STARTING WITH OUR

[48:24] TRAFFIC SAFETY CAMERAS, LITTLE OVER A MILLION DOLLARS, WAS

[48:29] ADDED TO FUND IMPLEMENTATION OF TRAFFIC SAFETY, THE TRAFFIC SAFETY CAMERA PILOT THAT WAS AUTHORIZED BY THE LEGISLATURE

[48:35] LAST YEAR. AS PART OF OUR GOAL TO REDUCE TRAFFIC DEATHS AND

[48:40] SERIOUS INJURIES ON OUR STREETS WE'RE STARTING WITH SPEED SAFETY CAMERAS, THIS YEAR I THINK FOLKS

[48:45] HAVE HEARD A LOT ABOUT THIS I HOPE, BUT FIVE CAMERAS ARE PLANNED TO BE ROLLED OUT IN

[48:51] SEPTEMBER OF THIS YEAR. SO THAT REMAINS ON TRACK MORE TO COME IN

[48:58] 2026 WHERE WE HAVE APPROXIMATELY A $1.9 MILLION BUDGET. THE GOAL ULTIMATELY FOR THAT PROGRAM I

[49:05] WILL MENTION IS TO BE COST NEUTRAL AS THERE IS A REVENUE

[49:10] COMPONENT THAT WILL BEGIN OVER TIME. NEXT ITEM WE HAVE SURFACE WATER AND SEWER. STAFFING

[49:17] SUPPORT. AND THIS IS REALLY TRIGGERED BY ADDITIONAL PERMIT REQUIREMENTS FROM THE MINNESOTA

[49:23] POLLUTION CONTROL AGENCY AND EPA. SO WE NEED TO DO MORE WORK AROUND STORMWATER MANAGEMENT

[49:29] BEST PRACTICES AND PERMIT REQUIREMENTS. SO WE ARE ON TRACK TO HAVE SEVEN POSITIONS

[49:35] HIRED TO MEET THOSE NEW REQUIREMENTS. ALL ARE HIRED OR IN PROCESS: FOR EV CHARGING THAT

[49:42] WAS FUNDED THROUGH THE CLIMATE LEGACY INITIATIVE, THIS IS MEANT TO SUPPORT AND EXPAND ELECTRIC

[49:48] VEHICLE CHARGING THROUGHOUT THE CITY. WORK IS CURRENTLY UNDERWAY TO INSTALL ONE TO THREE

[49:54] NEW EV CHARGING HUB SITES BY THE END OF THIS CALENDAR YEAR.

[50:00] ANOTHER CLIMATE LEGACY INITIATIVE FUNDED EFFORT WAS AROUND ZERO WASTE PLANNING, AND

[50:05] THE GOAL OF THIS ONE WAS TO REALLY EVALUATE ZERO WASTE FUNDING AND SUSTAINABILITY

[50:11] ACTIVITIES AND INVEST IN LOCAL WASTE REDUCTION PROJECTS TO PREVENT, YOU KNOW, REUSABLE, RECYCLABLE, AND COMPOSTABLE

[50:17] MATERIALS FROM ENTERING OUR WASTE STREAM. ALLOWING US TO GET TO THAT ZERO WASTE FUTURE.

[50:23] THERE ARE THREE PARTS OF THAT EFFORT, ALL THREE ARE UNDERWAY. IT INCLUDES UNDERSTANDING WHAT A

[50:29] ZERO WASTE FUNDING MECHANISM COULD LOOK LIKE MOVING FORWARD. COMMUNITY WASTE REDUCTION

[50:35] GRANTS, SO FUNDING COMMUNITY GROUPS TO DEVELOP THEIR OWN IDEAS AND HELP US UNDERSTAND THAT PATH FORWARD BASED ON SORT

[50:42] OF A BOTTOM UP APPROACH TO COMMUNITY ENGAGEMENT AND UNDERSTANDING AROUND ZERO WASTE,

[50:47] AND DOING A RECYCLING AWARENESS CAMPAIGN. NEXT EWE HAVE AN

[50:53] EARMARK AROUND UN UNSHELTERED HOMELESSNESS RESPONSE CLEAN-UP. THIS IS

[51:00] MEANT TO COVER EQUIPMENT AND STAFF TIME FOR ENCAMPMENT SITE MAINTENANCE AND CLEAN-UP. SO WE

[51:06] HAVE PURCHASED A BOBCAT WHICH IS A SMALL TRACT VEHICLE WITH A SCOOP ON THE FRONT ALONG WITH

[51:14] FUNDING FOR FOUR PEOPLE AT A QUARTER TIME EACH TO DO THAT WORK. NEXT UP WE HAVE AN

[51:26] ADDITIONAL SUPPORT FOR LEAD SERVICE LINE REPLACEMENTS. SO

[51:32] WE HAVE THESE PRIVATE LEAD SERVICE LINES THROUGHOUT THE CITY. IT'S A HUGE EXPENSE TO REPLACE THO, THOSE, SO

[51:40] SO FAR WE HAVE BEEN WORKING WITH STATE AND FEDERAL RESOURCES. THIS POSITION IS TO HEPPE HELP PEOPLE UNDERSTAND WHAT THOSE RESOURCES ARE AVAILABLE, AND

[51:45] HELP GET THEM SORT OF, HELP THEM TO COMPLETE THAT WORK SO THAT

[51:50] WOULD FUND ONE WATER LOSS SPECIALIST IN OUR WATER TREATMENT AND DISTRIBUTION SERVICES DIVISION TO SUPPORT THAT LEAD SERVICE LINE

[51:56] REPLACEMENT WORK. THE POSITION WAS HIRED IN APRIL, AND IS

[52:01] CURRENTLY WORKING IN THE FIELD. NEXT WE HAVE A PUBLIC SERVICE --

[52:08] EXCUSE ME, PUBLIC SAFETY IMPROVEMENT LOW BARRIER EMPLOYMENT PILOT. THIS IS A NEW

[52:17] PROGRAM. THE EARMARK DIRECTED US TO CREATE A NEW PILOT PROGRAM TO HIRE ADULTS WHO ARE

[52:23] ENCOUNTERING HOUSING INSTABILITY AND WORKING WITH THOSE, THAT ORGANIZATION OR THOSE PEOPLE TO CLEAN UP TRASH, GRAFFITI, AND DO

[52:29] OTHER CLEAN CITY TYPE OF WORK, ESPECIALLY IN THE SOUTH SIDE

[52:34] GREEN ZONE. NOW THIS IS A BRAND NEW PROGRAM SO WE ARE PLANNING TO POST THAT RFP THIS FALL, AND

[52:42] INTO -- ENTER INTO AGREEMENT BY THE END OF THE CALENDAR YEAR. WE DO HAVE $285,000 THAT WAS

[52:50] ALLOCATED FOR THIS WORK. WE DO NOT EXPECT TO SPEND THAT FULL AMOUNT THIS CALENDAR YEAR, BUT

[52:55] IF WE GET -- WE DO PLAN TO HAVE A CONTRACTOR UNDER CONTRACT ON

[53:01] BOARD SO THAT THOSE FUNDS COULD BE ROLLED FORWARD. NEIGHBORHOOD

[53:08] TRAFFIC CALMING. SO THIS $1.5 MILLION WAS MET TO COMPLETE

[53:13] MORE NEIGHBORHOOD TRAFFIC CALMING PROJECTS. I THINK MANY

[53:19] OF YOU ARE FAMILIAR WITH THIS BUT THIS IS CONSTRUCTION OF SPEED HUMPS AND TRAFFIC CIRCLES. THIS WORK IS CURRENTLY UNDERWAY.

[53:25] WE ARE WORKING ACTIVELY ON 49 PROJECTS ON NEIGHBORHOOD

[53:30] STREETS, 127 SPEED HUMPS, 13 TRAFFIC CALMING CIRCLTZ, FIVE BOLLARD BUMPOUTS, THOSE ARE IN PROGRESS, AND STARTING THIS

[53:37] FALL, WE HAVE SEVEN LOCATIONS IDENTIFIED ON MUNICIPAL STATE

[53:42] STREETS, THESE ARE HIGHER VOLUME STREETS. THAT WE HAVE SEVEN LOCATIONS IDENTIFIED FOR

[53:48] CONSTRUCTION THIS FALL. DINKY

[53:53] AFTER DARK, THIS IS A PEDESTRIAN SCALE LIGHTING PROJECT WHERE

[53:59] $500,000 WAS EARMARKED TO ADD LIGHTING IN THE MARCY HOMES NEIGHBORHOOD INCLUDING DINKY

[54:05] TOWN. WE UPDATED THE PEDESTRIAN SCALE MAP THAT WAS A REQUIREMENT IN ORDER FOR US TO SPEND MONEY IN THAT LOCATION. WE'RE CURRENTLY INSTALLING THOSE

[54:10] LIGHTS RIGHT NOW. IT'S ABOUT 29 LIGHTS KIND OF ON UNIVERSITY,

[54:15] KIND OF BETWEEN UNIVERSITY AVENUE SOUTHEAST, 5th AVENUE SOUTHEAST, BETWEEN 11th AND 13th. SO IN THAT DINKY TOWN

[54:23] AREA, WORK IS CURRENTLY UNDERWAY. IT SHOULD BE DONE IN THE NEXT FEW WEEKS.

[54:31] RECONNECTING COMMUNITIES. THIS WAS, IT HAS THE UNIQUE IDENTIFIER ON THAT ONE WITH THE BOX AROUND THE GREEN CIRCLE.

[54:38] THIS IS $400,000 THAT WAS MOVED FROM STREET MAINTENANCE TO BE USED AS A LOCAL MATCH FOR THE

[54:46] NONPROFIT OUR STREETS IF THEY RECEIVED A RECONNECTING

[54:51] COMMUNITIES GRANT. THEY DID NOT GET THE GRANT, SO THE MONEY REMAINED IN PUBLIC WORKS TRANSPORTATION MAINTENANCE AND REPAIR, SO WE'RE CONTINUING TO

[54:57] USE THAT FOR DAILY MAINTENANCE ACTIVITIES. AND FINALLY, THERE

[55:05] WAS A EARMARK FOR ELECTRIC WHEELCHAIR, SCOOTER, AND MOBILITY AID AND PHONE CHARGING

[55:11] STATIONS FEASIBILITY STUDY. SO THIS LOOKED AT HOW THE CITY CAN SUPPORT CHARGING PHONES, ELECTRIC WHEELCHAIRS, SCOOTERS,

[55:16] AND MOBILITY AIDS AROUND THE CITY AVAILABLE TO THE PUBLIC, SIMILAR TO HOW YOU MIGHT THINK

[55:21] ABOUT ELECTRIC VEHICLES CHARGING AROUND THE CITY. SO THAT WORK

[55:28] STARTED JULY 13th AND IS ON TRACK TO GO COMPLETED BY THE END OF THE YEAR. THAT IS THE FINAL PUBLIC WORKS CHANGE ITEM. AND I

[55:34] GUESS TURN IT OVER TO THE COO. >> THANK YOU, DIRECTOR. WELCOME BACK.

[55:39] >> THANK YOU, VICE CHAIR KOSKI. AS YOU CAN SEE, THESE CHANGE ITEMS FROM 2025 ARE ALMOST 100%

[55:48] ON TRACK, AND I WANT TO SAY THANK YOU TO ALL OF THE STAFF TEAMS WHO'VE BEEN WORKING ON

[55:53] THESE ITEMS. I ALSO WANT TO THANK A FEW PEOPLE FOR HELP ON THIS PRESENTATION. IT TAKES A

[56:00] LOT OF PEOPLE TO PULL THIS TOGETHER, AND SO I WANT TO THANK

[56:05] TRUDY IN OUR OFFICE, MOLLY IN OUR OFFICE WHO DID A LOT OF WORK ON THIS, JANE DISENSA A AS OUR

[56:14] BUDGET DIRECTOR AND HER TEAM TO ASSIST US AND OF COURSE ALL THE DEPARTMENT HEADS AND THEIR SUPPORT STAFF. THANK YOU.

[56:32] >> THANK YOU. WE HAVE COUNCILMEMBER PALMISANO. >> THANK YOU, MADAM CHAIR, AND THANK YOU, MS. ANDERSON-KELLIHER

[56:37] FOR THIS PRESENTATION. I REALLY APPRECIATE HOW WELL ORGANIZED IT IS. IT'S VERY EASY

[56:46] FOR US TO UNDERSTAND. I'M IN QUEUE SINCE DIRECTOR CHAPLAIN'S

[56:53] QUESTIONS. MY QUESTIONS START WITH HIM ON SL SLIDE 33. SOME OF THESE CHANGES THAT WE SAW IN THE PRESENTATION TODAY

[56:58] WERE FROM BUDGET AMENDMENTS THAT CAME THROUGH LAST YEAR. AND WE

[57:09] WERE AWARE OF THE IMPACTED FUNDING SOURCE. IN OTHERS THEY WERE LESS CLEAR, SO I FEEL THAT I WOULD BENEFIT, EVERYONE WOULD

[57:15] BENEFIT FROM A BETTER UNDERSTANDING FOR THE APPROPRIATIONS AND EARMARKS

[57:21] WITHIN A DEPARTMENT, HOW THAT ENDED UP IMPACTING SERVICE DELIVERY OR DEPARTMENT OPERATIONS. LIKE DID IT END UP

[57:26] BEING A GOOD TRADEOFF OR DID SOMETHING ELSE SUFFER THAT WE WERE UNAWARE OF WHEN WE DID THIS DURING THE BUDGET. SO DIRECTOR

[57:35] CHAPLAIN, BACK ON SLIDE 33, THERE HAD BEEN TWO EARMARKS AND YOU CALLED THEM OUT WITHIN

[57:40] HEALTH. THEY WERE CARBON FEES. THIS IS ONE I HAD SUPPORTED, THIS IS FOR P-CARD AND IT'S

[57:46] SITS STUDY AND I'M JUST

[57:52] CURIOUS HOW WERE THESE EARMARKS HANDLED IN YOUR DEPARTMENT AND

[57:57] WHAT WAS IMPACTED BY THAT CHANGE? >> YEAH, COUNCILMEMBER PALMISANO, VICE CHAIR KOSKI.

[58:03] THE EARMARKS WERE DESIGNED TO HELP SUPPORT CONTRACTING FOR

[58:10] BRAWN AND THEN ALSO HIRING THE POSITION FOR THE CARBON FEES AS WELL WHICH IS WHAT WE DID. WHAT WE'RE DOING.

[58:15] >> RIGHT BUT DIRECTOR WHAT I'M ASKING IS THAT MONEY HAD TO BE PULLED FROM SOMEWHERE IN YOUR

[58:21] DEPARTMENT. WE WERE NONSPECIFIC AS TO WHERE TO TAKE IT FROM, SO

[58:27] I'M CURIOUS WHERE THAT MONEY CAME FROM WITHIN YOUR DEPARTMENT, AND I SEE DIRECTOR

[58:35] HANLON HERE TO HELP.

[58:44] >> PATRICK HANLON, DEPUTY COMMISSIONER IN THE HEALTH DEPARTMENT. SO THE FUNDING THAT

[58:53] WAS USED TO EARMARK THESE POSITIONS, IT REDUCED THE AMOUNT OF WORK THAT WE COULD DO IN

[58:59] TERMS OF GREEN COST SHARE WORK OR SOME OF THE OTHER WORK

[59:06] RELATED TO ENERGY EFFICIENCY, SOLAR, THAT KIND OF WORK. SO THE, THE CHANGE IN EARMARK MADE

[59:13] FOR A REDUCTION IN THOSE TYPES OF PROJECTS. EXACTLY HOW MANY,

[59:18] I WOULDN'T KNOW, BUT IT DID REDUCE THE FUNDING. WE

[59:24] TYPICALLY, TAKE THE DOLLAR AMOUNT BETWEEN THOSE TWO 270.

[59:30] >> 275 ABOUT. >> YEAH I WOULD SAY PROBABLY ABOUT A MILLION DOLLARS IN REDUCTION IN INVESTMENTS IN

[59:35] THOSE TYPES OF PROJECTS, AND THEN WE WERE ABLE TO UTILIZE THAT POSITION WOULD BE COMING ON

[59:41] BOARD SOON, AND THEN WE WERE ABLE TO USE THAT STUDY FROM BRAWN TO INFORM OUR FEE STUDY

[59:48] THAT WOULD BE COMING FORWARD LATER THIS YEAR. >> YEAH. THANK YOU. THE IMPACTS OF THIS WOULD BE MUCH

[59:55] FURTHER OUT IN TERMS OF WHAT WE WOULD BE ABLE TO GET DONE THIS YEAR VERSUS OUR P-CARD PROGRAM

[1:00:01] ONCE UP AND RUNNING IS GAUCHE TO HELP IMPACT -- GOING TO HELP IMPACT OUR CITY, SO THANK YOU FOR THAT. MY NEXT QUESTION WAS

[1:00:08] ACTUALLY FOR CPED, SO I GUESS I'M ASKING DCOOHJEL LE, I'M JUST

[1:00:15] REMIND MY COLLEAGUES CPED HAD A LOT OF CHANGES, 31 TOTAL CHANGES AND OVER $18 MILLION WORTH OF

[1:00:20] CHANGES IS WHAT IS.

[1:00:36] BUT I SPECIFICALLY RECALL DIRECTOR HANSEN INDICATING AT THE TIME THAT ONE AMENDMENT

[1:00:44] REMOVED A SIGNIFICANT AMOUNT OF MONEY FROM CODE AND CONSTRUCTION SERVICES, AND THAT WAS VERY CONCERNING TO HIM, AND HE SAID

[1:00:51] AT THE TIME HE ABSOLUTELY COULD NOT TAKE THAT MONEY FROM CODE AND CONSTRUCTION SERVICES AND WOULD HAVE TO LOOK ELSEWHERE.

[1:00:56] AND SO IT'S VERY POSSIBLE YOU DON'T KNOW MR MR. HJELLE, DO

[1:01:05] YOU KNOW WHAT EARMARKS, AND WHAT OTHER SERVICES AND OPERATIONS

[1:01:10] WERE IMPACTED AS A RESULT OF IT. >> VICE CHAIR KOSKI AND

[1:01:15] COUNCILMEMBER PALMISANO, I DON'T HAVE THE DETAILS STANDING HERE. I KNOW ONE OF THE EARMARKED

[1:01:21] ITEMS IS COMING TO THE COUNCIL FOR AN UPDATE AND THAT WOULD LIKELY BE A PLACE -- THAT'S

[1:01:28] CERTAINLY SOMETHING I CAN FOLLOW UP WITH THE CPED TEAM*. >> OKAY, THANK YOU.

[1:01:39] >> DO YOU WANT A FORMAL MEMO? >> I THINK SO, THAT WAY WE'RE ALL AWARE OF IT.

[1:01:46] >> CLERKS CAN YOU NOTE THAT? DO YOU WANT HER TO REPEAT THAT, PLEASE. >> YES, PLEASE. >> I'M CURIOUS HOW THE

[1:01:52] REDUCTION, THE PROPOSED REDUCTION TO CODE AND CONSTRUCTION SERVICES ENDED UP BECAUSE DIRECTOR HANSEN HAD SAID

[1:01:58] HE ABSOLUTELY COULD NOT AFFORD A REDUCTION FROM THAT PART OF HIS

[1:02:04] BUDGET, AND MR. HJELLE SUGGESTED THAT THERE IS ACTUALLY SOMETHING COMING FORWARD TO COUNCIL FOR IT

[1:02:11] IN THE FUTURE. I WOULD LIKE INFORMATION AS TO HOW ALL OF THAT WORKED OUT. THANKS.

[1:02:16] >> AND I'LL GIVE DIRECTOR SEXTON A PASS THIS TIME.

[1:02:22] >> ALL RIGHT. COUNCILMEMBER CASHMAN. >> THANK YOU, VICE CHAIR. I HAVE A COUPLE QUESTIONS FOR REG

[1:02:27] SERVICES AND CPED. ALL DCOO HJELLE OR COO KELLIHER ON REG

[1:02:33] SERVICES. I WAS JUST WONDERING WITH THE UNSHELTERED HOMELESSNESS RESPONSE, ONE FTE AND ONE IN PROGRESS, WHAT NUMBER

[1:02:39] DOES THAT BRING US TO FOR THIS DEPARTMENT'S OR THIS PROGRAM'S STAFF LEVEL FOR UNSHELTERED

[1:02:47] HOMELESSNESS RESPONSE. >> VICE CHAIR COCKY, COUNCILMEMBER CASHMAN, CAN YOU TELL ME SLIDE NUMBER SO I CAN

[1:02:53] GET IT BACK UP? >> 27. >> OKAY. THANKS.

[1:03:02] >> DIRECTOR VELASQUEZ BEHIND YOU. >> OH, ALL RIGHT, HERE YOU ARE, ALL RIGHT. EXCELLENT.

[1:03:09] >> WELCOME. >> THANK YOU VERY MUCH, VICE CHAIR KOSKI. I BELIEVE IT WAS COUNCILMEMBER CHOWDHURY WHO ASKED THE QUESTION.

[1:03:15] >> CASHMAN. >> COUNCILMEMBER CASHMAN, SORRY, I COULDN'T HEAR. ENRIQUE VULAZ

[1:03:22] QUESTION, DIRECTOR OF REGULATORY SERVICES. SO IN ADDITION OF THESE TWO STAFF MEMBERS, THAT BRINGS OUR HRT TEAM UP TO --

[1:03:31] CURRENTLY WE HAVE 5.0 ON STAFF. >> OKAY, THANK YOU SO MUCH.

[1:03:37] YEAH, JUST A BRIEF COMMENT ON THAT. I HAVE FOUND THIS TO BE HELPFUL JUST FROM A USER EXPERIENCE AND FROM A CONSTITUENT SERVICES PERSPECTIVE

[1:03:44] OF BEING ABLE TO REACH OUT TO THIS TEAM AND HAVING THEM REALLY ON SCENE VERY QUICKLY TO HELP

[1:03:49] THE INDIVIDUALS WHO ARE CAMPING SOMEWHERE IN THE WARD, SO JUST WANTED TO GIVE KUDOS TO THAT

[1:03:55] TEAM AND THEIR WORK. MY NEXT QUESTIONS ARE FOR CPED, SO THE

[1:04:01] FIRST ONE IS FROM PAGE 35. NICOLLET PROGRAMMING, IT SAYS

[1:04:08] 150,000. I'M JUST WONDERING WHAT THAT WAS GOING TOWARDS AND WHERE IT IS IN THE BUDGET.

[1:04:15] >> VICE CHAIR KOSKI, COUNCILMEMBER CAS CASHMAN.

[1:04:20] THE NICOLLET ACTIVATION IS TO FUND A STUDY FOR AN INDOOR YOUTH

[1:04:32] CENTER, PLAYGROUND, SOMETHING OF

[1:04:37] LIKE THAT, ALLOCATION AND IDEAS.

[1:04:45] WE ARE FINALLY FUNDING -- >> THANK YOU. SECOND ONE IS STABLE HOME AND STABLE SCHOOLS

[1:04:53] EXPANSION, PAGE 8, THIS WAS COUNCILMEMBER CHOWDHURY AND BUDGET CHAIR CHUGHTAI, MAYBE OTHER AUTHORS ON THIS AMENDMENT.

[1:05:01] CHAVEZ AND PAYNE, SO YOU KNOW MORE THAN WILLING TO HEAR FROM YOU ALL TOO, BUT I DO RECALL FROM MY RECOLLECTION THAT THIS

[1:05:07] WAS TO EXPAND STABLE HOME, STABLE SCHOOLS TO SERVE MIDDLE

[1:05:14] SCHOOL CHILDREN, I SEE ON PAGE 38 IT DOES SAY IN PROGRESS BUT I KIND OF HEARD YOU SAY THAT YOU'RE STILL FIGURING OUT HOW TO SPEND THAT MONEY. AND SO COULD

[1:05:23] YOU GIVE A LITTLE BIT MORE DETAIL ON WHAT THE EXPANSION TO SERVE MIDDLE SCHOOL STUDENTS WILL L LOOK LIKE?

[1:05:30] >> VICE CHAIR COCKY, COUNCILMEMBER CASHMAN, MY UNDERSTANDING IS BASED ON THIS

[1:05:38] LARGE GROUP PARTNERSHIP THAT IS PUTTING THIS PROGRAM ON, THEY ARE LOOKING TO THE FUTURE AND SEEING THIS FISCAL CLIFF, AND BEFORE DECIDING TO EXPAND

[1:05:45] SOMETHING THAT HAS A CLIFF IN FRONT OF IT, THEY ARE TRYING TO FIGURE OUT THE BEST NEXT STEPS

[1:05:50] TO MAKE SURE THE CURRENT PROGRAM IS SUSTAINABLE. >> OKAY, THANKS. I JUST WANTED TO MAKE SURE I

[1:05:56] UNDERSTOOD CORRECTLY BECAUSE IT DOES SEEM LIKE SOMETHING THAT WE ALL NEED TO BE AWARE OF AND TRYING TO SOLVE FOR WITH SUCH

[1:06:06] SUCCESSFUL AND IMPACTFUL PROGRAM WITH SO MANY PARTNERS AND REALLY IMPORTANT SERVICE OF HELPING

[1:06:12] OUR PUBLIC SCHOOL FAMILIES ACCESS HOUSING SO I JUST WANTED TO BE ABLE TO RECOGNIZE THAT AND BRING IT TO OUR ATTENTION AS

[1:06:17] SOMETHING TO WORK ON IN THE LONG-TERM. AND THEN JUST THAT'S ALL THE QUESTIONS THAT I HAD BUT

[1:06:23] JUST WANTED TO THANK YOU ALL SO MUCH FOR THIS PRESENTATION. YOU KNOW, WE'RE IN A RAPIDLY

[1:06:29] CHANGING WORLD, AND CHANGING OUR BUDGET OR CITY BUDGET TO REFLECT EMERGING NEEDS COMING FROM THE

[1:06:34] COMMUNITY I THINK IS IMPORTANT. SO I'M GLAD THAT YOU KNOW OUR JOB AS REPRESENTATIVES IS TO

[1:06:39] IDENTIFY THOSE NEEDS AND TRY TO AMEND THE BUDGET ACCORDINGLY TO FIT WHAT OUR CONSTITUENTS ARE

[1:06:45] RAISING TO OUR ATTENTION, AND I THINK THIS IS REALLY GREAT WORK THAT'S COME IN JUST A FEW MONTHS

[1:06:51] OUT OF THIS YEAR, AND SO IT'S REALLY GREAT TO SEE ALL THOSE GREEN CIRCLES AND ALL THE

[1:06:59] PROGRESS. >> THANK YOU. COUNCILMEMBER VETAW. >> THANK YOU, CHAIR. MY

[1:07:05] QUESTION IS FOR DIRECTOR SEXTON. YOU SAID WE WERE GOING TO HAVE $400,000 GO BACK BECAUSE THE

[1:07:12] OPEN STREETS, OUR STREETS APPLICATION WASN'T AWARDED, SO

[1:07:18] I'M WONDERING WHAT'S GOING TO HAPPEN WITH THAT $400,000. >> VICE CHAIR KOSKI,

[1:07:23] COUNCILMEMBER VETAW. SO THE $400,000 WAS ORIGINALLY FROM OUR

[1:07:28] GENERAL SORT OF GENERAL MAINTENANCE FUNDING, SO THAT WOULD'VE BEEN TAKEN OUT OF

[1:07:34] THINGS LIKE PLOWING SNOW, POTHOLES, FILLING POTHOLES, SO THAT'S GOING BACK TO THAT

[1:07:41] FUNDING SOURCE. >> THAT'S EXACTLY WHAT I WANTED TO HEAR, DIRECTOR. GREAT SO MORE POT POTHOLES FILLED,

[1:07:48] MORE SNOW PLOWING HAPPENING WITH THAT $400,000. >> CORRECT. >> LOVE IT. THANK YOU.

[1:07:54] >> ALL RIGHT. ANY FURTHER QUESTIONS FROM COLLEAGUES? I'M NOT SEEING ANY. SO I JUST WANT

[1:08:00] TO SAY THANK YOU SO MUCH TO CITY STAFF AND LEADERS FOR PREPARING

[1:08:05] ALL OF THIS. I KNOW IT'S A TREMENDOUS LIFT, BUT I THINK IT'S SO HELPFUL FOR US TO SEE WHERE WE'RE AT AND PROGRESS, AND

[1:08:13] MAKING SURE THAT WE ARE SHOWING TO THE PUBLIC HOW THEIR TAXPAYER

[1:08:18] DOLLARS ARE BEING SPENT. SO IT'S GREAT AGAIN TO SEE ALL THE GREAT PROGRESS, AND THANK YOU

[1:08:24] FOR ALL OF THE HARD WORK TO MAKE THAT TRANSPARENT FOR US. SEEING

[1:08:31] NO FURTHER DISCUSSION, I'LL ASK THE CLERK TO RECEIVE AND FILE THIS REPORT, AND WITH THAT, WE'VE CONCLUDED ALL BUSINESS TO

[1:08:38] COME BEFORE THE COMMITTEE TODAY. WITH NO OBJECTION, WE STAND ADJOURNED. THANK YOU.

Was this story helpful?

Other Topics from This Document

  • Mid-year budget change updates

  • Performance management and data tracking of 2025 budgeted items

  • City Attorney's Office budget review

  • Office of Community Safety (OCS) budget and program status

  • Emergency Management and 911 staffing updates

  • MPD compliance and audit capacity progress

  • Behavioral Crisis Response (BCR) program status

  • Neighborhood safety initiative contracts

  • Health Department mid-year budget initiatives

  • Childhood lead poisoning prevention progress

  • Climate resilience and sustainability programs

  • CPED development project loans

Want to know when new stories arrive?

Enter your email to receive updates.

We will not use your email for any other purpose. You can unsubscribe at any time.