[0:01] Hi, John Nelson, assistant city engineer
[0:03] with the city of Lakeville. Here to talk
[0:05] to you today about active road projects
[0:07] going on within the city. We have the
[0:10] 202nd Street and Hamburg Avenue
[0:13] intersection improvement project. This
[0:15] will be construction of a single lane
[0:18] roundabout at the intersection of 202nd
[0:21] Street and Hamburg Avenue. The
[0:24] roundabout is being constructed due to
[0:26] the need for a safety improvement at the
[0:28] intersection and is necessary to help
[0:30] provide safety throughout the community
[0:32] with substantial completion targeting a
[0:35] midepptember completion date and
[0:37] intersection reopening at that time.
[0:40] 185th Street construction is actively
[0:43] underway. Construction is proceeding on
[0:46] schedule for that project. We are still
[0:49] targeting a substantial completion date
[0:51] at the beginning of September. 185th
[0:54] Street and IPava intersection is
[0:57] reopened to traffic at this time. Uh
[1:00] utilities, curbon gutter, and the first
[1:03] course of asphalt pavement have been
[1:05] installed throughout the east end of the
[1:07] project between Exonia Avenue and IPA
[1:11] Avenue. We are now beginning work on the
[1:14] west end of the project between County
[1:17] Road 50 and Exonia Avenue, starting from
[1:21] the ground up with utility
[1:22] installations. For more information, go
[1:25] to lakevillemn.gov
[1:26] for additional information on our city
[1:28] projects.