2025 Street Improvement Project Overview
Annual Street Improvement Program Objectives
Pavement Condition and Deterioration Analysis
Proposed Project Improvements and Utilities
Construction Process Details
Project Timeline and Approval Process
Project Financing and Special Assessments
Assessment Deferral Process for Financial Hardship
Notable Quotes (5)
The city of Oakdale has developed an annual Street Improvement program that has five objectives the first objective is to improve safety there is a direct correlation between pavment condition and safety on our streets for all users including bikers Walkers and motorists
patching is a very inefficient way to continue maintaining the streets as it costs five times more per ton to P to patch a street than it does to PVE a street
The estimated cost of this project is a little over 7.2 million the city will be financing 81% of the total project or a little more than 5.9 million uh the balance of the project will be financed with special assessments to the property owners
special assessments are defined as a loan that is recorded against the property and spread over a 10-year period the interest rate is 2% above the rate the city pays on a bond sale with interest acur starting in October of 2025
if the assessment creates a financial hardship there is a deferral that can be applied for and that's an application through the finance director generally the property is required to be Homestead status
Ordinances & Resolutions (4)
The informational presentation fulfilling the initial neighborhood meeting objective for the 2025 Street Improvement Project.
A report to be prepared and presented to the City Council on December 8th, reviewing the schedule and cost estimate for the project.
Engineering plans for the project, authorized for preparation if the Council orders the project.
The agreement to be awarded in April to the selected contractor for construction of the project.