StoryPlanning commission approval of Dakota Electric's headquarters preliminary platFebruary 21, 2025

Planning Commission Approves Dakota Electric Headquarters Plat

Meeting date: Feb 21, 2025
Published Oct 8, 2025

The Lakeville Planning Commission unanimously approved a preliminary plat Thursday for Dakota Electric Association's new headquarters facility, moving the project forward to the March 3 city council meeting for final approval.

The development, called Airlake DEA Second Edition, involves a one-lot subdivision east of Cedar Avenue and north of 225th Street. Dakota Electric plans to construct a 176,500-square-foot multi-use building that will house offices, warehouse space and storage facilities.

This project represents the development of a future headquarters for Dakota Electric," said Jeff Shoner, vice president of utility services at Dakota Electric Association. "Our hope is that as this goes through the process that we could start construction yet late spring summer and then it's a 2-year build and so by summer of 2027 that we would be moving into a new headquarters facility.

The commission approved the plat with 10 stipulations outlined in the planning report. Senior Planner Heather Boton told commissioners the proposed building and site improvements comply with setback requirements and zoning code standards for the industrial district.

Employee and visitor access will come from 225th Street to the south, while construction and fleet vehicles will use the future 222nd Street to the north. Dakota Electric will need to submit a separate administrative permit for fuel storage tanks planned for the site's western boundary.

Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.

Go deeper on this topic

Research related meeting documents and build a brief — without rewriting the story.

Full analysis

Summary

The Lakeville Planning Commission held a public hearing on February 20, 2025, to consider Dakota Electric Association's preliminary plat application for their new headquarters facility. The project, called Airlake DEA Second Edition, involves a one-lot subdivision east of Cedar Avenue and north of 225th Street. The commission unanimously approved the preliminary plat with 10 stipulations, and the project will move to the March 3rd city council meeting for final approval.

Key Highlights

Action Items

Present airlake DEA second edition preliminary plat to city council

Responsible: Planning DepartmentDue: 2025-03-03

Continue coordination with township regarding road improvements

Responsible: Dakota Electric AssociationDue: Ongoing

Submit administrative permit for fuel storage tanks

Responsible: Dakota Electric AssociationDue: TBD

People, Places & Organizations

Dakota Electric Association · Utility CompanyJeff Shoner · PersonHeather Boton · City StaffAirlake DEA Second Edition · Development ProjectCedar Avenue · Street225th Street · Street222nd Street · StreetLakeville Planning Commission · Government BodyCity Council · Government BodyTownship Board · Government Body