North St. Paul City Council — Transcript
Tuesday, September 15, 2026
Fiber Optic Installation Issues
Sewer System Blockage and City Response
2027 Maximum Levy Setting for City, HRA, and EDA
City Financial Software Upgrade
Minnesota Public Facilities Authority Grant for Water Tower
Departmental and Community Updates
Votes (5)
Setting of the 2027 Maximum Levy for City, HRA, and EDA Budget and Property Tax Levies
Dissent: None
Moved by Council member Schwar [18:03] · Seconded by Council member [18:05]
Finance Director Dan Winnick presented the preliminary 2027 maximum levy, aiming for a total levy increase of no more than 6%. This target was achieved through a $15,000 reduction in the Economic Development Authority (EDA) levy and a corresponding $25,000 increase in the general fund's investment income, after initial proposals. The city's levy components (general, street, park, asset preservation, debt funds) were detailed, and Ramsey County city levy comparisons were provided, showing North St. Paul's proposal as competitive. A council member raised a question regarding potential federal interest rate increases impacting future city bonding, to which the Finance Director acknowledged the concern for 2028 and beyond, but not the immediate 2027 levy.
Resolution adopting the preliminary 2027 tax levy for the North St. Paul Housing and Redevelopment Authority
Dissent: None
Moved by Council member [19:04] · Seconded by Council member Norby [19:07]
This resolution, part of the overall levy setting, specifically concerned the preliminary 2027 tax levy for the Housing and Redevelopment Authority (HRA). The amount proposed and approved remained consistent with the previous year at $11,000, contributing to the overall 6% levy increase target.
Resolution adopting the preliminary 2027 tax levy for the North St. Paul Economic Development Authority
Dissent: None
Moved by Council member [19:51] · Seconded by Council member Woods [19:54]
This resolution finalized the preliminary 2027 tax levy for the Economic Development Authority (EDA) at $185,97. This figure reflects the $15,000 reduction discussed as part of the strategy to achieve the city's overall 6% levy increase target, demonstrating a directed adjustment in this specific fund.
City Financial Software Upgrade from Tyler Technologies ERP Pro 9 to Pro 10
Dissent: None
Moved by Council member Schwar [28:51] · Seconded by Council member McKenzie [28:54]
Finance Director Dan Winnick presented the case for upgrading the city's outdated Tyler Technologies ERP Pro 9 financial software to Pro 10. The current system is inefficient for modern utility billing, manual for EV and solar net metering, prone to record locking, and has poor reporting capabilities. Pro 10 offers improved search, multi-user access, better reporting, and future capabilities like in-house bill printing. The city had previous issues with an OpenGov contract but emphasized using the same vendor for this upgrade reduces data migration risks. The upgrade involves a $6,400 annual increase for a contract manager module and a one-time $37,000 migration fee. A council member inquired about data security and breaches, which was generally addressed by noting the cloud-based nature and expected higher security of newer software.
Application for and Agreement with Minnesota Public Facilities Authority for Water Tower Grant
Dissent: None
Moved by Council member McKenzie [32:56] · Seconded by Council member Woods [32:59]
The City Council approved a resolution to apply for and enter into a grant agreement with the Minnesota Public Facilities Authority (MPFA) for a $4.5 million grant. This grant, initially allocated for a community center, was reappropriated for the water tower project during the previous legislative session, with support from Representative Leon Lily and Senator Tu Jang. The MPFA is a new entity for the city to collaborate with on grants, different from the prior Department of Employment and Economic Development (DEED). The resolution authorizes the Mayor and City Manager to execute the necessary application documents, with the formal grant agreement to follow for council approval.
Notable Quotes (9)
It was the city council's decision and the city manager to target our department heads to come up with a budget of that had a total levy increase of no more than 6%.
Doesn't doesn't mean that the levy can't go still go lower. It certainly can. You've got a few months to still talk about the budget.
Um there's rumors that the the Fed could do some stuff with the interest rate. If they do, does that have any impact that we would be concerned about for this levy?
My concern and one that we need to be very aware of is that we're scheduled to go out for a bonding next year. And if we're looking at that, we're probably looking at rates that are going to be in that 5% range.
It is very outdated very very much so. A lot of things have changed during that time. Part of what has really changed a lot is is our billing on the utilities and our electrical side to it where we're having time of use.
The biggest piece to it is, and I think we learned a lot of lessons just from... one of the biggest components that we can't lose sight of is when we just converted last year over to to the Paycom system and the and the and the hiccups and the issues that you know came with it. In this case, you're dealing with the same company that knows exactly where your data is and exactly how to migrate it over into the new system.
My my only or my concern is with going to this new system, this new technology is is the city protected to a level that the city is comfortable with if there's any data breaches with this data.
The grant of the $4.5 million that was originally assigned to the community center, in this past legislation center, session, due to the assistance of the Minnesota House Representative, Leon Lily and Minnesota Senator, Tu Jang, um and, um the I the mayor and the city manager were there to, to speak. um this was reappropriated and redirected to um the water tower.
Something that was new with this because before we had dealt with deed as governing over the grant agreements and the contract the looked these guys up and they're actually a conglomerate of several different commissions.
Ordinances & Resolutions (19)
Approved on the consent agenda
Approved on the consent agenda
Approved on the consent agenda
Approved on the consent agenda
Approved on the consent agenda
Approved on the consent agenda
Approved on the consent agenda
Approved on the consent agenda
Approved on the consent agenda
Previous contract questioned by a public speaker for missing Exhibit B
Approved preliminary maximum levy for the City portion
Approved preliminary maximum levy for the HRA portion
Approved preliminary maximum levy for the EDA portion
Current city financial software, approved for upgrade
Target financial software for upgrade
Previously implemented payroll/HR system
Approved the financial software upgrade
Approved the application process for the water tower grant
Future agreement for $4.5 million grant for water tower