North St. Paul City Council Workshop - 6/17/25

Tuesday, July 15, 2025

Community Center feasibility study update

Grant funding requirements and project parameters

Facility site analysis and deferred maintenance report

Demographics and regional market research

Operational performance and business proforma options

Areas of Interest (5)

  • City faces a $3 million gap beyond $5.3 million in grants to renovate the aging community center.
  • State 'B3' sustainability requirements could force costly upgrades on top of standard deferred maintenance.
  • Concerns raised regarding city's bonding capacity given existing debt from road reconstruction projects.
  • Consultants suggest shifting from city-run facility to public-private partnership to reduce operational subsidies.
  • Community center closure linked to pandemic, competition, and severe deferred maintenance issues.

Votes (1)

Adopt the agenda

PassedUnanimous

Moved by Council member Schwar · Seconded by Council member Woods

Notable Quotes (2)

If you accept the grant then you must do what is known as B3. B3 is the state's sustainability program.

— Mike Clark
Grant funding complianceExplaining the cost-increasing requirements attached to state funding.

We are currently a little heavily debted by our current bond for the road reconstruction projects that we do run.

— Mike Clark
Financial bonding capacityDiscussion on the feasibility of bonding for the community center.

People (8)

Mike ClarkDirector of Civic Design Group

Leading the feasibility study and presenting architectural findings.

1 quote

“The city would need to invest $3 million beyond the grant funding to bring that building up to a reasonably useful place.”

Regarding total capital improvement project costs.

Andrew SubieArchitect

Assisting with architectural analysis and documentation.

EvaCity Communications

Providing background on the community center's history and current status.

Darren BarConsultant

Remote expert on recreational facility planning and demographics.

MongiMayor

Chairing the workshop meeting.

WoodsCouncil Member

Participating in the workshop and questioning budget/bonding impacts.

SchwearCouncil Member

Participating in the workshop.

McKenzieCouncil Member

Participating in the workshop.

Places Mentioned

Maplewood Community CenterRamsey County Library

Events & Meetings (1)

  • June 17th workshop
View Source
North St. Paul City Council Workshop - 6/17/25 - North St Paul Recorder