Lake Elmo City Council — Transcript

Thursday, October 23, 2025

Story

Lake Elmo Council backs city sewer for major development project

Creation of a Tree Fund and Boulevard Tree Program

Continuation of GFOA Certificate of Achievement

Request to Change Garbage Collection Start Time

Votes (4)

High Point Crossing Development Alternatives

Consensus to pursue Option 1 (extend city sewer) and amend Comprehensive Plan; staff to bring back details.

The developer, Rachel Development, presented two alternatives after soil testing rendered the originally approved community septic system unviable for their 80-acre High Point Crossing project. Alternative 1 involves extending city sanitary sewer and amending the comprehensive plan to create a new 'Open Space Low Density Residential' (OP LDR) land use category, maintaining similar density to the original 65 units. This requires Met Council approval. Alternative 2 proposes a large-lot rural development with individual septic systems, reducing units to 30, and requesting flexibility on road standards, stormwater/wetland easements, and pipe materials. Council discussion highlighted long-term concerns about septic failures with Alternative 2 and the 'island MUSA' aspect of Alternative 1, but ultimately leaned towards the public sewer option due to long-term sustainability.

Tree Fund and Boulevard Tree Program

Consensus to proceed with developing a Tree Fund and Boulevard Tree Program; staff to bring back a detailed plan for council approval.

Staff proposed creating a Tree Fund with an initial $50,000 from school mitigation and establishing a Boulevard Tree Program. The program would allow residents to 'adopt' boulevard trees, which would be planted by contractors, with residents responsible for watering. The Council supported the initiative, emphasizing its ongoing nature, the need for clear eligibility (e.g., public right-of-way, no active warranty), and exploring optional 'pay it forward' donations for long-term sustainability. They clarified that the fund should not be used for trees on private property.

GFOA Certificate of Achievement

Consensus to discontinue pursuing the GFOA Certificate of Achievement.

Dissent: One unknown Council Member [0:51:50] expressed a desire to keep it as a 'nice thing to have'.

Staff questioned the value of continuing to pursue the GFOA Certificate of Achievement, noting that it costs the city over $5,000 per year, does not impact bond ratings, and does not add significant transparency beyond the standard audit. Council members generally agreed that the certificate did not offer sufficient tangible benefits to justify the ongoing cost and administrative effort.

Request to Change Garbage Collection Start Time

Staff directed to research garbage collection start times and citizen complaints in adjacent cities and report back to the Council.

The Council considered a request from Tennis, a garbage hauling company, to change the collection start time from 7 a.m. to 6 a.m. The company cited improved driver safety by avoiding construction traffic and increased efficiency in a growing community. Council members acknowledged potential benefits but also raised concerns about noise impact on residents. They noted varying policies in nearby cities (Woodbury/Maplewood at 6 a.m., Stillwater/North St. Paul at 7 a.m.).

Notable Quotes (9)

Alternative two uh is effectively what I would consider to be more of like a large lot development where the developer would be looking at having individual septic systems as opposed to a community septic system. um that would necessitate revision to reduce the number of lots, make the lots larger and in in in order to accommodate those primary and secondary drain fields for their septic systems.

Nathan [0:08:40]
High Point Crossing Development Alternatives

It became clear as we get were getting closer to the end of that design that they kept asking for more information... at the end of the day, we realized that they were going through a process of figuring out how to re-evaluate these septic systems, and they were going to require additional testing.

Paul Robinson [0:17:40]
High Point Crossing Development Alternatives

To me, when we go along with the septics on these, we set up a future issue for the city and trying to deal with those failures... I'm kind of inclined in the go to the fall. Let's get the sewer and be done with it for the then we're done for the future.

Council Member Draguch [0:35:56]
High Point Crossing Development Alternatives

Yeah, it would be kind of an island of the Musa, right? ... Some of it's just optics, right? And maybe I just need to forget about that and just say what what what makes sense.

Mayor [0:32:04]
High Point Crossing Development Alternatives

The current code allows for a fee in L, but it doesn't specify how the fund should be spent. ... The city does not have a rightaway or boulevard tree replacement program. So if trees die, they're out of their warranty period in a neighborhood. Sometimes they get cut down by public works. There isn't a fund or a way for the city to replace them except for going through the HOA.

Nathan [0:41:40]
Tree Fund and Boulevard Tree Program

I think having a tree fund with Boulevard tree program is a really great idea. You know, we we're a tree city. We require all these trees be planted with developments and that, but a boulevard of our trees get something happens, we don't replace them. And there's kind of a disconnect in in my mind and what is our value...

Council Member Jagusich [0:42:36]
Tree Fund and Boulevard Tree Program

with the the agreement for them to water the tree. Can there also be language in there? And they acknowledge there is no warranty period.

Council Member Holtz [0:43:37]
Tree Fund and Boulevard Tree Program

every time I had to touch this thing, I wondered what do we get from this? ... It does not affect our bond rating at all. I spoke with our auditors. There are some extra steps. it does not affect any type of um other than adding to that process, it really doesn't affect that audit or how it's viewed by whoever.

Nathan [0:51:00]
GFOA Certificate of Achievement

they hit a little little trigger in there that it it's probably a little bit safer for the drivers if they get in there before uh 7:00, not have to go around some construction equipment that may be starting at 7 o'clock and things of that nature.

Mayor [0:55:04]
Request to Change Garbage Collection Start Time

Ordinances & Resolutions (9)

Preliminary PlatPlan

Original approval for High Point Crossing development in September 2024.

Comprehensive PlanPlan

City's guiding document, requiring amendment for MUSA expansion in Alternative 1.

Zoning OrdinanceOrdinance

City's zoning rules, requiring amendment to create a new land use category (OP LDR).

OPUD standardsOther

Open Space Planned Unit Development standards, referenced for High Point Crossing.

OP LDR (Open Space Low Density Residential)Other

Proposed new future land use category for Alternative 1 development.

RSF (Rural Single Family)Other

Existing land use category in the Comprehensive Plan, guided for High Point Crossing property.

2050 Comp PlanPlan

Future comprehensive plan where a broader MUSA boundary conversation is expected.

Tree Preservation sectionOrdinance

Section of city code to be amended to add a new section G for the Tree Fund.

GFOA Certificate of AchievementOther

Certificate from the Government Finance Officers Association for financial reporting.

View Source