Edina City Council — Agenda

Monday, October 6, 2025

Story

Edina Council approves stormwater and flood protection ordinances

Fred Richards Park Wetland Restoration Project

Interactive Meeting Policy and Remote Participation

Stormwater Management Ordinance (No. 2025-10)

Floodplain Districts Ordinance (No. 2025-09)

France Avenue Sidewalk Phase 4 Professional Services

Minor Pipe and Grading Projects for Flood Risk Reduction

Edina Aquatic Center Improvements

Community Comment and Public Hearing Procedures

Finance Payment of Claims Security

Votes (13)

Ordinance No. 2025-10: Amendment Regarding Stormwater Management

Approved as part of Consent Agenda (Item 6.8)

Staff presented ordinance to update and move stormwater management requirements from Chapter 10 to Chapter 36. The update clarifies code requirements for stormwater management and erosion control plans, applying them to more than just new single and double dwelling units, including ADUs and major remodels/partial demolitions. The ordinance codifies staff application of requirements since 2016 following meetings with Council and Planning Commission. The update is consistent with Water Resources Management Plan policy to regulate development and redevelopment to ensure actions do not adversely impact others.

Ordinance No. 2025-09: Amending Chapter 36 Concerning Zoning, Article X. Floodplain Districts

Approved as part of Consent Agenda (Item 6.9)

Staff presented comprehensive update to Floodplain Districts Overlay Ordinance to incorporate local floodplain development policy from Water Resources Management Plan, incorporate 2022 MN DNR model ordinance, and incorporate FEMA Letter of Map Revision. Key changes include creation of new Local Flood Area District with elevation standards, incorporation of Interactive Water Resources Map by reference, clarification of substantial improvement/damage determinations, and application of elevation standards to ADUs. The ordinance acknowledges climate change impacts and alternative pathways for flood risk including groundwater and sanitary sewer backflow.

Request for Purchase: Professional Services for France Avenue Sidewalk Phase 4

Approved as part of Consent Agenda (Item 6.6)

Council approved professional engineering services with Bolton & Menk, Inc. for final design of Phase 4 sidewalk improvements along the east side of France Avenue from TH 62 to 62nd Street. The project is part of the City's 2018 Pedestrian and Bicycle Master Plan and fills a significant gap in the sidewalk network while supporting Metro Transit's E Line Bus Rapid Transit service. The scope includes project management, survey, utility coordination, final design, permitting, and bidding assistance. Construction is anticipated in 2026. The project is funded by the Pedestrian and Cyclist Safety (PACS) fund.

Request for Purchase: Professional Services for Minor Pipe and Grading Projects for Flood Risk Reduction

Approved as part of Consent Agenda (Item 6.7)

Council approved professional services with Barr Engineering for $197,700 to evaluate and implement minor storm sewer and grading projects citywide to reduce flood risk. The project includes citywide screening to identify locations where retrofits to existing storm sewer or overland flow paths could result in drainage improvements, preliminary hydraulic modeling to evaluate flood risk reduction, and final design for up to 10 project locations. The project is funded by the Storm Water Utility and CIP with total funding of $2.5M for both design and construction. Construction is anticipated in 2026.

Request for Purchase: Edina Aquatic Center Card Reader Access

Approved as part of Consent Agenda (Item 6.4)

Council approved purchase of card reader access devices for the Edina Aquatic Center pump room with Pro-Tec Design for $20,612.14. The contract was part of the project budget but not included in the construction contract as it is an owner-provided service. The city will implement, own, and operate the system.

Request for Purchase: Edina Aquatic Center Pump Room Security Cameras

Approved as part of Consent Agenda (Item 6.5)

Council approved purchase of CCTV cameras for the Edina Aquatic Center pump room with Pro-Tec Designs for $32,526.48. The contract will add new and replace existing cameras as part of the overall project budget. The city will implement, own, and operate the system.

2026-2027 Budget: Fire Staffing Discussion (September 16 Work Session)

No formal vote; continued discussion with staff to provide additional options

Council continued discussion on fire staffing as part of the 2026-2027 preliminary budget process. Staff reviewed data on overlapping incidents, mutual aid trends, ambulance response times, and operational impacts of adding firefighters in six-person increments. The Fire Chief explained that six additional firefighters would allow two more per shift, helping sustain a third ambulance and reduce reliance on mutual aid. Council expressed concerns about firefighter safety, overtime, recruitment challenges, and budget pressures from other citywide obligations including ADA compliance and future maintenance. Council discussed how many firefighters should be added and how to fund them, with the Chief indicating Edina's need is 18 firefighters, with a plan to add six on January 1 and twelve more if the SAFER grant is awarded.

Fred Richards Park Wetland Restoration Project Update (September 16 Work Session)

No formal vote; information only; staff recommendation noted

Staff presented an update on wetland design and restoration at Fred Richards Park. Two scenarios were reviewed: creating a wetland mitigation bank (more complex, uncertain, over budget by about $3.1M) or pursuing a wetland preserve (enhances existing conditions, reduces costs by about $2.6M, stays within budget). Staff recommended the preserve option, noting benefits such as allowing additional features not permitted in a wetland bank. Council discussed costs, risks, and differences between restoring to historical conditions versus preservation, with some expressing disappointment in the change.

Interactive Meeting Policy Update (September 16 Work Session)

No formal vote; continued discussion with staff to develop implementation plan

Staff shared changes to the Interactive Meeting Policy to provide a consistent process for remote participation and ensure compliance with Minnesota Open Meeting Law. Key changes include removal of requirements for participants to be in a public space or provide notice of their location. Staff recommended changes to Community Comment and public hearing procedures for security, including providing addresses on forms instead of stating them publicly. Staff also asked whether the Council should continue the call-in option, which began during COVID-19 but has had very low use this year and requires significant staff coordination. Council discussed the value of continuing the option, equity concerns for those unable to attend in person, staff time commitments, and comparisons to practices in other cities.

Finance Payment of Claims Security Enhancement (September 16 Work Session)

No formal vote; information and recommendation presented

Staff recommended moving Finance Payment of Claims approval materials from the public Council packet to a secure Council portal due to rising phishing attacks. Scammers have been using invoice details from online materials to create fraudulent invoices, leading some cities to lose funds. Many cities now remove these details from public documents. Payment of Claims will be available through the public data request process.

Community Comment - Fire Department Staffing Concerns

Community comment received; City Manager to respond at next meeting

During community comment at the September 16 meeting, Ralph Zickert thanked the Edina Fire Department for their work on a fire at his home in 2011 and discussed Edina's lack of funding for staffing the fire department over the last 15 years. This comment directly relates to the Council's discussion of fire staffing additions in the 2026-2027 budget.

Community Comment - ADA Compliance Concerns

Community comment received; City Manager to respond at next meeting

During community comment at the September 16 meeting, David Frankel noted that he filed an ADA complaint with the DOJ regarding the pedestrian bridge on Grandview, as the DOJ has stated that the bridge is not ADA-compliant. Mr. Frankel stated that the City should issue a formal public apology to all residents who have been unable to use this bridge and noted that he plans to run for City Council next year.

Community Comment - Bikeability and Utility Franchise Fees

Community comment received; City Manager to respond at next meeting

During community comment at the September 16 meeting, Caleb Bruhschwein called in remotely advocating for increased bikeability in the City and asked questions regarding the anticipated increase in utility franchise fees.

Notable Quotes (16)

The legal review revealed that permitting requirements in Chapter 10 do not apply to ADUs. The review further revealed that stormwater requirements in Chapter 10 do not apply to remodel/demolition projects that remove less than or equal to 50% of the area of exterior walls.

Jessica V. Wilson, Water Resources Manager
Ordinance No. 2025-10: Amendment Regarding Stormwater Management

Development projects have implications for stormwater runoff. The proposed change codifies the status quo of reviewing and mitigating potential adverse impacts to neighboring properties consistent with the original spirit of the stormwater management plan requirement.

Jessica V. Wilson, Water Resources Manager
Ordinance No. 2025-10: Amendment Regarding Stormwater Management

While this ordinance is primarily focused on reducing exposure and vulnerability of structures to flooding from surface sources, the City of Edina recognizes that seepage from high groundwater and sanitary sewer backflow are also pathways for flood exposure and that individual properties are responsible for understanding their exposure to all sources of flooding.

Jessica V. Wilson, Water Resources Manager
Ordinance No. 2025-09: Amending Chapter 36 Concerning Zoning, Article X. Floodplain Districts

Climate change is increasing the risks associated with flooding through more frequent and intense storm events, altered precipitation patterns, and prolonged elevated groundwater levels during wet cycles, creating long-term challenges.

Jessica V. Wilson, Water Resources Manager
Ordinance No. 2025-09: Amending Chapter 36 Concerning Zoning, Article X. Floodplain Districts

The City's 2018 Pedestrian and Bicycle Master Plan calls for the addition of sidewalk along the east side of France Avenue between from TH 62 to Fuller St. This fills a significant gap in the City's sidewalk network and will support Metro Transit's E Line Bus Rapid Transit service.

Bolton & Menk, Inc. (Sarah E. Lloyd, P.E., Sr. Project Manager)
Request for Purchase: Professional Services for France Avenue Sidewalk Phase 4

The existing topography on the east side of France Avenue from 62nd Street to approximately 200 ft south of 62nd Street is significantly higher than the existing roadway. The construction of retaining walls is expected throughout the majority of this segment of the corridor to avoid extremely steep slopes.

Bolton & Menk, Inc.
Request for Purchase: Professional Services for France Avenue Sidewalk Phase 4

The first part of the study includes a citywide screening to identify locations where retrofits to the existing storm sewer or overland flow paths could result in drainage improvements that reduce the risk of flooding. The goal is to identify locations where the system modifications are relatively minor, and localized, to minimize the potential for or extent of impacts outside of the area studied.

Barr Engineering (Brandon Barnes, Vice President)
Request for Purchase: Professional Services for Minor Pipe and Grading Projects for Flood Risk Reduction

Following identification of potential project locations, the City intends to identify local modifications to the storm sewer system or overland drainage paths to reduce flood risk. Project opportunities will be confirmed through preliminary hydraulic modeling to evaluate flood risk reduction and planning-level cost estimates for each opportunity.

Barr Engineering
Request for Purchase: Professional Services for Minor Pipe and Grading Projects for Flood Risk Reduction

Six additional firefighters would allow two more per shift, helping sustain a third ambulance and reduce reliance on mutual aid.

Fire Chief Andrew Slama
2026-2027 Budget: Fire Staffing Discussion (September 16 Work Session)

Council agreed this is a high-cost but high-value decision and requested staff to bring back clear options showing fiscal impacts and trade-offs for further discussion before the levy is set.

City Council (General Discussion)
2026-2027 Budget: Fire Staffing Discussion (September 16 Work Session)

The preserve option would enhance existing conditions, reduce costs by about $2.6M, and stay within budget.

City Staff
Fred Richards Park Wetland Restoration Project Update (September 16 Work Session)

Council discussed the value of continuing the option, equity concerns for those unable to attend in person, staff time commitments, and comparisons to practices in other cities. Some supported eliminating it, while others suggested limited off-camera access opportunities, such as quarterly sessions, as an alternative.

City Council (General Discussion)
Interactive Meeting Policy Update (September 16 Work Session)

Scammers have been using invoice details from online materials to create fraudulent invoices, leading some cities to lose funds. Many cities now remove these details from public documents.

City Staff
Finance Payment of Claims Security Enhancement (September 16 Work Session)

Thank you to the Edina Fire Department for their work on the fire at my home in 2011. I want to discuss Edina's lack of funding for staffing the fire department over the last 15 years.

Ralph Zickert, 4311 Cornelia Circle
Community Comment - Fire Department Staffing Concerns

I filed an ADA complaint with the DOJ regarding the pedestrian bridge on Grandview, as the DOJ has stated that the bridge is not ADA-compliant. The City should issue a formal public apology to all residents who have been unable to use this bridge.

David Frankel, 4510 Lakeview Drive
Community Comment - ADA Compliance Concerns

I am advocating for increased bikeability in the City. I also have questions regarding the anticipated increase in utility franchise fees.

Caleb Bruhschwein (remote), 5744 Ewing Avenue South
Community Comment - Bikeability and Utility Franchise Fees

Ordinances & Resolutions (28)

Ordinance No. 2025-10Ordinance

Amendment regarding Stormwater Management; updates and moves stormwater management requirements from Chapter 10 to Chapter 36; clarifies applicability to ADUs, major remodels, and partial demolitions

Ordinance No. 2025-09Ordinance

Amending Chapter 36 concerning Zoning, Article X. Floodplain Districts; incorporates local floodplain development policy, 2022 MN DNR model ordinance, and FEMA Letter of Map Revision

Resolution No. 2025-90Resolution

Submitting an Application for Noise Wall #62 Improvements by MnDOT

Resolution No. 2025-91Resolution

Setting Public Hearing Date for Municipal Consent for MnDOT's Project 2 of the I-494 Corridor Vision

Resolution No. 2025-97Resolution

Authorizing 2026 DWI/Traffic Safety Officer Grant Agreement

Resolution No. 2025-87Resolution

Approving the Participation of the Hennepin County Housing and Redevelopment Authority in an Affordable Housing Project

Resolution No. 2025-94Resolution

Approving the Participation of the Hennepin County Housing and Redevelopment Authority in an Affordable Housing Project

Resolution No. 2025-84Resolution

Transferring Local Board Authority of Appeal and Equalization Power and Duty to Hennepin County ('Open Book')

Resolution No. 2025-95Resolution

Weed Mowing Special Assessment, Improvement No. WD-25

Resolution No. 2025-96Resolution

Tree Removal Special Assessment, Improvement No. TR-25

Resolution No. 2025-100Resolution

Certification of Delinquent Utilities

Resolution No. 2025-85Resolution

Aquatic Vegetation Special Assessment, Improvement No. AQ-25

Resolution No. 2025-92Resolution

Grandview Maintenance District Annual Assessment, Improvement No. G-25

Resolution No. 2025-93Resolution

50th & France Maintenance District Annual Assessment, Improvement No. M-25

Resolution No. 2025-88Resolution

Concord B & C Neighborhood Roadway Reconstruction Special Assessment, Improvement No. BA-465

Resolution No. 2025-89Resolution

Southdale B Neighborhood Roadway Reconstruction Special Assessment, Improvement No. BA-464

Resolution No. 2025-98Resolution

Accepting Donations

Resolution No. 2025-83Resolution

Approving a Subdivision (Preliminary and Final Plat) at 6417 Warren Avenue

Resolution No. 2025-80Resolution

Site Plan Review and Variance at 5036 France Avenue South

Ordinance No. 2025-11Ordinance

Amending Chapter 6 Concerning Special Events and Approve Special Events Policy

Ordinance No. 2025-12Ordinance

Repeal and Amend Certain City Code Sections

Ordinance No. 2025-13Ordinance

Amending Chapter 2 Fee Schedule

Water Resources Management PlanPlan

City policy document incorporating Flood Risk Reduction Strategy; guides stormwater and floodplain management

Flood Risk Reduction StrategyPlan

Comprehensive strategy adopted in 2020 and incorporated into Water Resources Management Plan in 2022; addresses infrastructure, regulation, outreach, and emergency services

Interactive Water Resources MapPlan

City's local hydraulic and hydrologic model showing flood inundation areas and peak water surface elevations

Pedestrian and Bicycle Master PlanPlan

2018 plan calling for sidewalk additions along France Avenue to fill gaps in network and support Metro Transit E Line

FEMA Letter of Map Revision (LOMR), Case No. 25-05-1025PPermit

FEMA panel effective December 26, 2025, incorporated by reference in Floodplain Districts Ordinance

2026-2027 BudgetPlan

Preliminary budget under development; includes discussion of fire staffing additions and levy increase considerations

View Source
Edina City Council - Edina Recorder