Wheelock-Grotto Phase 1 Meeting | March 11, 2025
Will Grle Phase 1 project overview
Construction timeline and schedule
Sidewalk placement and design policy
ADA compliance and infrastructure upgrades
Tree planting and forestry management
Sanitary sewer service replacements and waiver forms
Underground infiltration trenches for water quality
Boulevard rain garden partnership with Watershed District
Forestry walk scheduling
Bike Boulevard pavement markings
Public hearing preparation and city council process
Property access during construction
Assessment notifications and processes
Full Document Analysis
Notable Quotes (3)
If we had put the sidewalk at the toe of those slopes we would not have had... amount of Boulevard for future tree planting.
The sewer waiver is requesting the project to replace the portion of your sewer service that is in the public right of way.
We will back fill at the end of the day... you won't be driving on asphalt it may be gravel.
People (4)
Janette RebarSt. Paul Public WorksManaging virtual meeting, chat, and attendee questions.
Managing virtual meeting, chat, and attendee questions.
Barb MundallProject LeadPrimary contact for project design, construction, and resident inquiries.
2 quotes
Primary contact for project design, construction, and resident inquiries.
“The sewer work will be replaced during the project during the other construction.”
Clarifying the timeline for sewer service replacement.
“We will be walking the neighborhood either Friday or Monday depending on she gave me two times and I said how about Friday.”
Addressing the forestry walk schedule on Osage.
Chris KzaCapital Region Watershed DistrictContact for Boulevard rain garden feasibility.
Contact for Boulevard rain garden feasibility.
Richard EobSewer DepartmentConsulted by resident regarding sewer depth and replacement scope.
Consulted by resident regarding sewer depth and replacement scope.
Places Mentioned
Events & Meetings (4)
- Virtual Open House: Current date
- Public Hearing: April 23, City Council Chambers
- Project Start: June 2 (tentative)
- Project End: October 31 - Mid-November
Ordinances & Resolutions (1)
Policy determining sidewalk placement, currently under review alongside new tree ordinances.