Wheelock-Grotto Phase 1 Meeting | March 11, 2025
Tuesday, April 15, 2025
Will Grle Phase 1 project overview
Construction timeline and schedule
Sidewalk placement and design policy
ADA compliance and infrastructure upgrades
Tree planting and forestry management
Sanitary sewer service replacements and waiver forms
Underground infiltration trenches for water quality
Boulevard rain garden partnership with Watershed District
Forestry walk scheduling
Bike Boulevard pavement markings
Public hearing preparation and city council process
Property access during construction
Assessment notifications and processes
Notable Quotes (3)
If we had put the sidewalk at the toe of those slopes we would not have had... amount of Boulevard for future tree planting.
Sidewalk PolicyExplaining sidewalk location decisions on Park View.
The sewer waiver is requesting the project to replace the portion of your sewer service that is in the public right of way.
Sanitary SewersClarifying the specific sewer section targeted by the project.
We will back fill at the end of the day... you won't be driving on asphalt it may be gravel.
Construction LogisticsAddressing property access and parking concerns.
People (4)
Janette RebarSt. Paul Public Works
Managing virtual meeting, chat, and attendee questions.
Barb MundallProject Lead
Primary contact for project design, construction, and resident inquiries.
Chris KzaCapital Region Watershed District
Contact for Boulevard rain garden feasibility.
Richard EobSewer Department
Consulted by resident regarding sewer depth and replacement scope.
Places Mentioned
Park ViewIvyOrangeEast Como BoulevardOsageAvenFsenSt. Paul City HallLake View
Events & Meetings (4)
- Virtual Open House: Current date
- Public Hearing: April 23, City Council Chambers
- Project Start: June 2 (tentative)
- Project End: October 31 - Mid-November
Ordinances & Resolutions (1)
Sidewalk Infill Policy
Policy determining sidewalk placement, currently under review alongside new tree ordinances.