Neighborhood Info Meeting 10_22_20 2 p.m. Glen_Amlee_Manitou

Wednesday, October 21, 2020

Glen Road, Amlie Road, and Manitou Lane construction project overview

Stormwater management and drainage concerns

Tree inventory and preservation status

Proposed water main installation and connection fees

Impact on native american burial mounds

Eminent domain and easement acquisition

Project timeline and milestones

Road design widths and no-parking zones

Hennepin County Regional Rail Authority property usage

Notable Quotes (3)

The city is confident that eminent domain will not be needed.

Andrew Buddy
Eminent DomainExplaining the property acquisition process.

If you don't have them today it's insane to be going ahead with this roads project.

Rich Aing
Hydraulic AnalysisQuestioning the readiness of the project given missing hydraulic flow data.

I don't think that that's fair that they were led you to believe it's okay and then pull the plug on you in the last minute.

Greg Larson
Hennepin County NegotiationsAddressing the failed Option 3 compromise.

People (3)

Places Mentioned

Glen RoadAmlie RoadManitou LaneShorewood, MNCounty Road 19Parcel 24740

Events & Meetings (10)

  • October 22, 2:00 PM: Neighborhood Open House 1
  • October 22, 7:00 PM: Neighborhood Open House 2
  • March 11, 2019: Feasibility study authorized
  • November 25, 2019: Feasibility study accepted
  • August 13, 2020: Final plans authorized
  • Winter 2020: Final plans and specifications meeting
  • Winter 2021: Contract awarding
  • March 2021: Tree removal start
  • May 2021: Excavation start
  • September 2021: Project completion