Mahtomedi Public Schools — Transcript

Sunday, November 22, 2026

Approval of Bid Packet Two and Overall Project Budget

Approval of Guaranteed Maximum Price (GMP) for Bid Packet One

Votes (2)

Approval of Bid Packet Two and Project Budget

Unanimous Approved

Dissent: None

Moved by Director Donna [Timestamp]

The discussion centered on the comprehensive budget for the project, including construction costs ($24,772,407) and soft costs ($3,508,593) for a total project cost of $28,281,000. Key points included how the budget was balanced by drawing from the owner's contingency, the rationale behind a single bid for electrical contractors (due to lead times for main switch gears up to 54 weeks), and the transparent process for Knutson Construction's self-performing bids. The management of project contingencies, including the district's and Knutson's, was thoroughly explained, noting how unused funds would be credited back to the district for project-related expenses. Alternate bids for items like cafeteria booths, gym equipment, carpet, and security cameras were identified as strategically chosen for easy addition or removal.

Approval of Guaranteed Maximum Price for Bid Packet One

Unanimous Approved

Dissent: None

Moved by Director Witson [Timestamp] · Seconded by Director Peterson [Timestamp]

This item focused on formalizing the financial commitment for Bid Packet One by approving the Guaranteed Maximum Price (GMP). The discussion highlighted that the GMP acts as a legal safeguard for the district, locking in project costs and transferring the risk of unforeseen material or labor price increases, delays, or hidden issues behind walls to Knutson Construction. The fee structure for Knutson's role was also disclosed as 1.55% of the project cost.

Notable Quotes (7)

And for this go around we're talking about bid package two guaranteed maximum price with the value there in that gold...And that total value for the construction costs is the 24 million 772,407 dollars. And that is inclusive of all contingencies, permitting, insurances, bonding, um subcontractor default insurance, staffing and operations, as well as general conditions.

— AJ [Timestamp]
Approval of Bid Packet Two and Project Budget

Yeah, so as far as addressing the the one out of the five that we had had prequalified so um we had expected um out of the five that prequalified if they'd have taken the time to prequalify we would have expected them to bid on that bid day. Um, sometimes businesses make decisions in the moment behind their doors on whether or not they're providing a bid for the project...

— AJ [Timestamp]
Approval of Bid Packet Two and Project Budget

There are two contingencies. There's ours and that just if if we don't use all of that um we we're able to use it on the project for certain things and that's at the district's discretion. And then there's a a larger contingency. It's about a a little over a million dollars...If all of that contingency did not get used, then it comes back as a credit to the district.

— AJ [Timestamp]
Approval of Bid Packet Two and Project Budget

We would probwe would look at what the lead times for that scope of work would be kind of make a backward pull backward timeline from there. Then we can track that in against where we're at with the progress of the construction as as with the progress of the contingency usage. And if those two line up, that's when that would be.

— Tim Erickson [Timestamp]
Approval of Bid Packet Two and Project Budget

So these are these are the legal documents that lock in that guaranteed maximum buy back budget and uh questions you might have but um on section one point one come back to budget um have director manager approved this for so this lock that up not

— Unknown [Timestamp]
Approval of Guaranteed Maximum Price for Bid Packet One

covers any surprises behind walls covers any change in material costs or labor costs or delays actually protects us change scope of the whole works right Well if if the district drive change scope then it's come back to but essentially yeah for the most part we're locked in and what delivery model is I I understand we're one of the first district school districts to should result in less change orders Uh and then it shifts. Now we're shifting. Also all of the contracts That's what I And just so I'm clear, you guys make a little bit of extra money on this, right? I mean this you're not doing this out of the kindness of your hearts. You must be doing this must be compensated and reducing your risk in some way, right? I mean is that accurate?

— Unknown [Timestamp]
Approval of Guaranteed Maximum Price for Bid Packet One

The fee that we take is listed in that document yes so they're 1.55%

— Unknown [Timestamp]
Approval of Guaranteed Maximum Price for Bid Packet One

Ordinances & Resolutions (5)

Bid Packet TwoOther

A set of bids for construction work, integrated into the overall project budget, requiring Board approval.

Bid Package OneOther

An earlier set of bids for construction work, with its Guaranteed Maximum Price previously approved and incorporated into the current budget.

Proposal Request Number One (PR1)Other

A specific proposal request for the remainder of structural steel, issued within Bid Package One.

Guaranteed Maximum Price (GMP)Other

A legal agreement locking in the maximum price for the construction project, transferring financial risk to the contractor.

International Code Council Standard 500Other

A building code standard reviewed as part of the soft costs, related to the storm shelter component of the project.

View Source