Edina Transportation Commission approves 2026-2027 work plan unanimously

The Edina Transportation Commission unanimously approved its work plan for 2026 and 2027 at a meeting on October 23, prioritizing traffic safety improvements and pedestrian access across the city. The commission also reviewed a major roadway reconstruction project planned for the Prospect Knolls neighborhood.

Meeting date: Oct 23, 2025
Published Jun 14, 2026

Commissioners voted unanimously to adopt the 2026/2027 Work Plan, which focuses on four key initiatives: continuing participation in the Safe and Equitable Mobility Action Plan (SEMAP), a citywide review of traffic safety standards, a pilot program for innovative traffic calming solutions, and integration with the city's comprehensive transportation plan.

The commission also discussed proposed changes to Edina's city code related to transportation and received updates on ongoing 2025 projects, including a bike-and-walk-to-school day at Concord Elementary and a draft report on bicycle-related city code provisions.

Staff presented a detailed report on a planned 2026 roadway reconstruction project in the Prospect Knolls neighborhood. The project will rebuild roads, install new sidewalks, and upgrade utilities including water mains, sewer lines, and storm drains across streets like Antrim Road, Dublin Circle, and Fleetwood Drive. According to Transportation Planner Andrew Scipioni, the project aligns with the city's Living Streets Policy and climate action goals. "Staff seeks to balance the recommendations of the City's guiding documents with feedback from affected residents, available right-of-way and potential tree and infrastructure impacts," Scipioni said.

Funding for the roadway portion will come from property taxes (47.4%) and special assessments paid by residents (52.6%), calculated based on residential equivalent units. The project also includes funding from city utility budgets and a Pedestrian and Cyclist Safety Fund for sidewalk construction. Residents have expressed concerns about traffic speed and driver behavior in the area, though opinions varied on whether new sidewalks are necessary.

The commission will continue reviewing the Prospect Knolls project details at future meetings. The approved work plan reflects the city's broader commitment to safer streets and improved pedestrian and bicycle infrastructure across Edina.

Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.

Go deeper on this topic

Research related meeting documents and build a brief — without rewriting the story.

Full analysis

City Code Review

Discussion Only

The Commissioners reviewed proposed changes to the City Code relevant to the Transportation Commission. The discussion focused on understanding and commenting on the implications of these changes.

2025 Work Plan Updates

Information Received

The Commission received updates on several components of the 2025 Work Plan, including the Safe and Equitable Mobility Action Plan (SEMAP) participation, Commission-Led Events like the Concord Elementary bike/walk to school day, and ongoing reviews of City Policies/Ordinances and City Code. A committee is also drafting a report on City Code regarding bicycles for future review.

2026/2027 Work Plan Proposal

Approved Unanimously

Moved by Commissioner Brown [None] · Seconded by Commissioner Bildsten [None]

Commissioners discussed and ranked the proposed initiatives for the 2026/2027 Work Plan. Key initiatives included continued SEMAP participation, a review of traffic safety standards and development of a decision-making playbook, innovative traffic calming solutions with a 'Towards Zero Deaths' pilot program, and the transportation segment of the comprehensive plan.

Prospect Knolls A/C/D Roadway Reconstruction Project (Report for Oct 23, 2025 Meeting)

Report for Discussion and Review

This report details a proposed roadway reconstruction project for 2026 in the Prospect Knolls A, C, & D neighborhood. It outlines plans for full roadway reconstruction, replacement of existing and installation of new concrete curb and gutter, construction of new concrete sidewalks (aligned with the Pedestrian and Bicycle Master Plan and Climate Action Plan), and comprehensive utility improvements including sanitary sewer lining, watermain replacement (especially near Dublin Reservoir), and storm sewer upgrades. The project aims to update substandard infrastructure, improve pedestrian facilities, and address resident concerns about traffic safety and localized drainage, balancing these with City policy guidelines and cost considerations. Funding will come from property taxes, special assessments based on residential equivalent units (REUs), City utility funds, and the Pedestrian and Cyclist Safety (PACS) Fund for sidewalks. Resident feedback indicated concerns about traffic speed and motorist behavior but also varied opinions on the need for sidewalks.

The project complies with the City’s Living Streets Policy, Vision Edina’s mission statement to 'provide effective and valued public services' and 'maintain a sound public infrastructure' and the 'Strong Foundations' City budget goal.

Andrew Scipioni/Transportation Planner [None]
Prospect Knolls A/C/D Roadway Reconstruction Project (Report for Oct 23, 2025 Meeting)

Staff seeks to balance the recommendations of the City’s guiding documents (Living Streets Plan, Pedestrian and Bicycle Master Plan and Climate Action Plan), feedback from affected residents, available right-of-way and potential tree and infrastructure impacts.

Andrew Scipioni/Transportation Planner [None]
Prospect Knolls A/C/D Roadway Reconstruction Project (Report for Oct 23, 2025 Meeting)

47.40% of the roadway costs will be funded through property taxes and 52.60% will be funded through special assessments at the following rates per residential equivalent unit (REU).

Andrew Scipioni/Transportation Planner [None]
Prospect Knolls A/C/D Roadway Reconstruction Project (Report for Oct 23, 2025 Meeting)
Source document

Meeting location:

Edina City Hall

Community Room

4801 W. 50th St.

Edina, MN

Transportation Commission Meeting Agenda

Thursday, October 23, 2025

6:00 PM

Accessibility Support:

The City of Edina wants all residents to be comfortable being part of the public process. If you need assistance in the way of hearing amplification,

an interpreter, large-print documents or something else, please call 952-927-8861 at least 72 hours in advance of the meeting.

1. Call to Order

2. Roll Call

3. Approval of Meeting Agenda

4. Approval of Meeting Minutes

4.1. Minutes

5. Community Comment

During "Community Comment," the Board/Commission will invite residents to share

issues or concerns that are not scheduled for a future public hearing. Items that are on

tonight's agenda may not be addressed during Community Comment. Individuals must

limit their comments to three minutes. The Chair may limit the number of speakers on

the same issue in the interest of time and topic. Individuals should not expect the Chair or

Board/Commission Members to respond to their comments tonight. Instead, the

Board/Commission might refer the matter to staff for consideration at a future meeting.

6. Reports/Recommendations

6.1. Prospect Knolls A/C/D Roadway Reconstruction Project

6.2. Parklawn Court Roadway Reconstruction Project

6.3. South Truck Sanitary Sewer Project

6.4. Traffic Safety Report of October 1, 2025

6.5. SEMAP Update

6.6. Initiative #5: City Code Sec. 26-282

Page 1 of 275

6.7. 2025 Work Plan Updates

6.8. 2026/2027 Work Plan Update

7. Staff Comments

7.1. Transportation Projects Update

8. Chair and Member Comments

9. Adjournment

Page 2 of 275

BOARD & COMMISSION

ITEM REPORT

Item Activity: Approve

Prepared By: Andrew Scipioni, Transportation Planner

Department: Engineering

Date: October 23, 2025

Meeting: Transportation Commission

Agenda Number: 4.1

Item Type: Minutes

Item Title:

Minutes

Action Requested:

Approve the minutes of the Transportation Commission's September 18, 2025 regular meeting.

Information/Background:

See attached draft minutes.

Supporting Documentation:

1.

Draft Minutes: Sept 18, 2025

Page 3 of 275

Draft Minutes☒

Approved Minutes☐

Approved Date:

Minutes

City Of Edina, Minnesota

Transportation Commission

City Hall Community Room

September 18, 2025

1. Call to Order

Chair Lewis called the meeting to order at 6:11 p.m.

2. Roll Call

Answering roll call: Commissioners Bildsten, Brown, Rosen, Bracken, Lassig, Lewis

Absent: Commissioners Olson, Trueger, White

Staff present: Transportation Planner Andrew Scipioni

2.1 Welcome Commissioner Bracken

The Commission welcomed new Student Commissioners Bracken.

3. Approval of Meeting Agenda

Motion was made by Commissioner Bildsten and seconded by Commissioner Brown to approve the

amended agenda. All voted aye. Motion carried.

4. Approval of Meeting Minutes

Motion was made by Commissioner Rosen and seconded by Commissioner Wright to approve the

August 21, 2025 meeting minutes. All voted aye. Motion carried.

5. Community Comment

None.

6. Reports/Recommendations

6.1. City Code Review

The Commissioner reviewed and commented on proposed changes to City Code relating to the

Transportation Commission.

6.2. 2025 Work Plan Updates

1. Safe and Equitable Mobility Action Plan Participation – PMT met this week, safety analysis and

prioritization framework are in progress.

2. Commission-Led Events – Committee will participate in Concord Elementary’s bike/walk to

school day on October 8. City will provide bike lights and bells to distribute.

3. Review of City Policies/Ordinances – No update.

4. City Code Update – Commission reviewed draft updates.

Page 4 of 275

Draft Minutes☒

Approved Minutes☐

Approved Date:

5. City Code Regarding Bicycles – Committee is drafting a report and recommendations to City

Council; will review with Commission next month.

6.3. 2026/2027 Work Plan Proposal

The Commissioner continued to discuss their work plan proposal and ranked initiatives as follows:

1. Continued SEMAP Working Group Participation

2. Traffic Safety Standards/Warrants Review and Playbook for Decision Making and Resident

Communication

3. Innovative Traffic Calming Solutions and “Towards Zero Deaths” Pilot Program (with Seasonal

Adaptations)

4. Transportation Segment of Comprehensive Plan

Motion was made by Commissioner Brown and seconded by Commissioner Bildsten to approve

the 2026/2027 work plan proposal. All voted aye. Motion carried.

7. Staff Comments – Received.

7.1. Transportation Projects Update

Staff provided an update on current and upcoming transportation projects in and around Edina.

7.2. 2025 Meeting Dates

The Commission’s next regular meeting is Thursday, October 23.

7.3. Proposed 2026 Meeting Dates

Staff provided the proposed regular meeting dates for 2026.

8. Chair and Member Comments – Received.

9. Adjournment

Motion was made by Commissioner Rosen and seconded by Commissioner Brown to adjourn the

September 18, 2025 regular meeting at 7:50 p.m. All voted aye. Motion carried.

Page 5 of 275

Draft Minutes☒

Approved Minutes☐

Approved Date:

TRANSPORTATION COMMISSION ATTENDANCE

J F M A M J J A S O N D

# of Mtgs

Attendance %

Meetings

1 1 1 1 1 1 1 1 1

SEAT

NAME

1

2

3

4

5

6

7

8

9

Wright, Grant

VACANT

Bildsten, Roger

Lewis, Andy

Rosen, Adam

Brown, Chris

Olson, Bethany

White, Joan

Trueger, Noah

10

11

Lassig, Augie (s)

Bracken, Logan (s)

1 1 1 1 1 1 1 1 1

1 1 1 1 1 1 1 1 1

1 1 1 1 1

1 1 1

1 1 1 1 1

1 1 1

1 1 1

1 1 1

1

1 1 1 1

1 1 1

1 1

1 1 1

1

1

1 1

1 1 1 1

1

1

9

9

9

8

8

7

7

5

2

7

1

100%

100%

89%

89%

78%

78%

71%

22%

78%

100%

Page 6 of 275

Date: October 23, 2025

Meeting: Transportation Commission

Agenda Number: 6.1

Item Type: Report and Recommendation

BOARD & COMMISSION

ITEM REPORT

Item Activity: Discussion

Prepared By: Andrew Scipioni, Transportation Planner

Department: Engineering

Item Title:

Prospect Knolls A/C/D Roadway Reconstruction Project

Action Requested:

Review and comment on the proposed 2026 roadway reconstruction project.

Information/Background:

Assistant City Engineer Aaron Ditzler, Senior Project Engineer Ben Jore and Graduate Engineer Chris

Moore will present the Prospect Knolls A/C/D roadway reconstruction project. See attached draft

engineering study.

Supporting Documentation:

1.

2.

Draft Engineering Study

Appendices

Page 7 of 275

ENGINEERING STUDY

PROSPECT KNOLLS A, C, & D NEIGHBORHOOD

ROADWAY RECONSTRUCTION

West 70th Street, Antrim Court, Antrim Road, Antrim Terrace,

Down Road, Dublin Circle, Dublin Road, Fleetwood Drive,

Kemrich Drive, Kerry Road, Lanham Lane, Lee Valley Circle, Lee

Valley Road, Shannon Drive, Tara Road, Tralee Drive, Village

Drive, Weston Circle, Wexford Road

IMPROVEMENT NO. BA-458

October 17, 2025

ENGINEERING DEPARTMENT

CITY OF EDINA

I hereby certify that this report was prepared by me or under my

direct supervision and that I am a duly Licensed Professional

Engineer under the laws of the State of Minnesota.

_______________

Aaron Ditzler Reg. No. Date

Page 8 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

SUMMARY:

The project involves reconstruction of local bituminous streets, replacement of

existing concrete curb and gutter, installation of new concrete curb and gutter,

construction of new concrete sidewalks, lining of sanitary sewer, localized

rehabilitation of the sanitary sewer, watermain, and storm sewer systems in the

neighborhood. Watermain improvements adjacent to the Dublin Reservoir (located

along Dublin Road) are also included in this project that will increase the efficiency of

the reservoir.

The estimated total project cost is $X_________. 47.40% of the roadway costs will

be funded through property taxes and 52.60% will be funded through special

assessments at the following rates per residential equivalent unit (REU).

Assessment

District

1

2

3

Preliminary

Assessment per

REU

$X_________

$X_________

$X_________

INITIATION:

LOCATION:

Utility improvements amount to $X_________ and will be funded through the City’s

utility funds. Sidewalk improvements are estimated to cost $X_________ and will

be funded through the Pedestrian and Cyclist Safety (PACS) Fund.

The project was initiated by the Engineering Department as part of the City’s

Neighborhood Reconstruction Program, identified in the Capital Improvement Plan.

The project complies with the City’s Living Streets Policy, Vision Edina’s mission

statement to “provide effective and valued public services” and “maintain a sound

public infrastructure” and the “Strong Foundations” City budget goal. This project

addresses updating substandard infrastructure with improvements associated with the

roadway condition, watermain system, storm sewer system, sanitary sewer system

and pedestrian facilities.

The project includes West 70th Street, Antrim Court, Antrim Road, Antrim Terrace,

Down Road, Dublin Circle, Dublin Road, Fleetwood Drive, Kemrich Drive, Kerry Road,

Lanham Lane, Lee Valley Circle, Lee Valley Road, Shannon Drive, Tara Road, Tralee

Drive, Village Drive, Weston Circle, and Wexford Road. A detailed location map of the

project is shown in Figure 1.

2

Page 9 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

Figure 1: Project Area Map

3

Page 10 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

EXISTING

CONDITIONS:

Roadways

The roadways in the Prospect Knolls A, C, and D neighborhood were originally

constructed between 1958 and 1990 (see Photo 1).

Photo 1: Prospect Knolls A/C/D Neighborhood, 1969

Approximately 2/3 of roadways in the project area have existing curb and gutter,

primarily the streets east of and including Antrim Court, Antrim Terrace and Shannon

Drive. The average roadway width is 28 feet (measured from the face of curb to the

face of curb or edge of pavement). The roadways located south and west of Village

Drive are privately owned and maintained. A recent geotechnical evaluation of the

project area shows the roadway section varies from 1.75 inches to 8 inches of

bituminous pavement and 3.0 inches to 23.75 inches of aggregate base, over a poorly

graded sand and silty sand base.

As part of the City’s Pavement Management Program, all streets are regularly

evaluated and rated on a scale from 1 to 100; 100 representing a brand-new road

surface and 0 being extremely poor. This rating is referred to as the Pavement

Condition Index (PCI), and is determined based on existing conditions and defects

(alligator cracking, raveling, potholes, etc.). The average PCI for the City of Edina is

4

Page 11 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

78 and the average PCI for Prospect Knolls A/C/D is 25. An example of the current

pavement condition can be seen in Photo 2.

Photo 2: Existing Pavement Condition

The existing geometry of the intersections at Kerry Road/Wexford Road and

Wexford Road/Down Road creates a large radius and wide pavement on the

southeast side of Wexford Road between the Down Road and Kerry Road

intersections. This allows southbound vehicles on Kerry Road that turn onto

Wexford Avenue and then take an immediate left onto Down Road to comfortably

maneuver through the two intersections at speeds higher than typical or desirable for

conventional intersections. The existing geometry of this intersection is shown in

Figure 2.

5

Page 12 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

Figure 2: Kerry Rd/Wexford Rd and Wexford Rd/Down Rd Intersections

(Existing Conditions)

The intersection of Down Road and Lee Valley Road is currently not centered in the

right-of-way and City employees have stated the intersection is hard to maneuver

with snow plows. The existing geometry of this intersection is shown in Figure 3.

Figure 3: Down Rd / Lee Valley Rd Intersection (Existing Conditions)

6

Page 13 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

Driveways

There are many unique driveways throughout the project area which include brick

pavers and colored concrete. Photo 3 shows an example of a driveway with brick

pavers in the project area.

Photo 3: Brick Paver Driveway

Cul-de-Sacs

There are nine cul-de-sacs within the project area. Six (Antrim Court, Antrim

Terrace, Dublin Circle, Shannon Drive, Tara Road and Weston Circle), have

existing curb and gutter. Two (Antrim Court and Shannon Drive), have center

islands that contain trees, boulders and landscaping. Four cul-de-sacs’ diameters are

smaller than the City’s standard diameter of 70’ and four are larger than the

standard diameter.

Traffic and Crash Data

Staff measured traffic volumes and speeds at several locations within or near the

neighborhood. Average daily traffic volumes within the neighborhood range between

291 and 754 vehicles per day with 85th percentile speeds between 25.2 and 29 miles

per hour. Traffic and crash data for this project is shown in Appendix A.

Landscaping

Numerous property owners have landscaping within the right of way. Many of

these landscape items are located directly behind the curb. Some of these landscape

7

Page 14 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

items will need to be removed in order to complete the necessary reconstruction

work. Photo 4 shows a typical landscaping feature found in the project’s right of

way.

Photo 4: Landscaping within ROW

Multi-Modal Transportation

Pedestrian Facilities

There are no pedestrian facilities within the project area. There are existing sidewalks

immediately adjacent to the project area on Dewey Hill Road, West 70th Street,

Antrim Road and Cahill Road. (see Appendix B). Additionally, a trail exists around

Lewis Park adjacent to the project area, including a trail entrance spur at the

intersection of Kemrich Drive and Tara Road.

Bicycle Facilities

There are no bicycle facilities within the project area; however, there are existing bike

lanes immediately adjacent to the project area on Antrim Road, West 70th Street and

Cahill Road (see Appendix C).

Transit Facilities

There are no transit facilities within the project area. Metro Transit’s Local Routes 6

and 540 operate within ½ mile of the project area on Cahill Rd and Dewey Hill Rd.

Public Utilities

Sanitary Sewer

SECTION INCOMPLETE

Watermain

8

Page 15 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

SECTION INCOMPLETE

Storm Sewer

SECTION INCOMPLETE

DESIGN INPUT:

Private Utilities

Gas, electric, communications, cable and fiber optic utilities are present in the

neighborhood. These utilities are a combination of overhead and underground

facilities located in backyards or along the boulevards. Street lighting within the

project area consists of standard “cobra head” fixtures mounted on wooden poles

and lantern-style fixtures mounted on fiberglass poles as shown in Appendix E. All

lighting is owned by Xcel Energy.

City Council

2018 Pedestrian and Bicycle Master Plan

This plan, part of the draft 2018 Comprehensive Plan, was developed to guide the

City’s efforts to create a comprehensive pedestrian and bicycle network. As shown

in Appendix B, a sidewalk is proposed along Shannon Drive between Dewey Hill Road

and Kemrich Drive, Kemrich Drive between Shannon Drive and Fleetwood Drive,

Fleetwood Drive, and Lanham Lane between Fleetwood Drive and West 70th Street.

Appendix C shows no proposed bicycle facilities within the project area.

2015 Living Streets Policy

This policy balances the needs of motorists, pedestrians, bicyclists and transit riders

in ways that promote safety and convenience, enhance community identity, create

economic vitality, improve environmental sustainability and provide meaningful

opportunities for active living and better health. The City will apply the Policy to all

street projects, including those involving operations, maintenance, new construction,

reconstruction, retrofits, repaving, rehabilitation or change in the allocation of

pavement space on an existing roadway. The Living Streets Plan includes 15 principles

to guide implementation of the Policy, divided into four categories: All Users and All

Modes, Connectivity, Context Sensitivity and Sustainability. Below is a summary of

how these principles are incorporated into this project:

All Users and All Modes – This project will improve mobility and access to the

transportation network for a variety of users, including pedestrians, cyclists, children,

seniors and the disabled. Replacement of the pavement surfaces and traffic control

signage will enhance safety and convenience for all users.

Connectivity – This project involves maintaining a transportation system that can

accommodate all modes of travel.

Context Sensitivity – Engineering strives to preserve and protect natural features

within or adjacent to construction sites where feasible, including trees, waterways

and sensitive slopes. Residents within the project area were invited to complete a

questionnaire soliciting input on project design components, including multi-modal

transportation and local drainage problems.

9

Page 16 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

Sustainability – Engineering works closely with Public Works to implement

infrastructure improvements with consideration of lifecycle costs and future

maintenance. The new roadway section can be easily maintained long-term with the

use of proactive rehabilitation treatments, which will significantly extend the life of

the pavement. Reductions in impervious surfaces benefit water quality, and may lessen

the demand for chemicals to manage snow and ice (such as chloride). Construction

operations are required to use the smallest footprint necessary to complete the work;

this includes utilizing trenchless technologies, such as pipe bursting or cured-in-place

pipe liners. This project will also reduce inflow and infiltration of clean water into the

sanitary sewer system, minimizing regional wastewater treatment, reducing the risk

of sewage surcharges and limiting the risk of back-ups to residential properties.

Relevant portions of the Living Streets Plan can be found in Appendix F.

Water Resource Management Plan (December 2022 Amendment)

SECTION INCOMPLETE

Climate Action Plan

The CAP identified the following strategies that align with this roadway

reconstruction project.

Transportation and Land Use (TL) 1: Decrease community-wide vehicle miles traveled

by 7% by 2030.

Action TL 1-2: Accelerate building on-street and off-street protected bike lanes,

sidewalks, crosswalks, and other walking infrastructure in high-need areas and fill

connectivity gaps as identified in the City's Bike and Pedestrian Master Plan.

TL 2: Double public transit commuter ridership from 3.3% to 6.6% by 2030.

Staff

Public Works

A draft engineering study was provided to the City’s Public Works Department.

COMMENTS REQUESTED

Police and Fire

A draft engineering study was provided to the City’s Police and Fire Departments.

COMMENTS REQUESTED

Edina Transportation Commission

Prior to the Edina Transportation Commission (ETC) regular meeting on October

23, 2025, a draft engineering study was provided for review.

[2025 COMMENTS]

Residents

As part of the Engineering Department’s practice of notifying residents 2-3 years prior

to a potential reconstruction project, residents were invited to numerous in person

or virtual open houses between September 2017 and August 2025. Residents were

10

Page 17 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

invited to an informational presentation and were able to directly ask questions to

staff in August 2025. Residents were notified of a recorded video version of the

August 2025 informational presentation posted on the Better Together Edina website,

where residents were able to ask questions to staff from the Better Together Edina

website, as well as telephone and email. Materials from the August 2025 informational

presentation can be found in Appendix I.

On June 25, 2025, residents were asked to complete a questionnaire, soliciting

feedback on motorized and non-motorized transportation and local drainage

problems within the project area. The questionnaire was completed by 74 of 283

property owners, a return rate of 26%.

The following is a summary of feedback received from residents:

• 25 of 74 (34%*) were concerned or very concerned with the speed of traffic

in the neighborhood; 49 (66%) were not concerned.

• 8 of 74 (11%*) were concerned or very concerned with the volume of traffic

or number of vehicles in the neighborhood; 65 (89%) were not concerned.

• 23 of 74 (31%*) concerned or very concerned with motorist behavior in the

neighborhood; 51 (69%) were not concerned.

• 34 of 74 (47%) identified an unsafe intersection within the neighborhood.

• 45 of 74 (76%) walk, run, or jog in the neighborhood at least 2-3 times per

week.

• 22 of 74 (31%) ride a bicycle in the neighborhood at least 2-3 times per week.

• 5 of 74 (7%) reported parking on the street at least 2-3 times per week;

56 (77%) reported parking on the street less than once per month.

• 10 of 74 (14%) identified localized drainage problems in the neighborhood.

*Percentages based on number of returned surveys

The full questionnaire and responses can be found in Appendix J.

Relevant correspondence from residents regarding the project can be found in

Appendix K.

The proposed improvements acknowledge many of the comments and concerns

raised by residents throughout the information gathering process, while still

maintaining the desired minimum standards of Engineering, Public Works and other

City staff. The proposed improvements also align with the Budget Work Plan values

and goals developed by the City Council and staff.

Roadways

Typical Section

The bituminous roadways are proposed to be completely reconstructed to the

subgrade. The existing bituminous pavement and suitable aggregate material will be

recycled for use as base material in the new roadway where feasible. A minimum of

8” of aggregate base material will be graded and compacted as the base layer prior to

placement of 2.5” of bituminous non-wear and 1.5” of bituminous wear course.

11

PROPOSED

IMPROVEMENTS:

Page 18 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

Unsuitable subgrade materials will be replaced as necessary to provide adequate

support for the new roadbed. Significant subgrade removals may occur where areas

of clay soils are present. The reconstructed sections will meet the requirements of a

minimum 20-year pavement design life based on projected traffic loadings.

All roadways within the project area are designated as Local Streets in the Living

Streets Plan. Per this plan’s design guidelines, Local Streets have concrete curb and

gutter and a typical width of 27’ (measured from the face of curb to the face of curb)

without sidewalks or 24’ with a 5’ sidewalk on one side. Local streets that vary from

the guidelines are as follows:

• Kerry Road will be reconstructed to a 24-foot width to minimize impacts on

mature trees and existing retaining walls, and to account for the steep slopes

present in the boulevards.

• Village Drive will be reconstructed to 30 feet to accommodate additional

parking and to match the privately owned and maintained street widths south

and west of Village Drive.

Parking

Per the Living Streets Plan, on-street parking should be evaluated based on

classification, adjacent land uses, existing demand and costs of construction and

maintenance.

One-sided parking is proposed on Fleetwood Drive, Kemrich Drive, Shannon Drive

between Dewey Hill Road and Fleetwood Drive, and Lanham Lane between

Fleetwood Drive and West 70th Street due to the proposed pedestrian facilities (see

pedestrian facilities below). One-sided parking is also proposed on Kerry Drive due

to the proposed 24’ street width. Given the existing demand for parking, staff believes

that parking changes should not occur on any other streets in the project area.

The existing and proposed street widths and parking recommendations are shown in

Figure 7 through 10, Table 1 and Appendix L.

12

Page 19 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

Figure 7: Streets with sidewalk: Shannon Drive between Dewey Hill

Road and Kemrich Drive, Kemrich Drive, Fleetwood Drive, and Lanham

Lane between Fleetwood Drive and West 70th Street

Figure 8: Streets without sidewalk: West 70th Street, Antrim Court,

Antrim Road, Antrim Terrace, Down Road, Dublin Circle, Dublin Road,

Lanham Lane between Kemrich Drive and Fleetwood Lane, Lee Valley

Circle, Lee Valley Road, Shannon Drive north of Kemrich Drive, Tara

Road, Tralee Drive, Weston Circle, Wexford Road

13

Page 20 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

Figure 9: Kerry Road

Figure 10: Village Drive

14

Page 21 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

Street

Name

W. 70th St

Antrim Ct

Antrim Rd

Antrim Ter

Down Rd

Dublin Cir

Dublin Rd

Fleetwood Dr

Kemrich Dr

Kerry Rd

Lanham Ln

betw.

Kemrich Dr

and

Fleetwood Dr.

Lanham Ln

betw.

Fleetwood Dr.

and W. 70th

St.

Lee Valley Cir

Lee Valley Rd

Shannon Dr,

between

Dewey Hill Rd

and Kemrich

Dr

Shannon Dr

north of

Kemrich Dr

Tara Rd

Tralee Dr

Village Dr

Weston Cir

Wexford Rd

Existing

Roadway

Width¹

(face to

face), feet

25-27

27

26-28

27

26-30

29.5

25-28

27.5

27.5

24-26

Existing

Curb Type

N/A

Surmountable

N/A

Surmountable

N/A

B618

N/A

Surmountable

Surmountable

N/A

Proposed

Roadway

Width

(face to

face), feet

27

27

27

27

27

27

27

24

24

24

27.5

Surmountable

27

27.5

29.5

28-30

Surmountable

B618

N/A

24

27

27

27.5

Surmountable

24

27.5

27

29-30

29.5

27.5

24-28

Surmountable

Surmountable

N/A

B618

Surmountable

N/A

27

27

27

30

27

27

Sidewalk,

feet

Boulevard

Width,

feet

Proposed

Parking

-

-

-

-

-

-

-

5

5

-

-

5

-

-

5

-

-

-

-

-

-

-

-

-

-

-

-

-

0-5

0-5

-

Two-sided

Two-sided

Two-sided

Two-sided

Two-sided

Two-sided

Two-sided

One-sided

One-sided

One-sided

-

Two-sided

0-5

-

-

One-sided

Two-sided

Two-sided

0-5

One-sided

-

-

-

-

-

-

Two-sided

Two-sided

Two-sided

Two-sided

Two-sided

Two-sided

¹Existing roadway width is measured from edge of bituminous to edge of bituminous

on streets with no curb and gutter

Table 1: Street Widths and Parking

The intersections of Kerry Road/Wexford Road and Wexford Road/Down Road are

proposed to closely match the existing geometry, with changes limited to about one

15

Page 22 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

or two feet. A double yellow pavement marking stripe will be added to the

intersections, discouraging drivers from crossing over the centerline.

The proposed geometry of the Down Road and Lee Valley Road intersection is shown

in Figure 11. The proposed roadway will move west from its existing location to be

more centered within the right of way. However, the roadway may only move

approximately 1–3 feet due to existing retaining walls and power pole guy wires on

the west and southwest side of the roadway. The widths of Down Road and Lee

Valley Road are proposed to be 27 feet from face of curb to face of curb. The width

of the roadway through the curve is proposed to be 30 feet in order to help snow

plow drivers maneuver the turn easier. The southern curb line through the curve is

proposed to receive surmountable curb so snow plows can safely and easily push

snow into the boulevard.

Figure 11: Proposed Down Rd/Lee Valley Rd Intersection

Roadway Signage

All traffic signage within the project area, including street name blades, will be replaced

to improve visibility and reflectivity (see Appendix E). All new signs will conform to

the standards of the Manual on Uniform Traffic Control Devices (MUTCD).

Driveways

Driveways will be affected by construction and will be reconstructed. The unique

driveways throughout the project area, including brick pavers, will be re-laid with the

intent to replicate existing conditions to the extent practicable.

Cul-de-Sacs

Due to the location of existing retaining walls, utility poles, large trees, and available

right-of-way, no significant change to the size and geometrics of the cul-de-sacs are

proposed. Minor geometric changes are proposed to allow for better turning

movements where feasible.

16

Page 23 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

Landscaping

Any landscaping disturbed by construction will be replaced with the intent to replicate

existing conditions to the extent practicable.

Multi-Modal Transportation

Staff seeks to balance the recommendations of the City’s guiding documents (Living

Streets Plan, Pedestrian and Bicycle Master Plan and Climate Action Plan), feedback

from affected residents, available right-of-way and potential tree and infrastructure

impacts.

Staff is proposing new sidewalks on the following streets as recommended in the

Pedestrian and Bicycle Master Plan:

• The east side of Shannon Dr from Dewey Hill Rd to Kemrich Dr

• The north side of Kemrich Dr from Shannon Dr to Fleetwood Dr

• The west side of Fleetwood Dr, and

• The south / west side of Lanham Ln between Fleetwood Dr and W 70th St

Staff is also proposing a new sidewalk on the north side of Kemrich Dr between

Fleetwood Dr and Tara Rd. This sidewalk is not included in the Pedestrian and

Bicycle Master Plan, but will connect the other proposed sidewalks to the trail at

Lewis Park. Figure 12 shows all existing and proposed pedestrian facilities (also

detailed in Table 1 above).

17

Page 24 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

Figure 12: Existing and Proposed Pedestrian Facilities

The benefits of these sidewalks include:

• Connection to existing and proposed multi-modal facilities on Dewey Hill

Rd and W 70th St

Improving access to Valley View Middle School and Edina High School

Improving access to Lewis Park

Improving access to adjacent transit facilities

18

Page 25 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

Locations were selected by staff based on existing topography, connections to

existing facilities and private utility conflicts, and maintenance. The grass boulevards

that will separate the new curb and the proposed sidewalks is proposed to be 5’-

wide but may vary depending on construction conflicts. Separation from vehicle

traffic creates a more pedestrian-friendly environment and is preferred by Public

Works for snow storage. The extra width needed for the sidewalks and boulevards

will be balanced between both sides of the street, where feasible.

All adjacent pedestrian curb ramps will be reconstructed to meet the current design

standards of the Americans with Disabilities Act (ADA), and portions of the existing

sidewalks will be reconstructed as necessary.

As the proposed sidewalk segments are not along Municipal State Aid routes,

adjacent to City property nor included in the City’s Active Routes to School Plan,

they will be maintained by the adjacent property owners.

Bicycle Facilities

There are no proposed bicycle facilities in this project area.

Public Utilities

Sanitary Sewer

SECTION INCOMPLETE

Watermain

COMMENTS REQUESTED

Storm Sewer

COMMENTS REQUESTED

Private Utilities

Staff will meet with representatives of several private utility companies in December

2025, to discuss the proposed 2026 reconstruction project and preliminary

improvements. Portions of the private utility networks may receive upgrades prior to

construction; however, this work is not part of the City’s project.

Currently, the City does not have a standard to determine where and when street

lighting should be improved. Unlike other infrastructure improvements, lighting can

be installed at a later date with minimal disturbance through the use of trenchless

technologies. The lighting in the neighborhood is sufficient to delineate the

intersections; therefore, staff is recommending no revisions to the current street

lighting.

RIGHT-OF-WAY/

EASEMENTS:

Existing right-of-way in this neighborhood varies from 40’ to 60’. It is anticipated that

the majority of this project can be constructed within existing ROW; temporary

construction easements may be required for utility improvements within existing

permanent easements.

19

Page 26 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

Many properties have special mailboxes, retaining walls, vegetation, boulders or other

landscaped items within the right-of-way. A portion of these landscape items will

interfere with some of the proposed infrastructure improvements and will need to

be removed to complete the necessary work.

PROJECT COSTS:

The total estimated project cost is $_________, (see Table 2). The total cost

includes direct costs for engineering, clerical and construction finance costs from the

start of the project to the final assessment hearing.

Item

Amount

Total Cost

Assessment District 1

$ _______

Assessment District 2

$ _______

Assessment District 3

$ _______

Roadway

$ _______

Funding

Source

Special

Assessments

Special

Assessments

Special

Assessments

Property

Taxes

Roadway Total:

Sanitary Sewer

Watermain

Storm Sewer

Utility Total:

Sidewalk Total:

Project Total:

$ _______

$ _______

$ _______

$ _______

$ _______

$ _______

$ _______

City Utility

Funds

PACS Fund

Table 2: Estimated Project Costs

ASSESSMENTS:

Assessments will be levied against the benefiting adjacent properties pursuant to

Chapter 429 of the Minnesota State Statutes. Based on the City’s Special Assessment

Policy, there are 231.67 roadway residential equivalent units (REUs) in the Prospect

Knolls A/C/D project area. The estimated assessment per REU is shown in Table 3,

and the assessment districts are shown in Figure 13. The preliminary assessment roll

can be found in Appendix M.

Assessment

District

1

2

3

REUs

58.67

153

20

Preliminary Assessment per

REU

$ _______

$ _______

$ _______

Table 3: Summary of Total REUs and Assessments

20

Page 27 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

Figure 13: Preliminary Roadway Assessment Map

21

Page 28 of 275

Engineering Study

Prospect Knolls A, C, & D Neighborhood Roadway Reconstruction BA-458

October 17, 2025

PROJECT SCHEDULE:

The following schedule outlines the past and future tasks to be performed related to

the project:

Neighborhood Open House (all 2019/2020 projects)

Neighborhood Open House (all 2020/2021 projects)

Neighborhood Informational Meeting (all 2020 projects)

Public Hearing (all 2020 projects)

City Council Rejects Prospect Knolls A 2020 Project

Neighborhood Informational Video Presentations (all 2024

and Future projects)

Neighborhood Informational Open House

ETC Engineering Study Review

Receive Engineering Study

Open Public Improvement Hearing

Close Public Improvement Hearing

Public Improvement Hearing Council Decision

Bid Opening

Award Contract/Begin Construction

Complete Construction

Final Assessment Hearing

Table 7: Project Timeline

September 25, 2017

September 24, 2018

August 12, 2019

December 9, 2019

January 7, 2020

Fall 2022

August 26, 2025

October 23, 2025

December 8, 2025

December 8, 2025

December 10, 2025

December 16, 2025

March/April 2026

Spring 2026

Fall 2026

October 2027

RECOMMENDATION:

Staff believes the project can be completed during the 2026 construction season. Staff

believes the construction of this project is feasible, cost effective and necessary to

improve the public infrastructure in the Prospect Knolls A, C, and D neighborhood.

APPENDIX:

A. Traffic and Crash Data

B. Comprehensive Plan Update – Pedestrian Facilities

C. Comprehensive Plan Update – Bicycle Facilities

D. Sewer Blocks and Watermain Breaks

E. Street Lights and Signs

F. Living Streets Plan

G. Edina Transportation Commission Meeting Minutes

H. Edina Transportation Commission Advisory Communication

I. Neighborhood Informational Presentation Materials

J. Resident Questionnaire

K. Correspondence from Residents

L. Proposed Typical Sections

M. Preliminary Assessment Roll

22

Page 29 of 275

APPENDIX A

Traffic and Crash Data

Page 30 of 275

Prospect Knolls Traffic Counts

Location

ADT

85% Speed

Peak

Date

W 70th

Antrim Rd

Lee Valley Rd

Shannon Dr

Fleetwood Dr

Lanham Ln

Kemrich Dr

332

395

622

307

754

291

577

539

378

N/A

36 – 2:30 PM

September 2019

N/A

26.2 MPH

43 – 3:30 PM

September 2019

August 2001

N/A

33 – 3:30 PM

September 2019

28.4 MPH

76 – 5:00 PM

September 2019

28.1 MPH

30 – 3:15 PM

May 2024

28.2 MPH

25.2 MPH

57 – 5:00

50 – 6:00

29 MPH

N/A

July 2007

July 2007

May 2011

Page 31 of 275 Traffic Safety Requests May 2018-Present

3

1

2

1

2

3

March 2025

Stop sign visibility

Under review

March 2022

Stop sign

No action

April 2023

Cut thru/speed complaints

No action

Page 32 of 275 Reported Crashes 2015-Present

1

2

3

#

1

2

3

Crash Type

Info

Date

Sideswipe – No injuries

Driver fleeing police

July 2020

Ran off road

Drunk driver

August 2018

Ran off road – property damage

Icy roadway

January 2017

Page 33 of 275 APPENDIX B

City Comprehensive

Plan Update –

Pedestrian Facilities Map

Page 34 of 275

Legend

Existing Sidewalk

Proposed Twin Loops

Proposed Sidewalk

Existing Shared-Use Path

Proposed Shared-Use Path

Nine Mile Creek Regional Trail

Proposed CP Rail Regional Trail

Weber

Park

44TH ST W

MALONEY AVE

Van Valkenburg

Park

INTERLACHEN BLVD

D

R

R

E

F

E

A

H

C

S

Mirror

Lake

D

R

E

K

A

L

B

VERNON AVE

D

R

N

O

S

A

E

L

G

Bredesen

Park

Mud

Lake

Arrowhead

Lake

Indianhead

Lake

Edina

High

School

VALLEY VIEW RD

Todd

Park

d

a

o

r

l

i

a

R

c

i

f

i

c

a

P

n

a

i

d

a

n

a

C

Highlands

Park

ON AVE

VERN

Yancey

Park

Melody

Lake

D

R

N

E

S

N

A

H

E

V

A

Y

C

A

R

T

MinnehahaCreek

City

Hall

50TH ST W

Arden

Park

E

V

A

E

L

A

D

D

O

O

W

54TH ST W

Edina

Community

Center

58TH ST W

Pamela

Park

VALLEY VIEW RD

Rosland

Park

66TH ST W

Lake

Cornelia

D

R

W

E

I

V

Y

E

L

VAL

70TH ST W

NineMileCreek

70TH ST W

Arneson

Acres

Park

Southdale

Library

Braemar

Arena

Braemar

Golf

Course

NineMile Creek

Lewis

Park

DEWEY HILL RD

d

a

o

r

l

i

a

R

c

i

f

i

c

a

P

n

a

i

d

a

n

a

C

D

R

L

L

I

H

A

C

78TH ST W

Lake

Edina

Public

Works

Fred

Richards

Park

76TH ST W

S

E

V

A

E

C

N

A

R

F

S

E

V

A

K

R

O

Y

Centennial

Lakes

MINNESOTA DR

City of Edina

Existing and Proposed Pedestrian Facilities

±

October 2022

Feet

0

2,250

Page 35 of 275

APPENDIX C

City Comprehensive

Plan Update –

Bicycle Facilities Map

Page 36 of 275

Legend

Advisory Bike Lane

Existing Bike Boulevard

Bikeable Shoulder

Existing Shared Bike Lane

Existing Bike Lane

Existing Buffered Bike Lane

Existing Shared-Use Path

Nine Mile Creek Regional Trail

Proposed Twin Loops

Proposed Bike Boulevard

Proposed Bike Lane

Proposed Buffered Bike Lane

Proposed Shared-Use Path

Proposed CP Rail Regional Trail

Weber

Park

44TH ST W

MALONEY AVE

Van Valkenburg

Park

INTERLACHEN BLVD

D

R

R

E

F

E

A

H

C

S

Mirror

Lake

D

R

E

K

A

L

B

VERNON AVE

D

R

N

O

S

A

E

L

G

Bredesen

Park

Mud

Lake

Arrowhead

Lake

Indianhead

Lake

Edina

High

School

VALLEY VIEW RD

Todd

Park

d

a

o

r

l

i

a

R

c

i

f

i

c

a

P

n

a

i

d

a

n

a

C

Highlands

Park

ON AVE

VERN

Yancey

Park

Melody

Lake

D

R

N

E

S

N

A

H

E

V

A

Y

C

A

R

T

MinnehahaCreek

City

Hall

50TH ST W

Arden

Park

E

V

A

E

L

A

D

D

O

O

W

54TH ST W

Edina

Community

Center

58TH ST W

Pamela

Park

VALLEY VIEW RD

Rosland

Park

66TH ST W

Lake

Cornelia

D

R

W

E

I

V

Y

E

L

VAL

70TH ST W

NineMileCreek

70TH ST W

Arneson

Acres

Park

Southdale

Library

Braemar

Arena

Braemar

Golf

Course

NineMile Creek

Lewis

Park

DEWEY HILL RD

d

a

o

r

l

i

a

R

c

i

f

i

c

a

P

n

a

i

d

a

n

a

C

D

R

L

L

I

H

A

C

78TH ST W

Lake

Edina

Public

Works

Fred

Richards

Park

76TH ST W

City of Edina

Existing and Proposed Bicycle Facilities

S

E

V

A

E

C

N

A

R

F

S

E

V

A

K

R

O

Y

Centennial

Lakes

MINNESOTA DR

±

October 2022

Feet

0

2,250

Page 37 of 275

APPENDIX D

Sewer Blocks and

Watermain Breaks

Page 38 of 275

APPENDIX E

Street Lights and Signs

Page 39 of 275

Page 40 of 275 Page 41 of 275 APPENDIX F

Living Streets Plan

Page 42 of 275

Living Streets Plan 2015

Safety

Health

Choice

Economy

Page 43 of 275 2. Living Streets Policy

INTRODUCTION

The Living Streets Policy was developed to provide the framework for a Living Streets Plan. The policy

initially stood alone and included sections to guide the creation of the Living Street Plan. This revised

policy is now an integral part of the Living Streets Plan.

The Living Streets Policy ties directly to key community goals outlined in the City’s 2008 Comprehensive

Plan. Those goals include safe walking, bicycling and driving; reduced storm water runoff, reduced energy

consumption, and promoting health. The Living Streets Policy also compliments voluntary City initiatives

such the “do.town” effort related to community health, Tree City USA and the Green Step Cities programs

related to sustainability. In other cases, the Living Streets Policy will assist the City in meeting mandatory

requirements set by other agencies.

The Living Streets Policy is broken up into three

parts: Vision, Principles and Implementation. The

Policy is followed by a description of core services

provided by the City of Edina that are related to or

implemented in part through Living Streets.

Mini Fact

Expect cyclists on the road. Watch for

cyclists on the road. Treat them as you

would any slow-moving vehicle.

POLICY

Living Streets balance the needs of motorists,

bicyclists, pedestrians and transit riders in ways that promote safety and convenience, enhance community

identity, create economic vitality, improve environmental sustainability, and provide meaningful

opportunities for active living and better health. The Living Streets Policy defines Edina’s vision for Living

Streets, the principles Living Streets will embody, and the plan that will guide implementation of their

construction.

LIVING STREETS VISION

Edina is a place where ...

• Transportation utilizing all modes is equally safe and accessible;

• Residents and families regularly choose to walk or bike;

Streets enhance neighborhood character and community identity;

Streets are safe, inviting places that encourage human interaction and physical activity;

• Public policy strives to promote sustainability through balanced infrastructure investments;

• Environmental stewardship and reduced energy consumption are pursued in public and private

sectors alike; and

Streets support vibrant commerce and add to the value of adjacent land uses.

8

Living Streets Plan – 2. Living Streets Policy

Page 44 of 275 LIVING STREETS PRINCIPLES

Fifteen principles guide implementation of the Living Streets Policy in the areas of all users and all

modes, connectivity, context sensitivity and sustainability. The City will incorporate these principles when

planning for and designing the local transportation network and when making public and private land use

decisions.

All Users and All Modes

Principle 1: Living Streets are high-quality transportation facilities that meet the needs of

the most vulnerable users such as pedestrians, cyclists, children, seniors and

the disabled; and

Principle 2:

Living Streets provide access and mobility for all transportation modes while

enhancing safety and convenience for all users.

Connectivity

Principle 3: The City designs, operates and maintains a transportation system that provides

a highly connected network of streets that accommodate all modes of travel;

Principle 4: The City seeks opportunities to overcome barriers to active transportation by

preserving and repurposing existing rights-of-way and adding new rights-

of-way to enhance connectivity for pedestrians, bicyclists and transit;

Principle 5: The City prioritizes improvements to non-motorized connections to key

destinations such as public facilities, public transit, the regional transportation

network and commercial areas;

Principle 6: The City will require new developments to provide interconnected street and

Principle 7:

sidewalk networks that connect to existing or planned streets or sidewalks

on the perimeter of the development; and

Projects will include consideration of the logical termini by mode. For

example, the logical termini for a bike lane or sidewalk may extend beyond the

traditional limits of a street construction or reconstruction project, in order to

ensure multimodal connectivity and continuity.

Context Sensitivity

Principle 8:

Principle 9:

Living Streets are developed with input from stakeholders and designed to

consider neighborhood character and promote a strong sense of place;

Living Streets preserve and protect natural features such as waterways, urban

forest, sensitive slopes and soils;

Principle 10: Living Streets are designed and built with coordination between business and

property owners along commercial corridors to develop vibrant commercial

districts;

Living Streets Plan – 2. Living Streets Policy

9

Page 45 of 275

Principle 11: Living Streets coordinate with regional transit networks and regional

authorities; and

Principle 12: The City will consider the fiscal context of projects and potential financial

impacts when implementing Living Streets at the project level.

Sustainability

Principle 13: Living Streets will improve the current and future quality of life of the public,

Principle 14: Living Streets will reduce environmental impacts associated with the

construction and operation of roadways; and

Principle 15: The City will increase the life span and resilience of its infrastructure and will

build infrastructure with consideration for lifecycle costs and ease

of maintenance.

LIVING STREETS IMPLEMENTATION

The City of Edina will develop Living Streets in the regular course of business of maintaining, expanding

or redeveloping the road network and will be guided by the Vision and Principles established above.

Implementation will happen predominantly through the neighborhood street reconstruction program, but

also though specific stand-alone stormwater utility, pedestrian, bicycle or safety projects.

Project prioritization is not specifically part of the Living Streets Plan. Prioritization of projects takes

place in the City’s Capital Improvement Program and Budget and is determined by the City Council with

guidance from the Living Streets Vision and Principles.

The City will actively promote and apply the Living Streets Policy and Plan by:

• Applying the Living Streets Policy and Plan to all street projects, including those involving

operations, maintenance, new construction, reconstruction, retrofits, repaving, rehabilitation or

changes in the allocation of pavement space on an existing roadway. This also includes privately

built roads, sidewalks, paths and trails.

• Drawing on all sources of transportation funding and actively pursuing grants, cost-sharing

opportunities and other new or special funding sources as applicable.

• Through all City departments supporting the vision and principles outlined in this Plan in their

work.

• By acting as an advocate for Living Streets principles when a local transportation or land use

decision is under the jurisdiction of another agency.

Projects that implement Living Streets will be guided by pedestrian and cyclist network plans and roadway

classifications and will consider the physical, social, ecologic, regulatory and economic context in a given

project area.

10

Living Streets Plan – 2. Living Streets Policy

Page 46 of 275

The project delivery system used to build Living Streets will:

Systematically engage Edina residents and project stakeholders to better inform project-level

recommendations.

• Keep Edina residents and project stakeholders informed about Living Streets and the range of services

they help provide.

• Follow minimum Living Streets design requirements and standards.

• Manage construction impacts to residents and users of streets.

Network

The creation of a Living Streets network of road, pedestrian and bicycle facilities provides mobility,

accessibility and access to people, places and spaces. The resulting interconnection of neighborhoods links

people to goods and services and to one another, and increases quality of life for those who live in, work

in, or visit the city.

Existing and planned transportation networks are identified in the City of Edina Comprehensive Plan and

other approved/adopted plans. Network plans include:

• Roadway Network (Functional Classification, Jurisdictional Classification)

Sidewalk Facilities

• Bicycle Facilities (Comprehensive Bicycle Transportation Plan)

• Active Routes to School Comprehensive Plan

• Transit Service

Network plans are approved by the City Council. In most cases, modification requires an amendment of

the Comprehensive Plan.

The expansion, creation and improvement of pedestrian and bicycle networks will be well planned and

prioritized:

• Expansion of existing networks and providing connections to key traffic generators or destinations

provide immediate benefit to all network users and is a top priority.

• Network connections serving vulnerable users such as children, seniors and the disabled are a top

priority.

• Network connections serving high-volume uses such as schools, retail destinations or regional

public transit are a top priority.

Living Streets Plan – 2. Living Streets Policy

11

Page 47 of 275 Context

Contextual variety can either constrain or create opportunity in roadway and other infrastructure

projects. The following are contexts that will be considered and will influence the planning, design and

implementation of Living Streets.

Ecological

Regulatory

Operational

Project Type

CONTEXTS OF LIVING STREETS

Water resource, ponds, wetlands, lakes, streams

Natural resouces, trees, and urban forest

Air quality

Climate

Sun and shade

Materials, waste, energy, sustainability

State Aid roadway

Watershed rules

Maintenance operations

Traffic control or functional constraints

Neighborhood street reconstruction

Public

Neighborhood street reconstruction with major

associated utility work

State Aid street reconstruction

Stand-alone sidewalk, bicycle or utility project

Public

partner lead

State

County

Transit agency

Parks district

Private

development

Will remain private

Future public

Exceptions

Living Streets principles will be included in all street construction, reconstruction, repaving and

rehabilitation projects, except under one or more of the conditions listed below. City staff will document

proposed exceptions as part of a project proposal.

• A project involves only ordinary maintenance activities designed to keep assets in serviceable

condition, such as mowing, cleaning, sweeping, spot repair, concrete joint repair or pothole filling,

or when interim measures are implemented on a temporary detour. Such maintenance activities,

however, shall consider and meet the needs of bicyclists and pedestrians.

12

Living Streets Plan – 2. Living Streets Policy

Page 48 of 275 • The City exempts a project due to an excessively disproportionate cost of establishing a bikeway,

walkway or transit enhancement as part of a project.

• The City determines that the construction is not practically feasible or cost effective because

of significant or adverse environmental impacts to waterways, flood plains, remnants or native

vegetation, wetlands or other critical areas.

• Available budget is constrained or project timing allows more efficient construction at a later date.

Engagement

Members of the public have an interest in understanding and providing input for public projects. Project

recommendations will be developed with a transparent and defined level of public engagement. The

public will have access to the decision-making process and decision makers via public meetings and

other correspondence and will be provided the opportunity to give input throughout the process. Project

reports will discuss how their input helped to influence recommendations and decisions. The City of

Edina’s Living Streets will continue to engage and solicit public input as a vital component of the project

implementation process. See Chapter 5 for a more detailed discussion regarding the purpose of and

opportunities for public engagement.

Design

The guidelines contained in the Living Streets Plan will be used to direct the planning, funding, design,

construction, operation and maintenance of new and modified streets, sidewalks, paths and trails. The

guidelines allow for context-sensitive designs.

The Design Guidelines (see Chapter 6):

• Keep street pavement widths to the minimum necessary.

• Provide well-designed pedestrian accommodation in the form of sidewalks or shared-use

pathways on all arterial, collector and local connector streets. Sidewalks shall also be required

where streets abut a public school, public building, community playfield or neighborhood park.

Termini will be determined by context.

• Provide frequent, convenient and safe street crossings. These may be at intersections designed to

be pedestrian friendly, or at mid-block locations where needed and appropriate.

• Provide bicycle accommodation on all primary bike routes.

• Allocate right-of-way for boulevards.

• Allocate right-of-way for parking only when necessary and not in conflict with Living Streets

principles.

• Consider streets as part of our natural ecosystem and incorporate landscaping, trees, rain gardens

and other features to improve air and water quality.

The Design Guidelines in this Plan will be incorporated into other City plans, manuals, rules, regulations

and programs as appropriate. As new and better practices evolve, the City will update this Living Streets

Plan. Minimum standards will guide how vehicular, pedestrian and bicycle networks interact and share

public right of way.

Living Streets Plan – 2. Living Streets Policy

13

Page 49 of 275 Benchmarks and Performance Measures

The ability to measure the performance of a plan, as well as knowing that it is functioning as it is intended,

is vitally important to overall success and the ability to sustain it. With this in mind, the City will monitor

and measure its performance relative to the Living Streets Policy. Benchmarks that will demonstrate

success include:

Every street and neighborhood is a comfortable place for walking and bicycling.

This does not mean that every street in the city will have walking and biking facilities. It means that each

neighborhood will provide a network of these facilities such that walking and biking to and through

neighborhoods is a comfortable experience.

Every child can walk or bike to school or a park safely.

It is essential that alternatives to driving to school or parks be provided to children and their caregivers.

These alternatives – walking or bicycling – will be both safe and convenient modes of transportation. See

the Edina Active Routes to School Plan for more information.

Seniors, children, and disabled people can cross all streets safely and comfortably.

Opportunities to cross all streets in Edina, including local, collectors and arterial streets, will be provided.

These crossings will be safe and comfortable for all users, regardless of age or ability.

An active way of life is available to all.

Opportunities for active living should be made available to all members of the Edina community by

connecting centers of activity via active, multimodal transportation. Each resident of and visitor to Edina

will have the ability to lead an active way of life.

There are zero traffic fatalities or serious injuries.

Perhaps the ultimate safety benchmark is zero traffic fatalities or serious injuries. Modeled from the Vision

Zero Initiative (www.visionzeroinitiative.com), an aspirational yet primary goal of Living Streets is to

achieve this high level of safety on the City’s roadways.

Reduce untreated street water flows into local waterways and reduce storm water volume.

Cost-effective stormwater best management practices (BMPs) are strategically selected to go above and

beyond regulatory requirements to provide for flood protection and clean water services through the use of

infrastructure that retains, settles, filters, infiltrates, diverts or reduces the volume of stormwater that flows

to local surface waters.

Retail streets stay or become popular regional destinations.

Part of Edina’s Living Streets vision is that “streets support vibrant commerce.” While most of the city’s

streets are residential, Edina’s business districts are a vital part of the community. The benefits of Living

Streets extend to retail streets as well, making them more attractive to businesses and consumers alike.

14

Living Streets Plan – 2. Living Streets Policy

Page 50 of 275 The City will draw on the following data to measure performance:

• Number of crashes or transportation-related injuries reported to the Police Department.

• Number and type of traffic safety complaints or requests.

• Resident responses to transportation related questions in resident surveys.

• Resident responses to post-project surveys.

• The number of trips by walking, bicycling and transit (if applicable) as measured before and after

the project.

• Envision ratings from the Institute for Sustainable Infrastructure.

• Additional performance measures may be identified as this Policy is implemented.

Mini Fact

Motorists must stop behind all

crosswalks.

Living Streets Plan – 2. Living Streets Policy

15

Page 51 of 275 APPENDIX G

Edina Transportation Commission

Meeting Minutes

Page 52 of 275

APPENDIX H

Edina Transportation Commission

Advisory Communication

Page 53 of 275

APPENDIX I

Neighborhood Informational

Meeting Materials

Page 54 of 275

2026 Neighborhood Roadway Reconstruction

Informational Meeting – August 26, 2025

EdinaMN.gov

Page 55 of 275 Agenda

Introductions

• Why Reconstruct

• Project Scopes

• What You Can Expect

• Funding Sources

• Timeline

• Communication

• How to Prepare

• Questions

Page 56 of 275 Engineering - Design & Construction Division

Chad Millner

Director of Engineering

Aaron Ditzler

Assistant City Engineer

Chris Moore

Graduate Engineer

Brandon Freeman

Sr. Engineering Technician

Liz Moore

Engineering Coordinator

Ben Jore

Sr. Project Engineer

Tom Haataja

Sr. Engineering Technician

Jon Moore

Sr. Engineering Technician

Page 57 of 275 2026 Project Areas

• Parklawn

Court

4 Properties

• Prospect

Knolls A, C, &D

283 Properties

Page 58 of 275 Why My Street?

• Streets grouped into

neighborhoods

• Maximizes economics of scale

• Extends pavement life

• Proactive Pavement

Management Program

• Prioritized based on;

• Pavement condition

• Underground utility issues

Page 59 of 275 Why Reconstruct?

• Roadway originally constructed

with in the 1950’s-1980’s

• Utility issues to address beneath

roadway

• More cost-effective than other

maintenance strategies (mill &

overlay, seal coat)

Page 60 of 275 Existing Conditions - Roadways

• Pavement reaching end of

useful life

• Some streets have curb and

gutter while others do not

• Some properties already have

concrete driveway aprons,

some do not

Page 61 of 275 Existing Conditions - Utilities

Sanitary Sewer

- Cracks, breaks, sags, etc.

- Inflow and infiltration

• Watermain

- Loss in pipe wall

thickness

- Main and service

breaks

- Undersized mains

Storm Sewer

- Structure deficiencies

- Undersized pipes

- Curb and gutter failing

Page 62 of 275 What / Where is the ROW?

• Surface and space

above and below

public roadways used

for travel purposes

and utilities

• Typically, 60’ width

• (MSA Streets 66’)

• Property corners

located during survey

Page 63 of 275 Existing Conditions – Right-of-Way

• Landscaping

• Outwalks /

steps

• Mailboxes

• Irrigation

systems and

pet fences

Page 64 of 275 Proposed Improvements – Roadways

• Replacement

and installation

of curb &

gutter

• Subgrade

corrections as

needed

• New roadbed

and asphalt

pavement

surface

Page 65 of 275 Living Streets Plan

• Approved by City Council in 2015

• Balances needs of motorists, bicyclists, pedestrians and transit

riders

Incorporates;

• Minimum roadway design elements

• Street Width

• Impacts

• Cost

• Pedestrian and Bicycle Master Plan

Page 66 of 275 Proposed Improvements - Driveways

• Aprons will be replaced /

installed to comply with City

standards

• Special driveway materials

• Reimbursement Policy

Page 67 of 275 Proposed Improvements - Utilities

Includes partial replacement

of watermain

• New service replacements

• New fire hydrants and gate

valves

• May include localized

sanitary sewer repairs and

rehabilitation

• Lining of sanitary sewer

• Storm sewer upgrades

Page 68 of 275 Proposed Improvements – Sump Drain

Installed when feasible and warranted

• Homeowners encouraged to connect

to City Sump Drain

• Notification will be given when

connecting is available

• Sump connection permit available

thru City website

Page 69 of 275 Utility Ownership

City Owned Utilities

A – Water Service

E – Water Service Shutoff

Resident Owned Utilities

B – Water Service

C & D – Sanitary Service

Page 70 of 275 Utility Ownership

• Recommend inspecting

private services prior to

construction

• Repairs/upgrades can be

coordinated with street

work

• Associated costs can be

added to special

assessment

Resident Owned Utilities

B – Water Service

C & D – Sanitary Service

City Owned Utilities

A – Water Service

E – Water Service Shutoff

Page 71 of 275 Proposed Improvements – Ped / Bike

• Based on Pedestrian

and Bicyclist Master

Plan

• Final design

evaluated based on

network

consistency and

construction

conflicts

Page 72 of 275 Private Utilities

• Gas, Electric, Telephone, Cable may

upgrade or repair their utilities

before construction begins

• Fiber optic internet currently being

installed

• Potential City-required relocations

• Goal: streamline projects and

minimize neighborhood

disturbance

Page 73 of 275 Overhead Utility Poles

• Resident request about

burying overhead utilities

• Not required by the City, nor

does the City fund this

If pursued, full cost by

property owners

• Significant cost

• Private service connection

not included

Page 74 of 275 What You Can Expect

• Dust, mud, noise, and

vibrations

• Occasional delays due to

inclement weather

• Localized flooding during

rainfall

• Residents will be asked to

limit water use occasionally

• Homes may be connected to

temporary watermain

Page 75 of 275 What You Can Expect

• Construction materials

stored temporarily in

ROW

• 5-10 feet of disturbance

behind back of curb

• Construction equipment

stored on streets

• Tree removals as

necessary (property

owners notified)

Page 76 of 275 What You Can Expect

• Driveways and roads will be periodically inaccessible

• Driveways will be inaccessible for 7 days to allow driveways to cure

Page 77 of 275 What You Can Expect

Items within the City’s

right-of-way may be

damaged

• You can remove plants and

other landscape features

before the project

• Irrigation and pet fences

will be repaired

• Disturbed areas will be

restored with new sod

Page 78 of 275 What You Can Expect

• We will;

• Provide opportunities for

input

• Keep you informed

• Do our best to minimize

inconveniences

• Our contractor will

accommodate residents

with special access needs

Page 79 of 275 City Utility Funds

• Collection of utility service charges paid to the City

• Covers 100% of:

• Storm sewer

(curb and gutter,

driveway aprons,

sump drain pipe)

• Sanitary sewer

• Watermain

Page 80 of 275 Pedestrian and Cyclist Safety (PACS) Fund

• Revenue from Xcel and CenterPoint Energy franchise fees

• Promotes non-motorized

transportation throughout

the City

• Covers 100% of:

• Sidewalks /shared-use

paths

• Bike lanes

• Associated signage

and pavement markings

Page 81 of 275 Do Taxes Cover Street Projects?

• ~23% of property taxes go to the City

for expenses including Police, Fire,

Parks, and Public Works

• ~3.2% go to Public Works

• Snowplowing

• Pothole repairs

• Other street maintenance

(sealcoating, overlays, patch repairs)

In 2022 taxes began paying for a

portion of street reconstruction

Figures per proposed 2025 Edina

Tax Levy (not final)

Page 82 of 275 Special Assessments

• Assigned to benefitting

properties of public

improvements

• Covers portion of roadway

costs

• Roadway and driveway removals

• Asphalt pavement

• Driveway installation

• Restoration

• Indirect Costs – engineering,

finance, soil investigations, mailings

Page 83 of 275 Residential Equivalent Units

• Assessments distributed based on REUs

• Factor used to compare properties to a single-family residence

Scenario

Land Use Class

REU Factor

A

B

Single-Family Residential

Multi-Family Residential – Apartment/Condos

1.0

0.5

• Additional factors for commercial, industrial, and public-use properties

Page 84 of 275 Project Details – Parklawn Court

• 4 properties (41.50 REUs)

• 330’ of road

• Full removal and replacement of curb

& gutter

• Concrete roadway removed and

replaced with Bituminous

• Water services replacement

• Sanitary Lining and local replacement

• Storm sewer improvements

• Potential sidewalk(s)

• Street width still to be determined

Page 85 of 275 Project Details – Prospect Knolls A, C, & D

• 283 properties (231.67 REUs)

• 3.20 miles of road

Installation and replacement of curb &

gutter

• Partial watermain and full water services

replacement

• Sanitary lining and localized repairs

• Storm sewer improvements

• 24’ street width 5’ walk:

• Portions of Shannon Drive, Lanham Lane

• Kemrich Drive, Fleetwood Drive

• Typically 27’ street width remaining

streets

Page 86 of 275 Proposed Utility Improvements

Install 12” watermain from

West 70th Street to Gleason

Road

• Existing Utility Easement

• Replace 6” watermain on

Dublin Circle

• Replace 6” watermain on

Lanham Lane

• Upgrade 1.5” watermain in

cul-de-sacs to 6” watermain

Install 8” sanitary sewer on

70th Street

Page 87 of 275 Pedestrian Facilities Plan

• 5’ concrete sidewalk

• Shannon Drive

• Kemrich Drive

• Fleetwood Drive

• Lanham Lane

• Connection to existing Lewis

Park path

• Sidewalk to be maintained by

adjacent property owners

Page 88 of 275 Proposed Roadway Widths – Sidewalk Streets

Existing: 30’ road width, two-sided parking

Proposed: 24’ road width, one-sided parking,

5’ sidewalk (0-5’ grass boulevard)

Page 89 of 275 Proposed Roadway Widths – No Sidewalk Streets

• 27’ road width

• Reduce street widths by 0-

3’

• Two-sided parking to

remain

• Exceptions

• Kerry Road

• 24’ width

• One-sided parking

• Village Drive

• 30’ width

Existing: 26’-30’ road width, two-sided parking

Proposed: 27’ road width, two-sided parking

Page 90 of 275 Revised Roadway Cost Assessment - Local

Sample Assessment During

Transition

Construction

Year

% of Local Roadway

Costs Assessed

$10,000

$20,000

$30,000

2020

2021-2025

2026

2027-2035

2036

100%

78.90%-57.86%

52.60%

$10,000

$7,890-

$5,786

$5,260

$20,000

$15,780-

$11,572

$10,520

$30,000

$23,670-

$17,358

$15,780

47.34%-5.26%

$4,734-$526

$9,468-$1,052

$14,202-$1,578

0%

$0

$0

$0

Page 91 of 275 Market Benefit Estimate

Special assessments are valid if;

• The assessment does not

exceed the special benefit

measured by the increase in

market value due to the

improvement.

• Licensed and Qualified Appraisal

Firm

Page 92 of 275 Assessments Districts – Prospect Knolls

• Disparity

in potential

benefit

• 3 Separate

Districts

Page 93 of 275 Preliminary Assessments – Prospect Knolls &

Parklawn Ct

*Residential equivalent unit (1 single-family home = 1 REU)

Year

Neighborhood

2026

2026

2026

2026

2026

2025

2024

Prospect Knolls

A/C/D

District 1

District 2

District 3

Parklawn Court

Presidents A/B

Concord B/C

% of

Roadway

Costs

Assessed

Estimated

Assessment Range

per REU*

# of

REUs

Square

Yards of

Paving

SY of

Paving per

REU

-

-

-

-

-

-

52.60%

52.60%

52.60%

57.86%

57.86%

63.12%

$16,200

$8,200

$2,900

$1,800

$7,500

$11,900

-

-

-

-

-

-

$21,500

$10,900

$3,800

$2,400

$11,500

$17,100

58.67

153

20

41.5

291.6

174.49

19,250

24,692

1,321

1,221

35,250

30,568

-

328.1

161.4

66.0

29.4

120.9

175.2

Page 94 of 275 Typical Project Timeline

Date

Milestone

July – September 2025

Engineering studies/estimates provided

December 2025

Public hearings

January – March 2026

Plan preparation and bidding

April – May 2026

Construction begins

October – November 2026

Construction concludes

2027

Fall 2027

Warranty work

Final assessment hearing

Page 95 of 275 Assessment Timing

Date

Milestone

December 2025

Summer 2026

October 2027

November 2027

January 2028

Initial Public Hearings

Project Constructed

Final Assessment Hearing

Assessment Filed with County

Assessment on Tax Statement

Page 96 of 275 Payment Options

• Pay entire amount upon receiving bill to avoid interest charges

• Pay min. 25% ; balance rolls to property taxes over 15 years

• Roll entire amount to property taxes over 15 years

• 2024 interest rate was 4.69%

• Finance charges are 1% over City’s borrowing interest rate

• Defer payment if 65 years of age or older and meet specific income

requirements

• Assessing Department – 952-826-0365

Page 97 of 275 Communication

• Regular Mail

• All meetings, public hearings, and questionnaires

Final assessment notices (one year after construction)

• Door hangers and flyers

• Time-sensitive information (water shut-offs, concrete, temporary

inaccessibility)

• Better Together Edina – City Website Project Page

Page 98 of 275 Better Together Edina

• Best way to stay

informed

• www.bettertogether

edina.org

• Free, access to

periodic updates on

project progress and

schedules

Page 99 of 275 Providing Input

• Questionnaires mailed to your home, weigh in on;

• Traffic/pedestrian issues

• Street drainage issues

• Streetlight upgrades

• Public hearing in December 2025

• Opportunity for residents to voice comments and concerns

Page 100 of 275 Questionnaire Results

Neighborhood

Responses Received

to Date

Prospect Knolls

26% (74 / 283)

Parklawn Court

25% (1 / 4)

Page 101 of 275 How To Prepare

• Complete project

questionnaire

• Begin financial planning

• Coordinate home and yard

improvement projects around

street reconstruction

schedule

• Review Better Together Edina

updates

• Ask questions, stay informed

Page 102 of 275 Contact Us

Engineering Department

7450 Metro Boulevard

Hours: 7:00 a.m. – 3:30 p.m.

952-826-0371

Aaron Ditzler

Assistant City Engineer

952-826-0443

ADitzler@edinamn.gov

Liz Moore

Engineering Coordinator

952-826-0449

LMoore@edinamn.gov

Page 103 of 275 Questions?

• Ask questions on Better Together Edina Q&A page

• https://www.bettertogetheredina.org/prospect-knolls

• https://www.bettertogetheredina.org/parklawn-court

• Call or email

Page 104 of 275 Thank you for your time!

Page 105 of 275 2026 NEIGHBORHOOD RECONSTRUCTION

INFORMATIONAL MEETING

AUGUST 26, 2025

NAME

70‘...4_,,,...,t.c.„s

K: i, cA-4-40) 101A-2.f eei-AA....

-)

jcV

.. ...

<- F 1

e--) 4 V \, (cid:9)

-, (1 (cid:9)

-

(-_) (cid:9)

-Lt.Sia V) -- ,(4n

,--(Er---F G /55 EL i3e-z--e--..

-)" (cid:9) OLP ; 11, (cid:9) Uje_Ary\----c

r, (cid:9) ((

-P--,,5 (cid:9)

1

2

3

4 -pk

5

6

c&)1•)te

7

8 Th(1"4- 47-ky 467-0011

9 X / Fi-e 44 4) fte-i"

10

) wt (cid:9) Sal bik4k5i,,14‘44/242_

11 Ga ry -. ate,/ Icy tc-Tc/in

12 A/ 4.7,-, ki g_e_4e-is

13

14

15

16

6( r.--\-- (cid:9) C-1-7 1 \-1--..ct

, 20- vQ.., LOMMe_____k

gkk.b i_.%/0„ 1

0,(2-1A--) (cid:9) C-* )3T--c, r NAL--

l_,S T.- 0

( j.x. cf 6,-

' nfz_t_&-s-L. /-6,,

17 M -A-1-1 (cid:9)

18

<-3: k ..\ (cid:9)

LAI3is

s5

t1606 ter00 i'df 7 //kat Rrib`ve

(cid:9) (-L©P

-L. ,,,-, (cid:9)

fiecipte

AoolNeAl.,e_ i\ActiAao/

g/a4

°

19

20

21 1)OiLl- (cid:9) UPt-d0 - ALPS ( -C:9

22

23

24

25

26 44,a f -95 (cid:9)

/' (cid:9)

27

28 -If \ (A6v (cid:9)

7e/

< e_ IA (cid:9)

-l-e1152-44.

b-A-4-‘`-- -2Y---4)--7--)-,--

PZ--k 04,..ess

4t,d64;126G

a--

,- , (cid:9) D,A

ao G,&,,

cy-,4_14

29

30

ADDRESS

I frz_RF_Jr

Zoo ? Z-4-A/ 44 ik,1

70 2„6

110QQt (cid:9) Down Psockct

7,00 siiin h (cid:9)

''<i (cid:9)

5---- ,7 (cid:9)

gs - C 3 ki\i - 7o (cid:9)

S- (cid:9)

(A) (cid:9) 3T)

‘ oo 5 6 06frA 6-e,1.e.)

* 1/a 7 D

6,5-0/ (cid:9)

1-c32,c) Slukyn&AA-CDr.

-- (cid:9)

.1 (cid:9)

(,-, (cid:9) Dv-

o!... (cid:9) Ts+,

TI-

1-1M1

c,r-

.SS D/ (cid:9)

11;//a6e, 4.)r,

1,1 (cid:9)

1$

II

__,_-\--4Th-1--c;,

-Apn (cid:9)

1°2 O (cid:9)

u - )e,

7671h (cid:9) KL=-_-)e__, (cid:9) E0,6,-

---/ (2..-:' (cid:9)

c L-e-e-1-t,/- 6 %) (cid:9)

D4--t

,s, (cid:9) Cltr do _

-Pal 0 e-

riee/A)ddd ipri:/z

-7/c4 (cid:9)

-110 .c (cid:9) 1-(s2eh,,,d..,t Pr,-e

----7 k 09 (cid:9)

r-, ffil-LaoD (cid:9)

721-2_ (cid:9)

I—A p(A-

7z2V /i4All--1/7(-n:x4

(5-ei/i ijA4-70 ci, or

55-26 (cid:9) YI'llat Dr i,i t_

57/7 (cid:9) // ':- , ii4.4fAR

_ I (cid:9) Lo L 1 A g,J

7100 Poies000l DY

-7`2-61r (cid:9) F ( (d-i (cid:9)

.3-.& (cid:9) Dr.

' MA (cid:9) La h hcon tr)

Zei--/ (cid:9)

7 (cid:9) o o

4 (cid:9)

55- Li c (cid:9) w_ 7o t-4 5 .r

-k,,..

Page 1 of 4

Page 106 of 275 2026 NEIGHBORHOOD RECONSTRUCTION

INFORMATIONAL MEETING

AUGUST 26, 2025

NAME

ADDRESS

e•

i.e..' -1/1 t„,t,L5

--Iv.S.W\ (cid:9)

Syr re- LA

,A eP (cid:9)

Pc,t,,1 d c•cru 0

re('',0f„rby

Cr (cid:9)

A (cid:9)

( )-(4,-"J,4 ' (cid:9)

a

0 (cid:9)

ti

e -

,

4,,..

,..,

„s

/ArP4'L4

(-pool, 1- At.ks4\ 0\ ert_ Pi--ers'eA

/44,64EL getarz_

--B

31

32

33

34

35 Veco n t ca, er 44(w.e.V

k(-1--, .\ Sai \\ a--_SA

36

37

38

39

40

41

42 cc AiNI (cid:9)

43 Rit a &\ (cid:9) .1v1i 1 t5

44

(fil (cid:9) -S i 1((t

.4 (cid:9)

45 494f( (cid:9)

1.,,,-y\iz-

46

, .b3 kik_ (cid:9)

47

48 T-L,,_ (cid:9)

49

s--e„fr (cid:9)

50 CIL -e '49 ,e,.-L (cid:9)

51 COLYY1 .e Bmi&Acti

52 CASV100. ‘Q 0"\-€ C MCA_ le\ 0

53

54

55

56

57

58

59

60

( 1 crS Q (cid:9) S0_,\---,c),e, (cid:9) ? \

,,t _,--,.-- ;co-.,

--C:;. 164,e_

-t-es--0-ZO,

E- 1.4 _To1-1—

... -q_ yr / . 5 cP•14-

c_115.-7-f A, (cid:9)

,74/iii 4-- (cid:9)

cj

4i/ 77

.) 07 (cid:9) 6-11 ir ' \v‘ (-1-

kekket L L

%laid (cid:9)

La eti-vt,"

1 OCI'l (cid:9)

7^

,..

--"x),( (cid:9) v (cid:9)

.

knol (cid:9) 701 St..,

_. -Si (cid:9)

r-rk_cz

'1113 (A (cid:9)

0 6-1

--\" (cid:9)

-aannvlA Oviv-t

70.2-e- (cid:9)

?CM, (cid:9) K--r '''y' (cid:9)

70/,,,,-1,.. ze,

1 " 4

703z.. CO ElFtet, gi)

--71/ a 24(,H~ 2,t)

...,Vi, IA e vv

---( 0 (- (cid:9)

'--7 (0 a (cid:9)

54ovitrAeK (cid:9) fi t

3 -/D5 Kunrick owe

)7 a/ (cid:9)

-lifol (cid:9) c-lA0.-mAN-0( (cid:9)

1 0 t \ (cid:9) LemVoi,\IQkf,jn

/<2.i,,' c4 (cid:9) At.,

-1>‘ (cid:9)

-

4a.....2-Ace.._,A,

70 54— (cid:9)

76 ›--s-

714 1:---4-e2t.....-J r)--

12‘co. (cid:9)

- \.t.e'rvv'ood 1)1'

12:2-I (cid:9) V\-Cew000l ,r

ONacv‘z(-\ 4-.1".

Cloy (cid:9) ci.5____ 1/A-1-6Eie (cid:9) *1)

Page 2 of 4

N\Q---k4 °L.- 1 C) (cid:9)

Page 107 of 275(cid:9)

(cid:9)

APPENDIX J

Resident Questionnaires

Page 108 of 275

Neighborhood

Reconstruction Survey

SURVEY RESPONSE REPORT

30 January 2019 - 24 August 2025

PROJECT NAME:

Prospect Knolls A/C/D Neighborhood Roadway Reconstruction

Page 109 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

SURVEY QUESTIONS

Page 1 of 47

Page 110 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q1 Does your property have drainage issues the City should know about?Examples: History

of flooding/standing water, grading, b...

10 (13.5%)

10 (13.5%)

64 (86.5%)

64 (86.5%)

Question options

Yes

No

Mandatory Question (74 response(s))

Question type: Radio Button Question

Page 2 of 47

Page 111 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q2 Please comment on the location and types of problems you have.

Scott Williams

6/28/2025 05:18 PM

peter334

6/28/2025 07:44 PM

Dan!

6/29/2025 02:58 PM

Brian

6/30/2025 06:23 AM

Standing water in backyard during rainy years.

Cul de sac additional storm drains and backyard storm and sewer

drains with fairly steep grade. Special drainage is in place and seems

to work OK.

front lawn collects water

Standing water in the street in front of the mailbox due to the road

sinking below the gutter.

JanFS

7/01/2025 02:43 AM

The NW corner of Cahill Road and Village Drive always has standing

water in the summer and ice in the winter making it impossible to

access the sidewalk.

Steve Thompson

7/03/2025 05:23 AM

Originally we had standing water in driveway and lawn. Through the

City we were able to connect drain tile to the concrete storm sewer

basin buried in the front yard (near street). Problem was solved.

MTK

7/06/2025 05:17 PM

Prior owners reported back yard had a partial mudslide following a

heavy rainfall. Currently problem has been addressed.

jachapman9094

7/08/2025 03:59 PM

PXO

7/19/2025 10:33 AM

Backyard- bottom of backyard has standing water when we get a lot

of rain.

Grading. Water runs down the hill and the street drainage sometimes

is insufficient.

Optional question (9 response(s), 65 skipped)

Question type: Essay Question

Page 3 of 47

Page 112 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q3 How concerned are you with the speed of traffic in your neighborhood or on your street?

7 (9.5%)

7 (9.5%)

18 (24.3%)

18 (24.3%)

Question options

Not Concerned

Concerned

Very Concerned

Optional question (74 response(s), 0 skipped)

Question type: Radio Button Question

Page 4 of 47

49 (66.2%)

49 (66.2%)

Page 113 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q4 If concerned or very concerned, please enter the location(s) of concern and why you feel

that way.

Sarah J

6/28/2025 12:28 PM

Jeff b gisselbeck

6/28/2025 03:09 PM

Salaar

6/28/2025 03:11 PM

John Uecker

6/28/2025 03:43 PM

People drive very fast on Kemrich Drive and fleetwood.

trucks going fast

W 70th St, people going too fast

NO sidewalks, we do not need them. Street is wide and has great

walkability.

Scott Williams

6/28/2025 05:18 PM

Between Shannon and Fleetwood many drivers rapidly accelerate

well beyond the speed limit. Many pedestrians, including young

children are ofter present.

Elizabeth Bennett

6/29/2025 11:20 AM

Cars go very fast down Fleetwood and around the corners on Lee

Valley/Down/Kerry/Antrim. A pedestrian or bike lane would be helpful

on Lee/Down/Kerry/Antrim to protect pedestrians.

cristina notermann

6/29/2025 11:55 AM

down fleetwood

Matt Melsen

6/29/2025 01:06 PM

Roger Thomas

6/29/2025 01:34 PM

Fleetwood is a popular connecting street between 70th and Dewey -

we have a lot of thru traffic that drives excessive speeds. Neighbor

traffic tends to be good speed as we all understand.

Antrim Court sometimes has people speeding quite a bit. Also Antrim

road, Kerry Road, Wexford Road, Down Road and Lee Valley road

have quite a bit of speeding. It can be a little dangerous on these

roads because there are not sidewalks and the turn from Wexford to

Down road is sharp, blind and the trees grow way into the road.

Laura Gillund

6/29/2025 02:14 PM

70th street and Tracy. People often speed and don't stop at the stop

sign.

Page 5 of 47

Page 114 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

michael.r.lommel

6/29/2025 02:34 PM

Dan!

6/29/2025 02:58 PM

Brutlag

6/29/2025 04:05 PM

Heath Marnach

6/29/2025 05:59 PM

northbound on fleetwood towards Lanham and westbound up

Lanham beginning east of Fleetwood to w70th. People drive way to

fast especially considering the amount of people who walk, kids

playing, etc.

Antrim RD, narrow and fast. Antrim Rd should not have street

parking.

All of Fleetwood Drive - seems like a cut through. Not a lot of cars but

travel fast

I live at 7201 Lanham Lane. We have 3 active children ages 13, 11,

and 8 that use the front yard for soccer, lacrosse and running around.

They also use the driveway and street for scooters and bikes. There

generally aren't too may cars, but there are plenty of them that drive

down the street well over 30 mph.

Brian

6/30/2025 06:23 AM

Traffic along 70th between Antrum and Tracy routinely runs above the

speed limit, especially teenagers when the high school lets out.

GGood

6/30/2025 12:02 PM

We are on a cul-de-sac and only rarely get delivery vehicles that are

traveling too quickly.

desa0080

6/30/2025 04:32 PM

I live on the middle of Fleetwood Dr and cars go very fast trying to

connect between 70th and Dewey Hill Rd

JanFS

7/01/2025 02:43 AM

Ryan

7/06/2025 02:20 PM

MTK

Page 6 of 47

Cahill Road and 70th Street are both posted at 25 mph which is

nonsense. Should be minimum 30 mph or 40 like other equivalent

streets like Gleason and Vernon. No vehicles, including City of Edina

cars and trucks, go 25.

Traffic using Fleetwood as a through street travels faster than the

speed limit. The curve and elevation change between 7212 and 7216

creates a blind spot for traffic headed south. We’ve seen drivers have

close calls with kids playing in driveways who have run out after balls

into the street. We do not want to see the street narrowed as a

solution.

Occasional fast cars. Not a significant issue, but kids play in front

Page 115 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

7/06/2025 05:17 PM

yards/driveways.

Liz Moore

7/10/2025 12:53 PM

Our street has a serious curve on a hill with a slight blind spot. Speed

is an issue.

SusanJ

7/17/2025 07:34 AM

Speed limit near 70th and Cahill is 25mph. I don't want speeding but

this seems extremely slow. Could city consider raising it to 30 or 35?

PXO

7/19/2025 10:33 AM

Chazbo711

7/21/2025 10:48 AM

The speed limit on Cahill is too low (especially for a hill).

Cahill Rd between 70th and 78th. Most drivers respect the speed limit

of 25 mph but some cars seem to go 40 mph. Please continue

occasional radar/ticketing. Also, after school some (probably Edina

HS students) speed down the hill on 70th heading east to the Cahill

Rd intersection.

francis.glover

7/23/2025 08:16 AM

Fleetwood drive hill can sometimes be used as a cut through and

some cars going down and up the hill can go faster than desired.

Jamie Glover

8/07/2025 01:19 PM

The curve on Fleetwood Drive doesn't have great visibility, and my

kids ride their bikes on the street often.

Normamuldowney

8/11/2025 05:38 PM

Coming up or down the hill on Antrim Road Frequently vehicles are

parked and cause blind spots. Too many fast drivers are going to

cause ahead on collision

Optional question (27 response(s), 47 skipped)

Question type: Essay Question

Page 7 of 47

Page 116 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q5 How concerned are you with the volume of traffic or number of vehicles in your

neighborhood or on your street?

2 (2.7%)

2 (2.7%)

6 (8.2%)

6 (8.2%)

65 (89.0%)

65 (89.0%)

Question options

Not Concerned

Concerned

Very Concerned

Optional question (73 response(s), 1 skipped)

Question type: Radio Button Question

Page 8 of 47

Page 117 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q6 If concerned or very concerned, please enter the location(s) of concern and why you feel

that way.

Klstone

6/28/2025 11:55 AM

I live on Village Drive. Traffic along Cahill has increased significantly

since I moved in 8 years ago. Making it difficult to exit neighborhood.

Sarah J

6/28/2025 12:28 PM

Sometimes there are a LOT of trucks in the neighborhood

michael.r.lommel

6/29/2025 02:34 PM

n/a

Dan!

6/29/2025 02:58 PM

Brutlag

6/29/2025 04:05 PM

Brian

6/30/2025 06:23 AM

Antrim Rd should not have street parking.

Speed not volume

When Hwy. 62 backs up, 70th becomes a major thoroughfare of

traffic from the freeway. Also heavy traffic when the high school lets

out in the afternoons during the school year.

desa0080

6/30/2025 04:32 PM

7208 Fleetwood Dr and same comment as above. Our street is full of

kids and is a through street between 70th and Dewey Hill Rd

Drea

7/06/2025 04:24 PM

Linda Berg

7/12/2025 10:53 AM

There is plenty of room on our street.

Delivery trucks drive tooooooo fast…..FedEx. Prime…..UPS…..all

delivery trucks….too &amp; from

SusanJ

7/17/2025 07:34 AM

More traffic on Cahill now with apartments and expecting more when

apartments on 78th are completed (I realize that is technically

Bloomington.)

On Antrim road Vehicles park on both sides of the road

Normamuldowney

8/11/2025 05:38 PM

Page 9 of 47

Page 118 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Optional question (11 response(s), 63 skipped)

Question type: Essay Question

Page 10 of 47

Page 119 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q7 How concerned are you with motorist behavior in your neighborhood? (Excludes speed

and traffic volumes. Examples of poor motorist behavior include rolling through stop signs,

failing to yield and driving aggressively)

4 (5.4%)

4 (5.4%)

19 (25.7%)

19 (25.7%)

51 (68.9%)

51 (68.9%)

Question options

Concerned

Not Concerned

Very Concerned

Optional question (74 response(s), 0 skipped)

Question type: Radio Button Question

Page 11 of 47

Page 120 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q8 If concerned or very concerned, please enter the location(s) of concern and why you feel

that way.

Klstone

6/28/2025 11:55 AM

Sarah J

6/28/2025 12:28 PM

Rolling through stop signs at 70th and Cahill.

People drive very fast - well above speed limit on kemrich and

fleetwood

Jeff b gisselbeck

6/28/2025 03:09 PM

I am close to 70th street they tend to speed up and there is a curve in

the street which can be a issue

Scott Williams

6/28/2025 05:18 PM

Very concerned. My vehicle was totaled last year at the intersection of

Dewey. Hill and Shannon. Westbound driver blew through the stop

sign and broadsided me. He said he didn't know there was a stop

sign. Many do rolling stops and assume they have right of way on

Dewey, even though drivers on Shannon stopped. Also, at Cahill and

Dewey a traffic circle should replace the goofy intersection currently

there.

cgaz

6/28/2025 06:15 PM

(We live in a townhome community that's not a through street, so the

only issues we've had were with previous residents who drove

recklessly)

Elizabeth Bennett

6/29/2025 11:20 AM

Cars are not on their proper side of the street around the corners of

Lee Valley/Down/Kerry/Antrim.

Roger Thomas

6/29/2025 01:34 PM

Again on that main road Antrim Road, Dublin road, Kerry Road Down

road people drive aggressive and fast. I don't understand why they

drive that way because they all live in the neighborhood.

tiamat2pi

6/29/2025 01:49 PM

70th and Antrim - sometimes drivers coming on Antrim from the north

don't realize cars coming from the left (up 70th) may not be turning

right and don't yield.

People often don't stop at the stop sign.

Laura Gillund

6/29/2025 02:14 PM

Page 12 of 47

Page 121 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

michael.r.lommel

6/29/2025 02:34 PM

n/a

Heath Marnach

6/29/2025 05:59 PM

There are plenty of drivers, teens and adults, that drive too fast and

do not pay attention to pedestrians. With no sidewalks, the only

option for walking is in the road.

Brian

6/30/2025 06:23 AM

Johnmlohmann

6/30/2025 06:41 AM

Steven Manacek

6/30/2025 11:00 AM

Motorists constantly coasting through the stop sign at 70th and Tracy

Ave.

Both rolling stops and ignoring healers signs are a problem

Large number of drivers treat stop signs, such as the ones at

Shannon Drive/Dewey Hill Road, as yield signs, barely slowing down,

and only actually stopping if another car is approaching at the same

time.

G

6/30/2025 09:39 PM

It is a windy street and when it comes to a curve you are often head

to head with another car.

JanFS

7/01/2025 02:43 AM

Many cars have no mufflers or mufflers that enhance the noise.

There should be a noise ordinance that limits noise. Vehicles with

load mufflers should be stopped.

druckd666

7/05/2025 08:10 AM

Ryan

7/06/2025 02:20 PM

jachapman9094

7/08/2025 03:59 PM

PXO

7/19/2025 10:33 AM

Page 13 of 47

Just UPS and FedEx drivers driving a bit too fast.

Motorists ignore the stop sign at Shannon and Kemrich for

southbound traffic.

At Dewey Hill and Shannon, people sometimes do not stop at the

stop sign. And at Kemrich and Shannon, people do not yield. Also-

turning the corner at the top of Lanham Drive is dangerous. And the

bushes at Lanham and 70th need to be cut down or trimmed as

turning traffic often doesn’t see a car there when turning.

People basically ignore the stop signs along Dewey Hill.

Page 122 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Chazbo711

7/21/2025 10:48 AM

There is a formal posted crosswalk across 70th from Hillside/Limerick

Lanes. Cars rarely stop for pedestrians waiting to cross. Luckily, there

are usually enough gaps in traffic to cross safely but we would never

venture out into the street there unless the coast was clear (or we run

across if there is a car in the distance). Most drivers seem to think

they have the right of way there. I don’t know why.

Normamuldowney

8/11/2025 05:38 PM

Antrim road up and down the hill

Optional question (22 response(s), 52 skipped)

Question type: Essay Question

Page 14 of 47

Page 123 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q9 In general, these behaviors impact you most when you are:

18 (35.3%)

18 (35.3%)

3 (5.9%)

3 (5.9%)

30 (58.8%)

30 (58.8%)

Question options

Driving

Bicycling

Walking, jogging, or running

Optional question (51 response(s), 23 skipped)

Question type: Radio Button Question

Page 15 of 47

Page 124 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q10 Do you feel any intersection in your neighborhood is unsafe?

38 (52.8%)

38 (52.8%)

34 (47.2%)

34 (47.2%)

Question options

Yes

No

Optional question (72 response(s), 2 skipped)

Question type: Radio Button Question

Page 16 of 47

Page 125 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q11 Which intersection do you feel is unsafe?

Klstone

6/28/2025 11:55 AM

Sarah J

6/28/2025 12:28 PM

Joe Johnson

6/28/2025 04:48 PM

thomaspmagne

6/28/2025 04:51 PM

Scott Williams

6/28/2025 05:18 PM

cgaz

6/28/2025 06:15 PM

70th and Cahill. I feel safe as a driver but not as a pedestrian. Cars

do not give walkers the right of way.

kemrich and Shannon Drive Fleetwood and Latham Lane Kemrich

Drive and Fleetwood drive

City hall

Shannon Dr. and Dewey Hill Rd.

Dewey and Shannon and Dewey and Cahill

The bike lane on 7oth Street disappears as the street passes under

Highway 100—feels dangerous for bicyclists.

peter334

6/28/2025 07:44 PM

Kerry to Down is a loop that people pay little attention to the Wexford

offshoot since it is lightly used, but heavy vegetation can impede

driver's view when turning left.

Antrum/70th; Make a 4 way stop

Shannon and Lee Valley &amp; Shannon and Kemrich

Hwy 62 and Tracy. (multiple issues) 1. Exiting from eastbound 62, the

sightlines are poor, and increased traffic due to cut-through traffic

during heavy traffic on 62 adds to problems. 2. Exiting from

westbound 62, there is too much traffic, and it is a relatively complex

intersection. Needs a stoplight. 3. Driving south on Tracy, the lanes

are not aligned as you pass the 62 entrance/exit (westbound) forcing

drivers to make a quick jog to the right to avoid the northbound traffic

turning left onto 62 west. Compounded by cars nudging out from exit

ramp onto Tracy given the heavy volume. 4. Similar issue when

driving northbound and trying to turn left onto 62 west. Need to pay

attention to make sure oncoming traffic notices that jog. 5. Tracy Ave

mas54po

6/29/2025 07:13 AM

Elizabeth Bennett

6/29/2025 11:20 AM

Paul Cashin

6/29/2025 11:47 AM

Page 17 of 47

Page 126 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

bridge over 62 is NOT pedestrian or bicycle friendly.

cristina notermann

6/29/2025 11:55 AM

Roger Thomas

6/29/2025 01:34 PM

Laura Gillund

6/29/2025 02:14 PM

ndanielsen

6/29/2025 02:25 PM

lee vallye and down road and down road and wexford road

Wexford, Down and Kerry is not very say. There should be sidewalks

on that whole road from 70th to Dewey Hill. Also 70th and Antrim

should have a signal. The idea that 70th has right of way and

everyone else stops is not obvious and it leads to issues with safety.

Valleyview and Antrim should have a signal.

70th and Tracy

Lee Valley Road and Shannon Drive. With the stop sign only at one of

the three directions, it's really confusing about who has the right of

way. Same for the intersection at Kemrich and Shannon (confusion

over right of way) Where Shannon Drive meets Lee Valley (coming

from the northern most section of Shannon Drive), there is a large

flower garden that blocks visibility around the corner.

michael.r.lommel

6/29/2025 02:34 PM

Kemrich/Shannon intersection. The southbound traffic on shannon

has a stop sign, which is frequently ignored. The other two directions

of traffic have no signage.

Dublin

6/29/2025 02:53 PM

The 70th street and Antrim - terrible - people don’t Know 70th has

right of way up to our neighborhood

Dan!

6/29/2025 02:58 PM

70th and Tracy. Why the stop sign? Trim trees to see the stop sign. 3

way stop at 70th and antrim - likely should be 4 way. people don't

know 1 side does not have a stopsign.

Brian

6/30/2025 06:23 AM

Johnmlohmann

6/30/2025 06:41 AM

70th and Tracy

There are very many blind corners in the prospect hills neighborhood

Steven Manacek

6/30/2025 11:00 AM

The 3-way intersection at Shannon Drive and Kemrich Drive has only

one stop sign, on Shannon south-bound. I have seen several narrow-

Page 18 of 47

Page 127 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

miss accidents between vehicles north-bound on Shannon and west-

bound on Kemrich, neither of whom has a stop sign. Also see above

re Shannon/Dewey Hill. Cars sometimes run straight through the

stops on Dewey Hill.

Shannon Drive at Dewey Hill. Stops signs along Dewey Hill are

occasionally ignored by motorists.

My only concern is the intersection of 70th St &amp; Antrim which is

currently a 3-way stop (no stop for westbound 70th st drivers) and

many motorists driving south on Antrim and making a left onto

Eastbound 70th don't realize its only a 3-way stop so they don't yield

to oncoming westbound 70th St vehicles

The bend (Hairpin) on Down Road.

Kemrich and Shannon.

1) Shannon and Kemrich. 2) Lanham and 70th

Getting off on Tracy from either way on 62

Stop sign@ Shanon &amp; Lee Valley road or Down road

70th and Antrim Rd

Dewey Hill and Shannon drive 4 way stop

70th Street &amp; Antrim caution used for drivers not stopping -

rolling through - off line

GGood

6/30/2025 12:02 PM

maggiedevoe

7/01/2025 05:26 AM

ElectronLady

7/03/2025 10:10 AM

Ryan

7/06/2025 02:20 PM

jachapman9094

7/08/2025 03:59 PM

Csazenski

7/09/2025 09:59 PM

Linda Berg

7/12/2025 10:53 AM

Mwild

7/13/2025 05:47 PM

dubesbennett

7/15/2025 03:48 PM

Liz Moore

7/16/2025 12:20 PM

Liz Moore

7/16/2025 12:26 PM

The site lines could be improved when traveling by car south on Lee

Valley Road where it intersects with Northbound Shannon Drive due

Page 19 of 47

to vegetation

Page 128 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

SusanJ

7/17/2025 07:34 AM

PXO

7/19/2025 10:33 AM

EdinaChris

8/06/2025 11:03 AM

Jamie Glover

8/07/2025 01:19 PM

rdizzo

8/11/2025 12:10 PM

70th and Cahill. It was re-done recently and turning from Cahill to

70th going East is EXTREMELY tight. Often cars have to move over

or wait until there are no cars to make the right turn. Poor design.

There is a weird triangle boulevard where Cahill and Dewey Hill meet

that creates really awkward turns.

Curve at the top of lanham between fleetwood and 70th.

Dewey Hill &amp; Shannon Drive

I feel all the intersections on Shannon Dr north of Dewey are unsafe

at times because people don't seem to know who has the right of way

all

Normamuldowney

8/11/2025 05:38 PM

jelliott5904

8/14/2025 11:25 AM

Antrim road and 70 th at the 3 way stop sign

Shannon at Kemrich

Optional question (38 response(s), 36 skipped)

Question type: Essay Question

Page 20 of 47

Page 129 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q12 Which, if any, of the following factors contribute to your feeling that the intersection is

unsafe? (select all that apply)

23

19

12

12

12

26

24

22

20

18

16

14

12

10

8

6

4

2

9

1

Question options

Lack of traffic control (traffic signal, stop sign, yield sign)

Issues with sight lines or clear view

Drivers failing to stop at stop sign

Drivers failing to yield

Drivers turning corner too fast

Insufficient lighting

Other (please specify)

Street(s) too wide

Optional question (45 response(s), 29 skipped)

Question type: Checkbox Question

Page 21 of 47

Page 130 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q13 In general, the intersection feels most unsafe when you are:

11 (26.2%)

11 (26.2%)

2 (4.8%)

2 (4.8%)

Question options

Driving

Bicycling

Walking, jogging, or running

Optional question (42 response(s), 32 skipped)

Question type: Radio Button Question

Page 22 of 47

29 (69.0%)

29 (69.0%)

Page 131 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q14 How frequently do you walk, jog, or run in your neighborhood?

4 (5.6%)

4 (5.6%)

4 (5.6%)

4 (5.6%)

9 (12.5%)

9 (12.5%)

16 (22.2%)

16 (22.2%)

39 (54.2%)

39 (54.2%)

Question options

Very frequently (daily or near daily)

Frequently (2-3 times per week)

Occasionally (1-4 times per month)

Rarely (less than once per month)

Never

Optional question (72 response(s), 2 skipped)

Question type: Radio Button Question

Page 23 of 47

Page 132 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q15 If you walk, jog, or run in your neighborhood, what are your primary reasons for doing

so? (select all that apply)

66

70

65

60

55

50

45

40

35

30

25

20

15

10

5

7

7

1

Question options

Health/exercise

Commute to/from work

Travel to/from destination (such as store, coffee shop)

Access transit

Other (please specify)

Optional question (66 response(s), 8 skipped)

Question type: Checkbox Question

Page 24 of 47

Page 133 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q16 If you don't walk, jog, or run in your neighborhood as often as you would like, what

reconstruction improvement might increase your walking, jogging, or running? Please list all

that you can think of.

Sarah J

6/28/2025 12:28 PM

Slower traffic and better intersections (safer for kids if motorists stop

at intersections)

Jeff b gisselbeck

6/28/2025 03:09 PM

nothing

John Uecker

6/28/2025 03:43 PM

NO sidewalks needed. Let’s keep the assessment price down.

Neighborhood is great for walking and jogging and biking as is.

Joe Johnson

6/28/2025 04:48 PM

cgaz

6/28/2025 06:15 PM

peter334

6/28/2025 07:44 PM

Elizabeth Bennett

6/29/2025 11:20 AM

tiamat2pi

6/29/2025 01:49 PM

ndanielsen

6/29/2025 02:25 PM

Less government

NA

none

Marked pedestrian or bike lanes, better lighting

more sidewalks

The stretch of Shannon between Kemrich and Lee Valley is really

unsafe for walking. A sidewalk or a bike/walk lane would be very

helpful. Same for the stretch of Lee Valley/Down/Kerry/Antrim. Those

routes are used by kids walking to bus stops or Valley View and EHS.

And with the curves, visibility is hard making it feel unsafe.

michael.r.lommel

6/29/2025 02:34 PM

n/a

Dublin

6/29/2025 02:53 PM

Page 25 of 47

None - if we want to walk we walk - it’s the hills that are hard to come

up

Page 134 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Dan!

6/29/2025 02:58 PM

Heath Marnach

6/29/2025 05:59 PM

Steven Manacek

6/30/2025 11:00 AM

CharlieBray1

6/30/2025 03:22 PM

EITAN MEDINI

7/02/2025 08:28 AM

Steve Thompson

7/03/2025 05:23 AM

more sidewalks

More sidewalk access or a dedicated area of the road for pedestrians

would be appreciated. We love living in Edina, but we miss sidewalk

access that we had when we lived in Minneapolis.

None. There are lots of walkers in my neighborhood; I'm just not

usually one of them. There is no impediment. Traffic on most streets,

except Dewey Hill, is light and usually moves fairly slowly, given the

winding streets and hilly terrain.

Having sidewalks will NOT increase the number of people walking in

this neighborhood.

none

Nothing

sburns

7/06/2025 07:33 PM

we do not want sidewalks. they would ruin the neighborhood. stay out

of our neighborhood, it is doing fine the way it is. NO to sidewalks!

Liz Moore

7/10/2025 12:53 PM

We need a sign indicating children at play. We need a complete

asphalt re-do of our street. No resurfacing and we no need sidewalks.

Liz Moore

7/16/2025 12:20 PM

Liz Moore

7/16/2025 12:26 PM

None needed. Leave as is.

None

Normamuldowney

8/11/2025 05:38 PM

Side walks A caution sign on hill

jelliott5904

8/14/2025 11:25 AM

Page 26 of 47

fewer potholes and huge cracks

Page 135 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Optional question (23 response(s), 51 skipped)

Question type: Essay Question

Page 27 of 47

Page 136 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q17 How frequently do you ride a bicycle in your neighborhood?

18 (25.4%)

18 (25.4%)

13 (18.3%)

13 (18.3%)

12 (16.9%)

12 (16.9%)

18 (25.4%)

18 (25.4%)

10 (14.1%)

10 (14.1%)

Question options

Very frequently (daily or near daily)

Frequently (2-3 times per week)

Occasionally (1-4 times per month)

Rarely (less than once per month)

Never

Optional question (71 response(s), 3 skipped)

Question type: Radio Button Question

Page 28 of 47

Page 137 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q18 If you ride a bicycle in your neighborhood, what are your primary reasons for doing so?

(select all that apply)

46

50

45

40

35

30

25

20

15

10

5

16

2

2

Question options

Health/exercise

Travel to/from destination (such as store, coffee shop)

Commute to/from work

Other (please specify)

Access transit

Optional question (50 response(s), 24 skipped)

Question type: Checkbox Question

Page 29 of 47

Page 138 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q19 If you don't ride a bicycle in your neighborhood as often as you would like, what

reconstruction improvement might increase your bicycle riding frequency? Please list all that

you can think of.

Joe Johnson

6/28/2025 04:48 PM

cgaz

6/28/2025 06:15 PM

peter334

6/28/2025 07:44 PM

Elizabeth Bennett

6/29/2025 11:20 AM

ndanielsen

6/29/2025 02:25 PM

Less government. Take out all bike lanes. Move bikes lanes off busy

streets. Roads were built for cars.

NA

none

Bike or pedestrian lanes

Same answer as above. The windy roads in our neighborhood are

tough for visibility and it can feel unsafe to bike. Our kids would like to

bike to school (EHS) but without a bike lane, it feels unsafe.

michael.r.lommel

6/29/2025 02:34 PM

n/a

Dublin

6/29/2025 02:53 PM

Dan!

6/29/2025 02:58 PM

Heath Marnach

6/29/2025 05:59 PM

maggiedevoe

7/01/2025 05:26 AM

EITAN MEDINI

7/02/2025 08:28 AM

Page 30 of 47

None - we are very close to a bike path if we want to bike

remove the hills on valleuview and 70th ;)

I'm generally quite happy with the bicycle lanes around Edina. I bike

regularly around Edina on my road bike and feel comfortable with the

bicycle lanes. I also bike to and from the Braemar mountain bike trails

with my children and the access is pretty good.

Existing bike lanes and traffic patterns support bicyclists today.

none

Page 139 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Steve Thompson

7/03/2025 05:23 AM

Nothing is needed to enhance the ability to bike

druckd666

7/05/2025 08:10 AM

Drea

7/06/2025 04:24 PM

sburns

7/06/2025 07:33 PM

Csazenski

7/09/2025 09:59 PM

Liz Moore

7/10/2025 12:53 PM

Liz Moore

7/16/2025 12:20 PM

Liz Moore

7/16/2025 12:26 PM

PXO

7/19/2025 10:33 AM

None. The neighborhood is reasonably accommodating to cycling.

No res construction needed in our neighborhood. Plenty of room on

our roads. We walk with group of 5 daily.

sidewalks would ruin the neighborhood.

I don’t want a bike path in neighborhood

Our street is a hill, we live at the top of a hill. Can't reconstruct that

and we 100% oppose sidewalks.

Leave as is. No sidewalks either.

None

Bike lanes would be great.

Debasish N Mallick

7/28/2025 01:33 PM

Not interested

Jamie Glover

8/07/2025 01:19 PM

My kids bike on Fleetwood Drive often, and I worry about northbound

cars (coming up the hill and around the curve) having bad sightlines

to see them.

Optional question (22 response(s), 52 skipped)

Question type: Essay Question

Page 31 of 47

Page 140 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q20 How frequently do you or a member of your household park on the street?

0 (0.0%)

0 (0.0%)

5 (6.8%)

5 (6.8%)

32 (43.8%)

32 (43.8%)

12 (16.4%)

12 (16.4%)

24 (32.9%)

24 (32.9%)

Question options

Frequently (2-3 times per week)

Occasionally (1-4 times per month)

Rarely (less than once per month)

Never

Very frequently (daily or near daily)

Optional question (73 response(s), 1 skipped)

Question type: Radio Button Question

Page 32 of 47

Page 141 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q21 How frequently do visitors to your household park on the street?

14 (19.2%)

14 (19.2%)

2 (2.7%)

2 (2.7%)

14 (19.2%)

14 (19.2%)

28 (38.4%)

28 (38.4%)

15 (20.5%)

15 (20.5%)

Question options

Very frequently (daily or near daily)

Frequently (2-3 times per week)

Occasionally (1-4 times per month)

Rarely (less than once per month)

Never

Optional question (73 response(s), 1 skipped)

Question type: Radio Button Question

Page 33 of 47

Page 142 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q22 How satisfied are you with the availability of on-street parking in your neighborhood?

1 (1.4%)

1 (1.4%)

2 (2.8%)

9 (12.5%) 2 (2.8%)

9 (12.5%)

22 (30.6%)

22 (30.6%)

38 (52.8%)

38 (52.8%)

Question options

Very Satisfied

Satisfied

Neutral

Dissatisfied

Very dissatisfied

Optional question (72 response(s), 2 skipped)

Question type: Radio Button Question

Page 34 of 47

Page 143 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Q23 Any additional comments about parking?

Sarah J

6/28/2025 12:28 PM

Jeff b gisselbeck

6/28/2025 03:09 PM

cgaz

6/28/2025 06:15 PM

peter334

6/28/2025 07:44 PM

Melissa Cohen

6/28/2025 08:12 PM

Would like to continue to have availability of on street parking as

needed

would like to have it on both sides

It rarely happens, but for several days this week, while a neighboring

apartment complex was repaving its roadway, residents parked their

cars in the bike line on Cahill Road. It felt unsafe for bikers.

none

If cars park on both sides of the road, it can be difficult to fit a vehicle

in between.

Matt Melsen

6/29/2025 01:06 PM

Worried that sidewalks will reduce the width of our street and not

allow for easy street parking. We have a steep driveway so our

guests really can only park on street.

michael.r.lommel

6/29/2025 02:34 PM

n/a

Dan!

6/29/2025 02:58 PM

Antrim Rd should not have street parking by 70th. Gets very crowded,

and the living facility staff park on the street, making it very narrow.

Brian

6/30/2025 06:23 AM

On Lee Valley Circle, when people park on both sides of the street it

becomes a one lane road. I'd like to see no parking signs on one side

of the street to keep it open for two way traffic.

Plenty of on street parking

Neighbors visitors often park in front of mailbox.

Steve Thompson

7/03/2025 05:23 AM

druckd666

7/05/2025 08:10 AM

Page 35 of 47

Page 144 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Ryan

7/06/2025 02:20 PM

MTK

7/06/2025 05:17 PM

sburns

7/06/2025 07:33 PM

Liz Moore

7/10/2025 12:53 PM

Linda Berg

7/12/2025 10:53 AM

dubesbennett

7/15/2025 03:48 PM

Liz Moore

7/16/2025 12:20 PM

SusanJ

7/17/2025 07:34 AM

Debasish N Mallick

7/28/2025 01:33 PM

Please don’t narrow the street. When there are cars parking in the

street, they tend to be associated with large gatherings at

neighboring houses. If the street goes down to the widths indicated

on Better Together, we are concerned about a lack of space for traffic

heading in both directions.

No

no to sidewalks. they would ruin the neighborhood.

Our street is wide, parking is excellent.

I drive down our street very slow…people often come up shannon

turn on the side of street …to cut corner…I away stop to be sure a

car in not coming north on Shannon…on my side of street

I appreciate the ability to park on either side of the street

Keep them off the street as you are doing (restrictions)

N/A regarding parking. I live in a townhouse association not right on

the street.

Everything is ok

jelliott5904

8/14/2025 11:25 AM

no

Optional question (21 response(s), 53 skipped)

Question type: Essay Question

Q24 Please tell us anything else you would like us to know about existing traffic or street

conditions in your neighborhood.

Page 36 of 47

Page 145 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Klstone

6/28/2025 11:55 AM

Sarah J

6/28/2025 12:28 PM

Jeff b gisselbeck

6/28/2025 03:09 PM

Salaar

6/28/2025 03:11 PM

Alan Weiner

6/28/2025 03:46 PM

cgaz

6/28/2025 06:15 PM

peter334

6/28/2025 07:44 PM

Melissa Cohen

6/28/2025 08:12 PM

Page 37 of 47

Village Drive looks like and drives like a lunar landing. It has patch on

top of patch.

we want the neighborhood to be a safe place for kids to play,

pedestrians, and bikers

street is in poor condition. I dont think we need sidewalks

When they came to do construction, they tore up the entire ground

and left and didn't fix it

The area is a mishmash of curvy and hilly roads. I have lived at my

current address for 18 years and outside of the absolute poor quality

of the roads, we have no issues with speeding or wreck less driving.

If you are not from our neighborhood, you will drive really slow

because of the twisty hilly roads and the potholes and road breaking

apart. We do not need any sidewalks or wider roads, we just need

new grading, paving, curbs and proper drainage at the low points of

the road. Sidewalks will ruin the quaintness of the entire Park Knolls

Neiborhood. I love all of the green space we have and like I have said

already, the twisty and hilly roads are not conducive to speeding or

wreck less driving.

Appreciate the city patching up the potholes on Village Drive this

week.

Asphalt sorely needs to be replaced. The snow plows annually tear

up any repairs due to the necessary maneuvering in the cul de sac to

remove snow. Road seems to be getting narrower due to overgrowth

from the sides. It's very limited traveled road, so not a big deal. Our

driveway apron is crumbling asphalt, so would like further information

on how much concrete apron we can expect and how much we might

need to prepare prior to reconstruction.

Before a sidewalk plan is finalized, I expect that homeowners whose

properties are affected by this will be contacted and have an

opportunity for input. With our house on the corner of Fleetwood Drive

and Lanham Lane, we are concerned about the long length of

sidewalk that may be installed on our property and the long term

impact of that (upkeep, snow removal, liability, etc.)

Page 146 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

mas54po

6/29/2025 07:13 AM

Paul Cashin

6/29/2025 11:47 AM

Matt Melsen

6/29/2025 01:06 PM

Roger Thomas

6/29/2025 01:34 PM

End of street--asphault in severe disrepair. Snow pushed into our

property and tears up grass/landscaping. We are having extensive

landscaping done and would like to not have snow pushed into our

yard

Concrete roadways are brutal on our cars' suspensions.

Given Fleetwood is a thru street, there is considerably more traffic

than one might think which causes the street to get tight/dangerous

during busy times. Delivery trucks/workers/contractors parking on

side while busy thru traffic is coming makes it wide enough for only

one car right now Please consider other utility projects - such as US

Internet, Centerpoint, Xcel, etc. - to minimize the yard impacts.

Street conditions are kind of bad in the area between 70th and Dewey

Hill road. I feel like Hilary Lane should have been reengineered when

it was resurfaced. I don't understand how the standing water on the

sidewalk and road hasn't been fixed. There are a lot of kids who walk

down Antrim Road, Dublin and Kerry. When I moved in the neighbors

said they shouldn't walk on the road because it is dangerous and he

was right. The road is narrow and there is a lot of trees which makes

it more dangerous.

michael.r.lommel

6/29/2025 02:34 PM

We'd prefer a marginally wider street with a bike/walking lane as

opposed to a sidewalk.

Dublin

6/29/2025 02:53 PM

Dan!

6/29/2025 02:58 PM

C

6/29/2025 07:13 PM

Brian

Page 38 of 47

We live on a quiet circle - it is perfect the way it is Somehow the city

thinks everyone wants the urban smashed together setting . Peaceful

is nice . If you’d like to know what would be nice is overhaul Cahill - it

looks like a slum - rental U hauls - the buildings are tired . We

deserve better - please help

Guests park on Antrim Ct, and it is safe and out of the way.

It’s fine. No need for excess construction projects, often taking years

at a time for minimal change.

Lee Valley Circle was supposed to be reconstructed in 2020 (if I

Page 147 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

6/30/2025 06:23 AM

remember correctly). The street is pitted and breaking apart and I

have heard nothing of plans to repair or replace the roadway surface.

GGood

6/30/2025 12:02 PM

CharlieBray1

6/30/2025 03:22 PM

G

6/30/2025 09:39 PM

JanFS

7/01/2025 02:43 AM

swankefamily

7/02/2025 06:53 AM

As our neighborhood expressed several years ago to City Council, we

still feel that our small section of this project could be adequately

addressed via a mill and overlay approach, rather than a full

reconstruction.

We do not need sidewalks here. This is a residential street and it

would be a giant waste of money. There is not enough traffic to

warrant this spending. Anything I can do to prevent this from

happening I will do.

Please do not narrow the street ( Antrim to Shannon) or put curbs in

on either side from Antrim off 70th street to Shannon. It’s windy and

even when you take the curve wide, it gets close to coming in contact

with another car. If the street is narrowed in any way or curbs are put

in there won’t be any space for cars to pass by. In the winter, the

snow will make it even harder. Parking for maintenance vehicles, and

guests will further the hinderance and will make it all but impossible to

get two cars through. Please do not narrow Antrim road to Shannon

road. It won’t work.

Speed limit too slow. Village Drive is a disaster. Needs repair.

Traffic volume--both vehicle and pedestrian--is minimal on our dead-

end street. We currently don't have sidewalks, and we don't need

them, as people can walk safely without them.

Steve Thompson

7/03/2025 05:23 AM

The streets are wide enough that sidewalks seem redundant and

unnecessary. There is no need. It’s a solution to a problem that

doesn’t actually exist.

Karin Wentz

7/03/2025 06:01 AM

druckd666

7/05/2025 08:10 AM

Page 39 of 47

We hope our street (Down Road) stays as is--for example, we would

strongly discourage adding sidewalks. The trees along the street are

a desirable feature to keep, and these might need to be removed if

sidewalks are added.

Neighbors who intentionally put yard debris into the street expecting

the city to remove it is unacceptable and should be punished.

Page 148 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Drea

7/06/2025 04:24 PM

I am strongly against adding sidewalks to fleetwood drive as it would

make the roads smaller and we do not have enough traffic for this to

make any sense. Use our money elsewhere.

MTK

7/06/2025 05:17 PM

jachapman9094

7/08/2025 03:59 PM

Csazenski

7/09/2025 09:59 PM

Liz Moore

7/10/2025 12:53 PM

Wondering when Edina plans to upgrade our street?

Our neighborhood does not need sidewalks. It’s a low traffic area.

I’m not interested in getting the sidewalk or bike path. Will make road

to small and to congested

Other than Lanham Lane is a pothole disaster and no amount of

resurfacing will help.

Linda Berg

7/12/2025 10:53 AM

snow plow always leaves huge pile of snow @ end of our

driveway….is by the mail box &amp; unssafe

dubesbennett

7/15/2025 03:48 PM

The streets feel safe and everyone drives carefully as it is not a

through street so we all know the people coming and going.

Liz Moore

7/16/2025 12:20 PM

No sidewalks - people have plenty of nearby parks. all it would add is

more upkeep and costs for village and taxpayers.

Liz Moore

7/16/2025 12:26 PM

rm

7/20/2025 01:41 PM

The street is in good condition and no sidewalks or bike paths are

needed or wanted.

Our street has minimal car traffic. Lots of people walk and bike with

no problem

Liz Moore

7/23/2025 11:47 AM

It's very safe. Students from nearby high school practice skiing using

roller blades. Our street is hilly and perfect for this. No sidewalks

please. Lanham Lane is great without them.

Debasish N Mallick

No issues experienced over the last 25 years

Page 40 of 47

Page 149 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

7/28/2025 01:33 PM

EdinaChris

8/06/2025 11:03 AM

Jamie Glover

8/07/2025 01:19 PM

CJM

8/08/2025 06:58 AM

Please don't add sidewalks to Kemrich Drive as they aren't necessary

given the low traffic volume. It will also damage the curb appeal of

many homes.

I know that there is a plan to put a sidewalk on Fleetwood Drive. From

my perspective, I don't feel unsafe walking on the street (and see

people walking all of the time). I do have safety concerns regarding

kids biking on our streets, however. I'm worried that if we had a

sidewalk (and my understanding is that bikers, maybe with the

exception of very young kids, are not supposed to bike on sidewalks),

that the narrower street will make it even more unsafe for kids to bike

on the street.

Kemrich Drive is very quiet street, walking and biking is very safe. I

walk multiple times a day throughout Kemrich, Lanham, and

Fleetwood. Many people walk in groups and with strollers along side

their children on bikes, it is very safe to do so. Sidewalks are not

needed and would even prohibit the group from staying together.

Normamuldowney

8/11/2025 05:38 PM

Cars speed coming around the bend at Antrim Road and Dublin

Often drinking on wrong side of road

jelliott5904

8/14/2025 11:25 AM

Don't put in barrier curbing. It forces bikes farther from the edge.

Likewise, narrowing the street also forces bikes and pedestrians

closer to the traffic, contrary to the talk about being bike friendly.

Drive through Braemar on Hillary and see the flooding only where

there is curbing.

Optional question (42 response(s), 32 skipped)

Question type: Essay Question

Q25 What is your address?

JamesD

6/28/2025 11:32 AM

Klstone

6/28/2025 11:55 AM

Page 41 of 47

7204 Lanham Lane

5501 Village Drive

Page 150 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Sarah J

6/28/2025 12:28 PM

Jeff b gisselbeck

6/28/2025 03:09 PM

Salaar

6/28/2025 03:11 PM

John Uecker

6/28/2025 03:43 PM

Alan Weiner

6/28/2025 03:46 PM

Joe Johnson

6/28/2025 04:48 PM

thomaspmagne

6/28/2025 04:51 PM

Scott Williams

6/28/2025 05:18 PM

cgaz

6/28/2025 06:15 PM

peter334

6/28/2025 07:44 PM

Melissa Cohen

6/28/2025 08:12 PM

mas54po

6/29/2025 07:13 AM

Nancy Drake

6/29/2025 09:20 AM

Elizabeth Bennett

6/29/2025 11:20 AM

Page 42 of 47

5804 kemrich Drive

7008 Lanham ln

7001 Lee Valley Circle

7105

7105 Tralee Drive

123 condo dr

7125 Shannon Dr.

5805 Kemrich Dr.

5544 Village Drive, Edina 55439

7032 Wexford Rd

7100 Fleetwood Drive

7117 Tralee Dr. Edina 55439

5900 Lee Valley Road

7112 Shannon Drive

Page 151 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Paul Cashin

6/29/2025 11:47 AM

cristina notermann

6/29/2025 11:55 AM

Matt Melsen

6/29/2025 01:06 PM

Roger Thomas

6/29/2025 01:34 PM

tiamat2pi

6/29/2025 01:49 PM

Laura Gillund

6/29/2025 02:14 PM

ndanielsen

6/29/2025 02:25 PM

7009 Weston Cir

7221 fleetwood drive

7108 Fleetwood Dr

7109 Antrim Court

7001 Dublin Road

7020 Weston Circle

7100 Shannon Drive

michael.r.lommel

6/29/2025 02:34 PM

7017 Lanham Lane

Dublin

6/29/2025 02:53 PM

Dan!

6/29/2025 02:58 PM

Brutlag

6/29/2025 04:05 PM

Heath Marnach

6/29/2025 05:59 PM

C

6/29/2025 07:13 PM

Brian

6/30/2025 06:23 AM

Page 43 of 47

6000 Dublin Circle

7101 Antrim CT

7109 Fleetwood Drive

7201 Lanham Ln

Kemrich Drive

7015 Lee Valley Circle

Page 152 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Johnmlohmann

6/30/2025 06:41 AM

Steven Manacek

6/30/2025 11:00 AM

GGood

6/30/2025 12:02 PM

CharlieBray1

6/30/2025 03:22 PM

desa0080

6/30/2025 04:32 PM

G

6/30/2025 09:39 PM

JanFS

7/01/2025 02:43 AM

maggiedevoe

7/01/2025 05:26 AM

tamie

7/01/2025 09:14 AM

swankefamily

7/02/2025 06:53 AM

EITAN MEDINI

7/02/2025 08:28 AM

Steve Thompson

7/03/2025 05:23 AM

Karin Wentz

7/03/2025 06:01 AM

7101 Tralee Dr

5901 Lee Valley Road

7028 Shannon Drive

7212 Fleetwood Drive

7208 Fleetwood Drive Edina MN 55439-1810

5908 Lee Valley Road

5501 Village Drive

6004 Dublin Circle

5511 village drive

7020 Shannon Drive, Edina, MN 55439

7121 Fleetwood Dr Edina MN 55439

5805 Shannon Dr.

7029 Down Road, Edina, MN 55439

ElectronLady

7133 SHANNON DR

Page 44 of 47

Page 153 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

7/03/2025 10:10 AM

Barbara Grossman

7/04/2025 08:39 AM

druckd666

7/05/2025 08:10 AM

terrirovick

7/05/2025 10:18 AM

Ryan

7/06/2025 02:20 PM

Drea

7/06/2025 04:24 PM

MTK

7/06/2025 05:17 PM

sburns

7/06/2025 07:33 PM

Keith Solsvig

7/08/2025 01:02 PM

jachapman9094

7/08/2025 03:59 PM

Csazenski

7/09/2025 09:59 PM

Liz Moore

7/10/2025 12:53 PM

Linda Berg

7/12/2025 10:53 AM

7300 Lanham Lane

7113 Shannon Drive

7100 Down Road

7216 Fleetwood

7105 fleetwood dr

7112 Lanham Lane

5725 Kemrich Dr

5713 Kemrich Drive

5721 Kemrich Drive

7024 lanham lane

7041 Lanham Lane (Transcribed by City Staff)

7104 Shannon Drive, Edina, MN 55439

John F Kortebein

7/13/2025 12:14 PM

7028 Lanham Lane

Page 45 of 47

Page 154 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

Mwild

7/13/2025 05:47 PM

dubesbennett

7/15/2025 03:48 PM

Liz Moore

7/16/2025 12:20 PM

Liz Moore

7/16/2025 12:26 PM

SusanJ

7/17/2025 07:34 AM

PXO

7/19/2025 10:33 AM

rm

7/20/2025 01:41 PM

Chazbo711

7/21/2025 10:48 AM

francis.glover

7/23/2025 08:16 AM

Liz Moore

7/23/2025 11:47 AM

7013 Dublin Rd

5708 Kemrich Drive

7024 Down Road (Transcribed by City Staff)

7104 Shannon Drive (Transcribed by City Staff)

5553 VIllage Drive

5800 Kemrich Drive.

7217 Fleetwood Drive

5511 West 70th St Edina MN 55439

7201 Fleetwood Drive

7220 Lanham Lane (Transcribed by City staff)

Debasish N Mallick

7/28/2025 01:33 PM

5709 Kemrich Drive, Edina, MN 55439

EdinaChris

8/06/2025 11:03 AM

Jamie Glover

8/07/2025 01:19 PM

CJM

8/08/2025 06:58 AM

Page 46 of 47

5721 Kemrich

7201 Fleetwood Dr

5705 Kemrich Drive

Page 155 of 275 Neighborhood Reconstruction Survey : Survey Report for 30 January 2019 to 24 August 2025

rdizzo

8/11/2025 12:10 PM

7100 Shannon Dr

Normamuldowney

8/11/2025 05:38 PM

6 Antrim Terrace

jelliott5904

8/14/2025 11:25 AM

5904 Lee Valley Road

Mandatory Question (74 response(s))

Question type: Single Line Question

Page 47 of 47

Page 156 of 275 APPENDIX K

Correspondence from Residents

Page 157 of 275

APPENDIX L

Proposed Typical Sections

Page 158 of 275

APPENDIX M

Preliminary Assessment Roll

Page 159 of 275

Date: October 23, 2025

Meeting: Transportation Commission

Agenda Number: 6.2

Item Type: Report and Recommendation

BOARD & COMMISSION

ITEM REPORT

Item Activity: Discussion

Prepared By: Andrew Scipioni, Transportation Planner

Department: Engineering

Item Title:

Parklawn Court Roadway Reconstruction Project

Action Requested:

Review and comment on the proposed 2026 roadway reconstruction project.

Information/Background:

Assistant City Engineer Aaron Ditzler, Senior Project Engineer Ben Jore and Graduate Engineer Chris

Moore will present the Prospect Knolls A/C/D roadway reconstruction project. See attached draft

engineering study.

Supporting Documentation:

1.

2.

Draft Engineering Study

Appendices

Page 160 of 275

ENGINEERING STUDY

PARKLAWN COURT NEIGHBORHOOD

ROADWAY RECONSTRUCTION

Parklawn Court

IMPROVEMENT NO. BA-467

OCTOBER 17, 2025

ENGINEERING DEPARTMENT

CITY OF EDINA

I hereby certify that this report was prepared by me or under my

direct supervision and that I am a duly Licensed Professional

Engineer under the laws of the State of Minnesota.

Aaron Ditzler Reg. No. Date

Page 161 of 275

Engineering Study

Parklawn Court Neighborhood Reconstruction BA-467

October 17, 2025

SUMMARY:

INITIATION:

The project involves reconstruction of local concrete streets, replacement of existing

concrete curb and gutter, construction of new sidewalk, lining of sanitary sewer,

localized rehabilitation of the sanitary sewer, watermain and storm sewer systems in

the neighborhood.

The estimated total project cost is $X_________. 47.40% of the roadway cost will

be funded through property taxes and 52.60% will be funded through special

assessments at a rate of approximately $X_________ per residential equivalent unit

(REU). Utility improvements amount to $X_________ and will be funded through

the City’s utility funds. Sidewalk improvements are estimated to cost $X_________

and will be funded through the Pedestrian and Cyclist Safety (PACS) Fund.

The project was initiated by the Engineering Department as part of the City’s

Neighborhood Reconstruction Program, identified in the Capital Improvement Plan.

The project complies with the City’s Living Streets Policy, Vision Edina’s mission

statement to “provide effective and valued public services” and “maintain a sound

public infrastructure” and the “Strong Foundations” City budget goal. This project

addresses updating substandard infrastructure with improvements associated with the

roadway condition, watermain system, storm sewer system, sanitary sewer system

and pedestrian and bicycle facilities.

LOCATION:

The project includes Parklawn Court. A detailed location map of the project is

shown in Figure 1.

Figure 1: Project Area Map

2

Page 162 of 275

Engineering Study

Parklawn Court Neighborhood Reconstruction BA-467

October 17, 2025

EXISTING

CONDITIONS:

Roadways

Parklawn Court was originally constructed in 1966. Various concrete panels have

been replaced over the years, but no maintenance has been performed over the entire

street (see Photo 1).

Photo 1: Parklawn Court Neighborhood, 1967

Parklawn Court, as a concrete street, has integral curb. The roadway width is 36’

(measured from the face of curb to the face of curb). A recent geotechnical evaluation

of the project area performed by Braun Intertec showed the roadway section varies

from 8” of concrete pavement over an apparent aggregate base followed by a

combination of silty sand and sand with silt soils.

As part of the City’s Pavement Management Program, all streets are regularly

evaluated and rated on a scale from 1 to 100; 100 representing a brand-new road

surface and 0 being extremely poor. This rating is referred to as the Pavement

Condition Index (PCI) and is determined based on existing conditions and defects

(alligator cracking, raveling, potholes, etc. for bituminous streets ; popouts,

longitudinal and transverse cracking, potholes, etc. for concrete streets). The average

3

Page 163 of 275

Engineering Study

Parklawn Court Neighborhood Reconstruction BA-467

October 17, 2025

PCI for the City of Edina is 78 and the average PCI for Parklawn Court is 51. An

example of the current pavement condition can be seen in Photo 2.

Photo 2: Existing Pavement Condition

Traffic and Crash Data

Given the location and context of this project, staff did not measure traffic

volumes or speeds. It is assumed that the volume and speed are comparable to most

local streets in the City (≤ 1,000 vehicles per day, 85th-percentile speeds ≤

30 miles per hour, respectively). Crash data for this project is shown in Appendix A.

Multi-Modal Transportation

Pedestrian Facilities

There are no pedestrian facilities within the project area. There are sidewalks on

Parklawn Avenue and W 76th Street immediately adjacent to the project area (see

Appendix B).

Bicycle Facilities

There are no bicycle facilities within the project area. The project area is less than ¼

mile (or a 1-minute bike ride) from the Nine Mile Creek Regional Trail (see Appendix

C).

Transit Facilities

Metro Transit’s Local Route 6 serves this neighborhood, with bus stops along

Parklawn Avenue and W 76th Street. Local Routes 537 and 540 also operate within a

½ mile of the project area. Most of the bus stops adjacent to the project area are

4

Page 164 of 275

Engineering Study

Parklawn Court Neighborhood Reconstruction BA-467

October 17, 2025

accessible by sidewalks; none have shelters. Parklawn Court is also within the service

area of the City’s CloverRide circulator bus service.

DESIGN INPUT:

Public Utilities

Sanitary Sewer

The sanitary sewer system consists of

SECTION INCOMPLETE

Watermain

The watermain system consists of

SECTION INCOMPLETE

Storm Sewer

The storm sewer network is in the Nine Mile Creek Watershed District. The system

consists of

SECTION INCOMPLETE

Private Utilities

Gas, electric, communications and cable utilities are present along Parklawn Court.

These utilities are a combination of overhead facilities located in backyards and

underground utilities along the boulevards.

City Council

2018 Pedestrian and Bicycle Master Plan

This plan, part of the 2018 Comprehensive Plan, was developed to guide the City’s

efforts to create a comprehensive pedestrian and bicycle network. As shown in

Appendices B and C, there are no proposed pedestrian and bicycle facilities within

the project area.

2015 Living Streets Policy

This policy balances the needs of motorists, pedestrians, bicyclists and transit riders

in ways that promote safety and convenience, enhance community identity, create

economic vitality, improve environmental sustainability and provide meaningful

opportunities for active living and better health. The City will apply the Policy to all

street projects, including those involving operations, maintenance, new construction,

reconstruction, retrofits, repaving, rehabilitation or change in the allocation of

pavement space on an existing roadway. The Living Streets Plan includes 15 principles

to guide implementation of the Policy, divided into four categories: All Users and All

Modes, Connectivity, Context Sensitivity and Sustainability. Below is a summary of

how these principles are incorporated into this project:

All Users and All Modes – This project will improve mobility and access to the

transportation network for a variety of users, including pedestrians, cyclists, children,

seniors and people with disabilities. Replacement of the pavement surfaces and traffic

control signage will enhance safety and convenience for all users.

Connectivity – This project involves maintaining a transportation system that can

accommodate all modes of travel.

5

Page 165 of 275

Engineering Study

Parklawn Court Neighborhood Reconstruction BA-467

October 17, 2025

Context Sensitivity – Engineering strives to preserve and protect natural features

within or adjacent to construction sites where feasible, including trees, waterways

and sensitive slopes. Residents within the project area were invited to complete a

questionnaire soliciting input on project design components, including multi-modal

transportation, street lighting and local drainage problems.

Sustainability – Engineering works closely with Public Works to implement

infrastructure improvements with consideration of lifecycle costs and future

maintenance. The new roadway section can be easily maintained long-term with the

use of proactive rehabilitation treatments, which will significantly extend the life of

the pavement. Reductions in impervious surfaces benefit water quality and may lessen

the demand for chemicals to manage snow and ice (such as chloride). Construction

operations are required to use the smallest footprint necessary to complete the work;

this includes utilizing trenchless technologies, such as pipe bursting or cured-in-place

sanitary sewer system, minimizing regional wastewater treatment, reducing the risk

of sewage surcharges, and limiting the risk of back-ups to residential properties.

Relevant portions of the Living Streets Plan can be found in Appendix F.

2018 Comprehensive Water Resource Management Plan

SECTION INCOMPLETE

Climate Action Plan

The CAP identified the following strategies that align with this roadway

reconstruction project.

Transportation and Land Use (TL) 1: Decrease community-wide vehicle miles traveled

by 7% by 2030.

Action TL 1-2: Accelerate building on-street and off-street protected bike lanes,

sidewalks, crosswalks, and other walking infrastructure in high-need areas and fill

connectivity gaps as identified in the City's Bike and Pedestrian Master Plan.

TL 2: Double public transit commuter ridership from 3.3% to 6.6% by 2030.

Public Works

A draft engineering study was provided to the City’s Public Works Department.

COMMENTS REQUESTED

Police and Fire

A draft engineering study was provided to the City’s Police and Fire Departments.

COMMENTS REQUESTED

Edina Transportation Commission

Prior to the Edina Transportation Commission (ETC) regular meeting on October

23, 2025, a draft engineering study was provided for review.

[2025 COMMENTS]

6

Page 166 of 275

Engineering Study

Parklawn Court Neighborhood Reconstruction BA-467

October 17, 2025

PROPOSED

IMPROVEMENTS:

Residents

Residents were invited to an informational presentation and were able to directly ask

questions to staff in August 2025. Residents were notified of a recorded video version

of the August 2025 informational presentation posted on the Better Together Edina

website, where residents were able to ask questions to staff from the Better Together

Edina website, as well as telephone and email. Materials from the August 2025

informational presentation can be found in Appendix I.

On June 25, 2025, residents were asked to complete a questionnaire, soliciting

feedback on motorized and non-motorized transportation and local drainage

problems within the project area. Unique feedback was requested on potential

support of sidewalks on Parklawn Court. Unfortunately, only one resident completed

the questionnaire. We will re-engage the owners and residents again before the

Public Hearing to attempt to get more responses.

The full questionnaire and one response can be found in Appendix J.

Relevant correspondence from residents regarding the project can be found in

Appendix K.

The proposed improvements acknowledge many of the comments and concerns

raised by residents throughout the information gathering process, while still

maintaining the desired minimum standards of Engineering, Public Works and other

City staff. The proposed improvements also align with the Budget Work Plan values

and goals developed by the City Council and staff.

Roadways

Typical Section

The concrete roadway is proposed to be completely reconstructed to the subgrade.

A minimum of 8” of aggregate base material will be graded and compacted as the base

layer prior to placement of 2.5” of bituminous non-wear and 1.5” of bituminous wear

course.

Unsuitable subgrade materials will be replaced as necessary to provide adequate

support for the new roadbed. The reconstructed sections will meet the requirements

of a minimum 20-year pavement design life based on projected traffic loadings.

Parklawn Court is designated as a Local Street in the Living Streets Plan. Per this

plan’s design guidelines, Local Streets have a typical width of 27’ (measured from the

face of curb to the face of curb) without sidewalks or 24’ with an 8’ shared-use path

or 5’ sidewalk on one side. Parklawn Court is proposed to be 27’ wide to

accommodate the higher frequency of larger vehicles that serve the adjacent multi-

family properties.

Cul-de-Sac

7

Page 167 of 275

Engineering Study

Parklawn Court Neighborhood Reconstruction BA-467

October 17, 2025

The cul-de-sac bulb is proposed to be reduced in size to the City’s standard 70’

diameter. This size will accommodate large emergency vehicles while also reducing

impervious surfaces within the neighborhood.

Parking

Per the Living Streets Plan, on-street parking should be evaluated based on

classification, adjacent land uses, existing demand and costs of construction and

maintenance. Parking is proposed to be restricted within the cul-de-sac bulb, with

one-sided parking provided along the roadway to allow space for proposed sidewalks

on both sides.

The existing and proposed roadway widths, sidewalks and parking recommendations

are also shown in Figure 3, Table 1 and Appendix L.

Existing 36’ road width, two-sided parking

Proposed 27’ road width, one-sided parking

Figure 3: Parklawn Court

Street

Existing

Roadway

Width

(face to

face),

feet

Proposed

Roadway

Width

(face to

face), feet

Sidewalk

Width,

feet

Boulevard

Width,

feet

Parking

Parklawn Court

36

Cul-de-sac

* Diameter of the cul-de-sac

97.5*

27

70*

5

5

0-5

0-5

Southeast

Side

None

8

Page 168 of 275

Engineering Study

Parklawn Court Neighborhood Reconstruction BA-467

October 17, 2025

Table 1: Street Widths, Sidewalks and Parking

Roadway Signage

All traffic signage within the project area, including street name blades, will be replaced

to improve visibility and reflectivity (see Appendix E). All new signs will conform to

the standards of the Manual on Uniform Traffic Control Devices (MUTCD).

Multi-Modal Transportation

Staff seeks to balance the recommendations of the City’s guiding documents (Living

Streets Plan, Pedestrian and Bicycle Master Plan and Climate Action Plan), feedback

from affected residents, available right-of-way and potential tree and infrastructure

impacts. Staff is proposing new sidewalks along both sides of Parklawn Court and

around the cul-de-sac bulb (see Figure 4).

Figure 4: Existing and Proposed Pedestrian Facilities

Although no new facilities are recommended in the Pedestrian and Bicycle Master

Plan, the proposed sidewalks are consistent with the character of the neighborhood

as many adjacent local streets have pedestrian facilities on both sides (Parklawn

Avenue, West 76th Street and Gallagher Drive). The proposed sidewalks also

support the Climate Action Plan goal to “accelerate building…sidewalks and other

walking infrastructure in high-need areas.” Compared to Edina overall, this

neighborhood has a higher percentage of population identifying as Black, Indigenous,

or People of Color (BIPOC); a higher percentage of population in poverty; a higher

percentage of population under the age of 18; and a higher percentage of population

9

Page 169 of 275

Engineering Study

Parklawn Court Neighborhood Reconstruction BA-467

October 17, 2025

that is foreign-born. The proposed multi-modal facilities will improve access,

mobility and safety for these populations.

The grass boulevards that will separate the new curb and the proposed sidewalks

are proposed to be 5’-wide but may vary depending on construction conflicts.

Separation from vehicle traffic creates a more pedestrian-friendly environment and

is preferred by Public Works for snow storage.

All adjacent pedestrian curb ramps will be reconstructed to meet the current design

standards of the Americans with Disabilities Act (ADA), and portions of the existing

sidewalks will be reconstructed as necessary.

The sidewalks will be maintained by adjacent property owners as they are not

within state or county right-of-way, along Municipal State Aid routes, or included in

the City’s Active Routes to School Plan.

Bicycle Facilities

There are no proposed bicycle facilities in this project area.

Transit Facilities

An accessible boarding area (also referred to as an ADA pad) will be constructed at

the bus stop adjacent to the project area. Staff will coordinate with Metro Transit

on the design and location of the pad.

Public Utilities

Sanitary Sewer

The sanitary sewer main has been televised, and portions will be repaired using a

combination of open cut and cured-in-place-pipe (CIPP) methods. These repairs will

address the issues of sags, cracks and groundwater infiltration into the sewer main.

The manhole castings will also be removed and replaced to reduce inflow and

infiltration of stormwater.

Watermain

SECTION INCOMPLETE

Storm Sewer

Because the existing curb and gutter are integral with the concrete pavement, they

will be replaced as part of the roadway pavement reconstruction, providing a

continuous, functional conduit for stormwater. The existing drainage structures will

be removed and replaced due to their poor condition as well as the proposed

roadway width change. Sump drains will be installed where feasible to allow property

owners to connect their sump pump discharges directly into the storm sewer system.

Increasing stormwater storage in Fred Richards Park will be necessary in the future

to help reduce flood risk on Parklawn Court.

Street Lighting

The City owned street lighting system will be removed and replaced by Xcel Energy

due to its poor condition.

10

Page 170 of 275

Engineering Study

Parklawn Court Neighborhood Reconstruction BA-467

October 17, 2025

Staff is preparing an agreement with Xcel Energy for the proposed street lighting

system work. The agreement will detail each agency’s responsibilities regarding

construction, cost allocation, ownership, and future maintenance. Ownership and

maintenance of the street lighting system on Parklawn Court will transition from the

City to Xcel Energy.

Private Utilities

Staff will meet with representatives of several private utility companies in December

2025, to discuss the proposed 2026 reconstruction project and preliminary

improvements. Portions of the private utility networks may receive upgrades prior to

construction; however, this work is not part of the City’s project.

RIGHT-OF-WAY/

EASEMENTS:

Existing roadway right-of-way for Parklawn Court is 60’. It is anticipated that this

project can be constructed within the existing ROW. A portion of the in place

landscape

infrastructure

improvements and will need to be removed to complete the necessary work.

interfere with some of the proposed

items will

PROJECT COSTS:

The total estimated project cost is $_________, (see Table 2). The total cost

includes direct costs for engineering, clerical and construction finance costs from the

start of the project to the final assessment hearing.

Item

Amount

Total Cost

Street Lighting

$ _______

$ _______

$ _______

$ _______

$ _______

$ _______

$ _______

Roadway

Roadway

Roadway Total:

Sanitary Sewer

Watermain

Storm Sewer

Utility Total:

Sidewalk Total:

Project Total:

Funding

Source

Special

Assessments

Special

Assessments

Property

Taxes

$ __________

City Utility

Funds

PACS Fund

$ __________

$ __________

ASSESSMENTS:

Assessments will be levied against the benefiting adjacent properties pursuant to

Chapter 429 of the Minnesota State Statutes. Based on the City’s Special Assessment

Policy, there are 41.5 roadway residential equivalent units (REUs) in the Parklawn

Table 2: Estimated Project Costs

11

Page 171 of 275

Engineering Study

Parklawn Court Neighborhood Reconstruction BA-467

October 17, 2025

Court project area. The estimated assessment per REU is $_______ (see Figure 5).

The preliminary assessment roll can be found in Appendix M.

Figure 5: Preliminary Roadway Assessment Map

PROJECT SCHEDULE:

The following schedule outlines the future tasks to be performed related to the

project:

Neighborhood Informational Open House

ETC Engineering Study Review

Receive Engineering Study

Open Public Improvement Hearing

Close Public Improvement Hearing

Public Improvement Hearing Council Decision

Bid Opening

Award Contract/Begin Construction

Complete Construction

Final Assessment Hearing

August 26, 2025

October 23, 2025

December 9, 2025

December 9, 2025

December 11, 2025

December 17, 2025

March/April 2026

Spring 2026

Fall 2026

October 2027

RECOMMENDATION:

Staff believes the project can be completed during the 2026 construction season. Staff

believes the construction of this project is feasible, cost effective and necessary to

improve the public infrastructure along Parklawn Court.

APPENDIX:

12

Page 172 of 275

Engineering Study

Parklawn Court Neighborhood Reconstruction BA-467

October 17, 2025

A. Crash Data

B. Comprehensive Plan Update – Pedestrian Facilities

C. Comprehensive Plan Update – Bicycle Facilities

D. Sewer Blocks and Watermain Breaks

E. Street Lights and Signs

F. Living Streets Plan

G. Edina Transportation Commission Meeting Minutes

H. Edina Transportation Commission Advisory Communication

I. Neighborhood Informational Presentation Materials

J. Resident Questionnaire

K. Correspondence from Residents

L. Proposed Typical Sections

M. Preliminary Assessment Roll

13

Page 173 of 275

APPENDIX A

Traffic and Crash Data

Page 174 of 275

Parklawn Court Reported Crashes 2015-2025

#

Crash Type

Info

Ran off road

Ran off road

Icy road condition, hit light pole

Intoxicated driver hit light pole

Left turn

Eastbound vehicle turn left into

parking lot was hit by WB driver

approaching Parklawn Ave

Rear-end

Rear-end

Parked car rear-ended

Parked car rear-ended

Rear-end

Parked car rear-ended

1

2

3

4

Date

January

2015

March 2022

September

2023

July 2021

April 2024

October

2026

Page 175 of 275 APPENDIX B

City Comprehensive

Plan Update –

Pedestrian Facilities Map

Page 176 of 275

Legend

Existing Sidewalk

Proposed Twin Loops

Proposed Sidewalk

Existing Shared-Use Path

Proposed Shared-Use Path

Nine Mile Creek Regional Trail

Proposed CP Rail Regional Trail

Weber

Park

44TH ST W

MALONEY AVE

Van Valkenburg

Park

INTERLACHEN BLVD

D

R

R

E

F

E

A

H

C

S

Mirror

Lake

D

R

E

K

A

L

B

VERNON AVE

D

R

N

O

S

A

E

L

G

Bredesen

Park

Mud

Lake

Arrowhead

Lake

Indianhead

Lake

Edina

High

School

VALLEY VIEW RD

Todd

Park

d

a

o

r

l

i

a

R

c

i

f

i

c

a

P

n

a

i

d

a

n

a

C

Highlands

Park

ON AVE

VERN

Yancey

Park

Melody

Lake

D

R

N

E

S

N

A

H

E

V

A

Y

C

A

R

T

MinnehahaCreek

City

Hall

50TH ST W

Arden

Park

E

V

A

E

L

A

D

D

O

O

W

54TH ST W

Edina

Community

Center

58TH ST W

Pamela

Park

VALLEY VIEW RD

Rosland

Park

66TH ST W

Lake

Cornelia

D

R

W

E

I

V

Y

E

L

VAL

70TH ST W

NineMileCreek

70TH ST W

Arneson

Acres

Park

Southdale

Library

Braemar

Arena

Braemar

Golf

Course

NineMile Creek

Lewis

Park

DEWEY HILL RD

d

a

o

r

l

i

a

R

c

i

f

i

c

a

P

n

a

i

d

a

n

a

C

D

R

L

L

I

H

A

C

78TH ST W

Lake

Edina

Public

Works

Fred

Richards

Park

76TH ST W

S

E

V

A

E

C

N

A

R

F

S

E

V

A

K

R

O

Y

Centennial

Lakes

MINNESOTA DR

City of Edina

Existing and Proposed Pedestrian Facilities

±

October 2022

Feet

0

2,250

Page 177 of 275

APPENDIX C

City Comprehensive

Plan Update –

Bicycle Facilities Map

Page 178 of 275

Legend

Advisory Bike Lane

Existing Bike Boulevard

Bikeable Shoulder

Existing Shared Bike Lane

Existing Bike Lane

Existing Buffered Bike Lane

Existing Shared-Use Path

Nine Mile Creek Regional Trail

Proposed Twin Loops

Proposed Bike Boulevard

Proposed Bike Lane

Proposed Buffered Bike Lane

Proposed Shared-Use Path

Proposed CP Rail Regional Trail

Weber

Park

44TH ST W

MALONEY AVE

Van Valkenburg

Park

INTERLACHEN BLVD

D

R

R

E

F

E

A

H

C

S

Mirror

Lake

D

R

E

K

A

L

B

VERNON AVE

D

R

N

O

S

A

E

L

G

Bredesen

Park

Mud

Lake

Arrowhead

Lake

Indianhead

Lake

Edina

High

School

VALLEY VIEW RD

Todd

Park

d

a

o

r

l

i

a

R

c

i

f

i

c

a

P

n

a

i

d

a

n

a

C

Highlands

Park

ON AVE

VERN

Yancey

Park

Melody

Lake

D

R

N

E

S

N

A

H

E

V

A

Y

C

A

R

T

MinnehahaCreek

City

Hall

50TH ST W

Arden

Park

E

V

A

E

L

A

D

D

O

O

W

54TH ST W

Edina

Community

Center

58TH ST W

Pamela

Park

VALLEY VIEW RD

Rosland

Park

66TH ST W

Lake

Cornelia

D

R

W

E

I

V

Y

E

L

VAL

70TH ST W

NineMileCreek

70TH ST W

Arneson

Acres

Park

Southdale

Library

Braemar

Arena

Braemar

Golf

Course

NineMile Creek

Lewis

Park

DEWEY HILL RD

d

a

o

r

l

i

a

R

c

i

f

i

c

a

P

n

a

i

d

a

n

a

C

D

R

L

L

I

H

A

C

78TH ST W

Lake

Edina

Public

Works

Fred

Richards

Park

76TH ST W

City of Edina

Existing and Proposed Bicycle Facilities

S

E

V

A

E

C

N

A

R

F

S

E

V

A

K

R

O

Y

Centennial

Lakes

MINNESOTA DR

±

October 2022

Feet

0

2,250

Page 179 of 275

APPENDIX D

Sewer Blocks and

Watermain Breaks

Page 180 of 275

APPENDIX E

Street Lights and Signs

Page 181 of 275

APPENDIX F

Living Streets Plan

Page 182 of 275

Living Streets Plan 2015

Safety

Health

Choice

Economy

Page 183 of 275 2. Living Streets Policy

INTRODUCTION

The Living Streets Policy was developed to provide the framework for a Living Streets Plan. The policy

initially stood alone and included sections to guide the creation of the Living Street Plan. This revised

policy is now an integral part of the Living Streets Plan.

The Living Streets Policy ties directly to key community goals outlined in the City’s 2008 Comprehensive

Plan. Those goals include safe walking, bicycling and driving; reduced storm water runoff, reduced energy

consumption, and promoting health. The Living Streets Policy also compliments voluntary City initiatives

such the “do.town” effort related to community health, Tree City USA and the Green Step Cities programs

related to sustainability. In other cases, the Living Streets Policy will assist the City in meeting mandatory

requirements set by other agencies.

The Living Streets Policy is broken up into three

parts: Vision, Principles and Implementation. The

Policy is followed by a description of core services

provided by the City of Edina that are related to or

implemented in part through Living Streets.

Mini Fact

Expect cyclists on the road. Watch for

cyclists on the road. Treat them as you

would any slow-moving vehicle.

POLICY

Living Streets balance the needs of motorists,

bicyclists, pedestrians and transit riders in ways that promote safety and convenience, enhance community

identity, create economic vitality, improve environmental sustainability, and provide meaningful

opportunities for active living and better health. The Living Streets Policy defines Edina’s vision for Living

Streets, the principles Living Streets will embody, and the plan that will guide implementation of their

construction.

LIVING STREETS VISION

Edina is a place where ...

• Transportation utilizing all modes is equally safe and accessible;

• Residents and families regularly choose to walk or bike;

Streets enhance neighborhood character and community identity;

Streets are safe, inviting places that encourage human interaction and physical activity;

• Public policy strives to promote sustainability through balanced infrastructure investments;

• Environmental stewardship and reduced energy consumption are pursued in public and private

sectors alike; and

Streets support vibrant commerce and add to the value of adjacent land uses.

8

Living Streets Plan – 2. Living Streets Policy

Page 184 of 275 LIVING STREETS PRINCIPLES

Fifteen principles guide implementation of the Living Streets Policy in the areas of all users and all

modes, connectivity, context sensitivity and sustainability. The City will incorporate these principles when

planning for and designing the local transportation network and when making public and private land use

decisions.

All Users and All Modes

Principle 1: Living Streets are high-quality transportation facilities that meet the needs of

the most vulnerable users such as pedestrians, cyclists, children, seniors and

the disabled; and

Principle 2:

Living Streets provide access and mobility for all transportation modes while

enhancing safety and convenience for all users.

Connectivity

Principle 3: The City designs, operates and maintains a transportation system that provides

a highly connected network of streets that accommodate all modes of travel;

Principle 4: The City seeks opportunities to overcome barriers to active transportation by

preserving and repurposing existing rights-of-way and adding new rights-

of-way to enhance connectivity for pedestrians, bicyclists and transit;

Principle 5: The City prioritizes improvements to non-motorized connections to key

destinations such as public facilities, public transit, the regional transportation

network and commercial areas;

Principle 6: The City will require new developments to provide interconnected street and

Principle 7:

sidewalk networks that connect to existing or planned streets or sidewalks

on the perimeter of the development; and

Projects will include consideration of the logical termini by mode. For

example, the logical termini for a bike lane or sidewalk may extend beyond the

traditional limits of a street construction or reconstruction project, in order to

ensure multimodal connectivity and continuity.

Context Sensitivity

Principle 8:

Principle 9:

Living Streets are developed with input from stakeholders and designed to

consider neighborhood character and promote a strong sense of place;

Living Streets preserve and protect natural features such as waterways, urban

forest, sensitive slopes and soils;

Principle 10: Living Streets are designed and built with coordination between business and

property owners along commercial corridors to develop vibrant commercial

districts;

Living Streets Plan – 2. Living Streets Policy

9

Page 185 of 275

Principle 11: Living Streets coordinate with regional transit networks and regional

authorities; and

Principle 12: The City will consider the fiscal context of projects and potential financial

impacts when implementing Living Streets at the project level.

Sustainability

Principle 13: Living Streets will improve the current and future quality of life of the public,

Principle 14: Living Streets will reduce environmental impacts associated with the

construction and operation of roadways; and

Principle 15: The City will increase the life span and resilience of its infrastructure and will

build infrastructure with consideration for lifecycle costs and ease

of maintenance.

LIVING STREETS IMPLEMENTATION

The City of Edina will develop Living Streets in the regular course of business of maintaining, expanding

or redeveloping the road network and will be guided by the Vision and Principles established above.

Implementation will happen predominantly through the neighborhood street reconstruction program, but

also though specific stand-alone stormwater utility, pedestrian, bicycle or safety projects.

Project prioritization is not specifically part of the Living Streets Plan. Prioritization of projects takes

place in the City’s Capital Improvement Program and Budget and is determined by the City Council with

guidance from the Living Streets Vision and Principles.

The City will actively promote and apply the Living Streets Policy and Plan by:

• Applying the Living Streets Policy and Plan to all street projects, including those involving

operations, maintenance, new construction, reconstruction, retrofits, repaving, rehabilitation or

changes in the allocation of pavement space on an existing roadway. This also includes privately

built roads, sidewalks, paths and trails.

• Drawing on all sources of transportation funding and actively pursuing grants, cost-sharing

opportunities and other new or special funding sources as applicable.

• Through all City departments supporting the vision and principles outlined in this Plan in their

work.

• By acting as an advocate for Living Streets principles when a local transportation or land use

decision is under the jurisdiction of another agency.

Projects that implement Living Streets will be guided by pedestrian and cyclist network plans and roadway

classifications and will consider the physical, social, ecologic, regulatory and economic context in a given

project area.

10

Living Streets Plan – 2. Living Streets Policy

Page 186 of 275

The project delivery system used to build Living Streets will:

Systematically engage Edina residents and project stakeholders to better inform project-level

recommendations.

• Keep Edina residents and project stakeholders informed about Living Streets and the range of services

they help provide.

• Follow minimum Living Streets design requirements and standards.

• Manage construction impacts to residents and users of streets.

Network

The creation of a Living Streets network of road, pedestrian and bicycle facilities provides mobility,

accessibility and access to people, places and spaces. The resulting interconnection of neighborhoods links

people to goods and services and to one another, and increases quality of life for those who live in, work

in, or visit the city.

Existing and planned transportation networks are identified in the City of Edina Comprehensive Plan and

other approved/adopted plans. Network plans include:

• Roadway Network (Functional Classification, Jurisdictional Classification)

Sidewalk Facilities

• Bicycle Facilities (Comprehensive Bicycle Transportation Plan)

• Active Routes to School Comprehensive Plan

• Transit Service

Network plans are approved by the City Council. In most cases, modification requires an amendment of

the Comprehensive Plan.

The expansion, creation and improvement of pedestrian and bicycle networks will be well planned and

prioritized:

• Expansion of existing networks and providing connections to key traffic generators or destinations

provide immediate benefit to all network users and is a top priority.

• Network connections serving vulnerable users such as children, seniors and the disabled are a top

priority.

• Network connections serving high-volume uses such as schools, retail destinations or regional

public transit are a top priority.

Living Streets Plan – 2. Living Streets Policy

11

Page 187 of 275 Context

Contextual variety can either constrain or create opportunity in roadway and other infrastructure

projects. The following are contexts that will be considered and will influence the planning, design and

implementation of Living Streets.

Ecological

Regulatory

Operational

Project Type

CONTEXTS OF LIVING STREETS

Water resource, ponds, wetlands, lakes, streams

Natural resouces, trees, and urban forest

Air quality

Climate

Sun and shade

Materials, waste, energy, sustainability

State Aid roadway

Watershed rules

Maintenance operations

Traffic control or functional constraints

Neighborhood street reconstruction

Public

Neighborhood street reconstruction with major

associated utility work

State Aid street reconstruction

Stand-alone sidewalk, bicycle or utility project

Public

partner lead

State

County

Transit agency

Parks district

Private

development

Will remain private

Future public

Exceptions

Living Streets principles will be included in all street construction, reconstruction, repaving and

rehabilitation projects, except under one or more of the conditions listed below. City staff will document

proposed exceptions as part of a project proposal.

• A project involves only ordinary maintenance activities designed to keep assets in serviceable

condition, such as mowing, cleaning, sweeping, spot repair, concrete joint repair or pothole filling,

or when interim measures are implemented on a temporary detour. Such maintenance activities,

however, shall consider and meet the needs of bicyclists and pedestrians.

12

Living Streets Plan – 2. Living Streets Policy

Page 188 of 275 • The City exempts a project due to an excessively disproportionate cost of establishing a bikeway,

walkway or transit enhancement as part of a project.

• The City determines that the construction is not practically feasible or cost effective because

of significant or adverse environmental impacts to waterways, flood plains, remnants or native

vegetation, wetlands or other critical areas.

• Available budget is constrained or project timing allows more efficient construction at a later date.

Engagement

Members of the public have an interest in understanding and providing input for public projects. Project

recommendations will be developed with a transparent and defined level of public engagement. The

public will have access to the decision-making process and decision makers via public meetings and

other correspondence and will be provided the opportunity to give input throughout the process. Project

reports will discuss how their input helped to influence recommendations and decisions. The City of

Edina’s Living Streets will continue to engage and solicit public input as a vital component of the project

implementation process. See Chapter 5 for a more detailed discussion regarding the purpose of and

opportunities for public engagement.

Design

The guidelines contained in the Living Streets Plan will be used to direct the planning, funding, design,

construction, operation and maintenance of new and modified streets, sidewalks, paths and trails. The

guidelines allow for context-sensitive designs.

The Design Guidelines (see Chapter 6):

• Keep street pavement widths to the minimum necessary.

• Provide well-designed pedestrian accommodation in the form of sidewalks or shared-use

pathways on all arterial, collector and local connector streets. Sidewalks shall also be required

where streets abut a public school, public building, community playfield or neighborhood park.

Termini will be determined by context.

• Provide frequent, convenient and safe street crossings. These may be at intersections designed to

be pedestrian friendly, or at mid-block locations where needed and appropriate.

• Provide bicycle accommodation on all primary bike routes.

• Allocate right-of-way for boulevards.

• Allocate right-of-way for parking only when necessary and not in conflict with Living Streets

principles.

• Consider streets as part of our natural ecosystem and incorporate landscaping, trees, rain gardens

and other features to improve air and water quality.

The Design Guidelines in this Plan will be incorporated into other City plans, manuals, rules, regulations

and programs as appropriate. As new and better practices evolve, the City will update this Living Streets

Plan. Minimum standards will guide how vehicular, pedestrian and bicycle networks interact and share

public right of way.

Living Streets Plan – 2. Living Streets Policy

13

Page 189 of 275 Benchmarks and Performance Measures

The ability to measure the performance of a plan, as well as knowing that it is functioning as it is intended,

is vitally important to overall success and the ability to sustain it. With this in mind, the City will monitor

and measure its performance relative to the Living Streets Policy. Benchmarks that will demonstrate

success include:

Every street and neighborhood is a comfortable place for walking and bicycling.

This does not mean that every street in the city will have walking and biking facilities. It means that each

neighborhood will provide a network of these facilities such that walking and biking to and through

neighborhoods is a comfortable experience.

Every child can walk or bike to school or a park safely.

It is essential that alternatives to driving to school or parks be provided to children and their caregivers.

These alternatives – walking or bicycling – will be both safe and convenient modes of transportation. See

the Edina Active Routes to School Plan for more information.

Seniors, children, and disabled people can cross all streets safely and comfortably.

Opportunities to cross all streets in Edina, including local, collectors and arterial streets, will be provided.

These crossings will be safe and comfortable for all users, regardless of age or ability.

An active way of life is available to all.

Opportunities for active living should be made available to all members of the Edina community by

connecting centers of activity via active, multimodal transportation. Each resident of and visitor to Edina

will have the ability to lead an active way of life.

There are zero traffic fatalities or serious injuries.

Perhaps the ultimate safety benchmark is zero traffic fatalities or serious injuries. Modeled from the Vision

Zero Initiative (www.visionzeroinitiative.com), an aspirational yet primary goal of Living Streets is to

achieve this high level of safety on the City’s roadways.

Reduce untreated street water flows into local waterways and reduce storm water volume.

Cost-effective stormwater best management practices (BMPs) are strategically selected to go above and

beyond regulatory requirements to provide for flood protection and clean water services through the use of

infrastructure that retains, settles, filters, infiltrates, diverts or reduces the volume of stormwater that flows

to local surface waters.

Retail streets stay or become popular regional destinations.

Part of Edina’s Living Streets vision is that “streets support vibrant commerce.” While most of the city’s

streets are residential, Edina’s business districts are a vital part of the community. The benefits of Living

Streets extend to retail streets as well, making them more attractive to businesses and consumers alike.

14

Living Streets Plan – 2. Living Streets Policy

Page 190 of 275 The City will draw on the following data to measure performance:

• Number of crashes or transportation-related injuries reported to the Police Department.

• Number and type of traffic safety complaints or requests.

• Resident responses to transportation related questions in resident surveys.

• Resident responses to post-project surveys.

• The number of trips by walking, bicycling and transit (if applicable) as measured before and after

the project.

• Envision ratings from the Institute for Sustainable Infrastructure.

• Additional performance measures may be identified as this Policy is implemented.

Mini Fact

Motorists must stop behind all

crosswalks.

Living Streets Plan – 2. Living Streets Policy

15

Page 191 of 275 APPENDIX G

Edina Transportation Commission

Meeting Minutes

Page 192 of 275

APPENDIX H

Edina Transportation Commission

Advisory Communication

Page 193 of 275

APPENDIX I

Neighborhood Informational

Meeting Materials

Page 194 of 275

2026 NEIGHBORHOOD RECONSTRUCTION

INFORMATIONAL MEETING

AUGUST 26, 2025

NAME

70‘...4_,,,...,t.c.„s

K: i, cA-4-40) 101A-2.f eei-AA....

-)

jcV

.. ...

<- F 1

e--) 4 V \, (cid:9)

-, (1 (cid:9)

-

(-_) (cid:9)

-Lt.Sia V) -- ,(4n

,--(Er---F G /55 EL i3e-z--e--..

-)" (cid:9) OLP ; 11, (cid:9) Uje_Ary\----c

r, (cid:9) ((

-P--,,5 (cid:9)

1

2

3

4 -pk

5

6

c&)1•)te

7

8 Th(1"4- 47-ky 467-0011

9 X / Fi-e 44 4) fte-i"

10

) wt (cid:9) Sal bik4k5i,,14‘44/242_

11 Ga ry -. ate,/ Icy tc-Tc/in

12 A/ 4.7,-, ki g_e_4e-is

13

14

15

16

6( r.--\-- (cid:9) C-1-7 1 \-1--..ct

, 20- vQ.., LOMMe_____k

gkk.b i_.%/0„ 1

0,(2-1A--) (cid:9) C-* )3T--c, r NAL--

l_,S T.- 0

( j.x. cf 6,-

' nfz_t_&-s-L. /-6,,

17 M -A-1-1 (cid:9)

18

<-3: k ..\ (cid:9)

LAI3is

s5

t1606 ter00 i'df 7 //kat Rrib`ve

(cid:9) (-L©P

-L. ,,,-, (cid:9)

fiecipte

AoolNeAl.,e_ i\ActiAao/

g/a4

°

19

20

21 1)OiLl- (cid:9) UPt-d0 - ALPS ( -C:9

22

23

24

25

26 44,a f -95 (cid:9)

/' (cid:9)

27

28 -If \ (A6v (cid:9)

7e/

< e_ IA (cid:9)

-l-e1152-44.

b-A-4-‘`-- -2Y---4)--7--)-,--

PZ--k 04,..ess

4t,d64;126G

a--

,- , (cid:9) D,A

ao G,&,,

cy-,4_14

29

30

ADDRESS

I frz_RF_Jr

Zoo ? Z-4-A/ 44 ik,1

70 2„6

110QQt (cid:9) Down Psockct

7,00 siiin h (cid:9)

''<i (cid:9)

5---- ,7 (cid:9)

gs - C 3 ki\i - 7o (cid:9)

S- (cid:9)

(A) (cid:9) 3T)

‘ oo 5 6 06frA 6-e,1.e.)

* 1/a 7 D

6,5-0/ (cid:9)

1-c32,c) Slukyn&AA-CDr.

-- (cid:9)

.1 (cid:9)

(,-, (cid:9) Dv-

o!... (cid:9) Ts+,

TI-

1-1M1

c,r-

.SS D/ (cid:9)

11;//a6e, 4.)r,

1,1 (cid:9)

1$

II

__,_-\--4Th-1--c;,

-Apn (cid:9)

1°2 O (cid:9)

u - )e,

7671h (cid:9) KL=-_-)e__, (cid:9) E0,6,-

---/ (2..-:' (cid:9)

c L-e-e-1-t,/- 6 %) (cid:9)

D4--t

,s, (cid:9) Cltr do _

-Pal 0 e-

riee/A)ddd ipri:/z

-7/c4 (cid:9)

-110 .c (cid:9) 1-(s2eh,,,d..,t Pr,-e

----7 k 09 (cid:9)

r-, ffil-LaoD (cid:9)

721-2_ (cid:9)

I—A p(A-

7z2V /i4All--1/7(-n:x4

(5-ei/i ijA4-70 ci, or

55-26 (cid:9) YI'llat Dr i,i t_

57/7 (cid:9) // ':- , ii4.4fAR

_ I (cid:9) Lo L 1 A g,J

7100 Poies000l DY

-7`2-61r (cid:9) F ( (d-i (cid:9)

.3-.& (cid:9) Dr.

' MA (cid:9) La h hcon tr)

Zei--/ (cid:9)

7 (cid:9) o o

4 (cid:9)

55- Li c (cid:9) w_ 7o t-4 5 .r

-k,,..

Page 1 of 4

Page 195 of 275 2026 NEIGHBORHOOD RECONSTRUCTION

INFORMATIONAL MEETING

AUGUST 26, 2025

NAME

ADDRESS

e•

i.e..' -1/1 t„,t,L5

--Iv.S.W\ (cid:9)

Syr re- LA

,A eP (cid:9)

Pc,t,,1 d c•cru 0

re('',0f„rby

Cr (cid:9)

A (cid:9)

( )-(4,-"J,4 ' (cid:9)

a

0 (cid:9)

ti

e -

,

4,,..

,..,

„s

/ArP4'L4

(-pool, 1- At.ks4\ 0\ ert_ Pi--ers'eA

/44,64EL getarz_

--B

31

32

33

34

35 Veco n t ca, er 44(w.e.V

k(-1--, .\ Sai \\ a--_SA

36

37

38

39

40

41

42 cc AiNI (cid:9)

43 Rit a &\ (cid:9) .1v1i 1 t5

44

(fil (cid:9) -S i 1((t

.4 (cid:9)

45 494f( (cid:9)

1.,,,-y\iz-

46

, .b3 kik_ (cid:9)

47

48 T-L,,_ (cid:9)

49

s--e„fr (cid:9)

50 CIL -e '49 ,e,.-L (cid:9)

51 COLYY1 .e Bmi&Acti

52 CASV100. ‘Q 0"\-€ C MCA_ le\ 0

53

54

55

56

57

58

59

60

( 1 crS Q (cid:9) S0_,\---,c),e, (cid:9) ? \

,,t _,--,.-- ;co-.,

--C:;. 164,e_

-t-es--0-ZO,

E- 1.4 _To1-1—

... -q_ yr / . 5 cP•14-

c_115.-7-f A, (cid:9)

,74/iii 4-- (cid:9)

cj

4i/ 77

.) 07 (cid:9) 6-11 ir ' \v‘ (-1-

kekket L L

%laid (cid:9)

La eti-vt,"

1 OCI'l (cid:9)

7^

,..

--"x),( (cid:9) v (cid:9)

.

knol (cid:9) 701 St..,

_. -Si (cid:9)

r-rk_cz

'1113 (A (cid:9)

0 6-1

--\" (cid:9)

-aannvlA Oviv-t

70.2-e- (cid:9)

?CM, (cid:9) K--r '''y' (cid:9)

70/,,,,-1,.. ze,

1 " 4

703z.. CO ElFtet, gi)

--71/ a 24(,H~ 2,t)

...,Vi, IA e vv

---( 0 (- (cid:9)

'--7 (0 a (cid:9)

54ovitrAeK (cid:9) fi t

3 -/D5 Kunrick owe

)7 a/ (cid:9)

-lifol (cid:9) c-lA0.-mAN-0( (cid:9)

1 0 t \ (cid:9) LemVoi,\IQkf,jn

/<2.i,,' c4 (cid:9) At.,

-1>‘ (cid:9)

-

4a.....2-Ace.._,A,

70 54— (cid:9)

76 ›--s-

714 1:---4-e2t.....-J r)--

12‘co. (cid:9)

- \.t.e'rvv'ood 1)1'

12:2-I (cid:9) V\-Cew000l ,r

ONacv‘z(-\ 4-.1".

Cloy (cid:9) ci.5____ 1/A-1-6Eie (cid:9) *1)

Page 2 of 4

N\Q---k4 °L.- 1 C) (cid:9)

Page 196 of 275(cid:9)

(cid:9)

2026 Neighborhood Roadway Reconstruction

Informational Meeting – August 26, 2025

EdinaMN.gov

Page 197 of 275 Agenda

Introductions

• Why Reconstruct

• Project Scopes

• What You Can Expect

• Funding Sources

• Timeline

• Communication

• How to Prepare

• Questions

Page 198 of 275 Engineering - Design & Construction Division

Chad Millner

Director of Engineering

Aaron Ditzler

Assistant City Engineer

Chris Moore

Graduate Engineer

Brandon Freeman

Sr. Engineering Technician

Liz Moore

Engineering Coordinator

Ben Jore

Sr. Project Engineer

Tom Haataja

Sr. Engineering Technician

Jon Moore

Sr. Engineering Technician

Page 199 of 275 2026 Project Areas

• Parklawn

Court

4 Properties

• Prospect

Knolls A, C, &D

283 Properties

Page 200 of 275 Why My Street?

• Streets grouped into

neighborhoods

• Maximizes economics of scale

• Extends pavement life

• Proactive Pavement

Management Program

• Prioritized based on;

• Pavement condition

• Underground utility issues

Page 201 of 275 Why Reconstruct?

• Roadway originally constructed

with in the 1950’s-1980’s

• Utility issues to address beneath

roadway

• More cost-effective than other

maintenance strategies (mill &

overlay, seal coat)

Page 202 of 275 Existing Conditions - Roadways

• Pavement reaching end of

useful life

• Some streets have curb and

gutter while others do not

• Some properties already have

concrete driveway aprons,

some do not

Page 203 of 275 Existing Conditions - Utilities

Sanitary Sewer

- Cracks, breaks, sags, etc.

- Inflow and infiltration

• Watermain

- Loss in pipe wall

thickness

- Main and service

breaks

- Undersized mains

Storm Sewer

- Structure deficiencies

- Undersized pipes

- Curb and gutter failing

Page 204 of 275 What / Where is the ROW?

• Surface and space

above and below

public roadways used

for travel purposes

and utilities

• Typically, 60’ width

• (MSA Streets 66’)

• Property corners

located during survey

Page 205 of 275 Existing Conditions – Right-of-Way

• Landscaping

• Outwalks /

steps

• Mailboxes

• Irrigation

systems and

pet fences

Page 206 of 275 Proposed Improvements – Roadways

• Replacement

and installation

of curb &

gutter

• Subgrade

corrections as

needed

• New roadbed

and asphalt

pavement

surface

Page 207 of 275 Living Streets Plan

• Approved by City Council in 2015

• Balances needs of motorists, bicyclists, pedestrians and transit

riders

Incorporates;

• Minimum roadway design elements

• Street Width

• Impacts

• Cost

• Pedestrian and Bicycle Master Plan

Page 208 of 275 Proposed Improvements - Driveways

• Aprons will be replaced /

installed to comply with City

standards

• Special driveway materials

• Reimbursement Policy

Page 209 of 275 Proposed Improvements - Utilities

Includes partial replacement

of watermain

• New service replacements

• New fire hydrants and gate

valves

• May include localized

sanitary sewer repairs and

rehabilitation

• Lining of sanitary sewer

• Storm sewer upgrades

Page 210 of 275 Proposed Improvements – Sump Drain

Installed when feasible and warranted

• Homeowners encouraged to connect

to City Sump Drain

• Notification will be given when

connecting is available

• Sump connection permit available

thru City website

Page 211 of 275 Utility Ownership

City Owned Utilities

A – Water Service

E – Water Service Shutoff

Resident Owned Utilities

B – Water Service

C & D – Sanitary Service

Page 212 of 275 Utility Ownership

• Recommend inspecting

private services prior to

construction

• Repairs/upgrades can be

coordinated with street

work

• Associated costs can be

added to special

assessment

Resident Owned Utilities

B – Water Service

C & D – Sanitary Service

City Owned Utilities

A – Water Service

E – Water Service Shutoff

Page 213 of 275 Proposed Improvements – Ped / Bike

• Based on Pedestrian

and Bicyclist Master

Plan

• Final design

evaluated based on

network

consistency and

construction

conflicts

Page 214 of 275 Private Utilities

• Gas, Electric, Telephone, Cable may

upgrade or repair their utilities

before construction begins

• Fiber optic internet currently being

installed

• Potential City-required relocations

• Goal: streamline projects and

minimize neighborhood

disturbance

Page 215 of 275 Overhead Utility Poles

• Resident request about

burying overhead utilities

• Not required by the City, nor

does the City fund this

If pursued, full cost by

property owners

• Significant cost

• Private service connection

not included

Page 216 of 275 What You Can Expect

• Dust, mud, noise, and

vibrations

• Occasional delays due to

inclement weather

• Localized flooding during

rainfall

• Residents will be asked to

limit water use occasionally

• Homes may be connected to

temporary watermain

Page 217 of 275 What You Can Expect

• Construction materials

stored temporarily in

ROW

• 5-10 feet of disturbance

behind back of curb

• Construction equipment

stored on streets

• Tree removals as

necessary (property

owners notified)

Page 218 of 275 What You Can Expect

• Driveways and roads will be periodically inaccessible

• Driveways will be inaccessible for 7 days to allow driveways to cure

Page 219 of 275 What You Can Expect

Items within the City’s

right-of-way may be

damaged

• You can remove plants and

other landscape features

before the project

• Irrigation and pet fences

will be repaired

• Disturbed areas will be

restored with new sod

Page 220 of 275 What You Can Expect

• We will;

• Provide opportunities for

input

• Keep you informed

• Do our best to minimize

inconveniences

• Our contractor will

accommodate residents

with special access needs

Page 221 of 275 City Utility Funds

• Collection of utility service charges paid to the City

• Covers 100% of:

• Storm sewer

(curb and gutter,

driveway aprons,

sump drain pipe)

• Sanitary sewer

• Watermain

Page 222 of 275 Pedestrian and Cyclist Safety (PACS) Fund

• Revenue from Xcel and CenterPoint Energy franchise fees

• Promotes non-motorized

transportation throughout

the City

• Covers 100% of:

• Sidewalks /shared-use

paths

• Bike lanes

• Associated signage

and pavement markings

Page 223 of 275 Do Taxes Cover Street Projects?

• ~23% of property taxes go to the City

for expenses including Police, Fire,

Parks, and Public Works

• ~3.2% go to Public Works

• Snowplowing

• Pothole repairs

• Other street maintenance

(sealcoating, overlays, patch repairs)

In 2022 taxes began paying for a

portion of street reconstruction

Figures per proposed 2025 Edina

Tax Levy (not final)

Page 224 of 275 Special Assessments

• Assigned to benefitting

properties of public

improvements

• Covers portion of roadway

costs

• Roadway and driveway removals

• Asphalt pavement

• Driveway installation

• Restoration

• Indirect Costs – engineering,

finance, soil investigations, mailings

Page 225 of 275 Residential Equivalent Units

• Assessments distributed based on REUs

• Factor used to compare properties to a single-family residence

Scenario

Land Use Class

REU Factor

A

B

Single-Family Residential

Multi-Family Residential – Apartment/Condos

1.0

0.5

• Additional factors for commercial, industrial, and public-use properties

Page 226 of 275 Project Details – Parklawn Court

• 4 properties (41.50 REUs)

• 330’ of road

• Full removal and replacement of curb

& gutter

• Concrete roadway removed and

replaced with Bituminous

• Water services replacement

• Sanitary Lining and local replacement

• Storm sewer improvements

• Potential sidewalk(s)

• Street width still to be determined

Page 227 of 275 Project Details – Prospect Knolls A, C, & D

• 283 properties (231.67 REUs)

• 3.20 miles of road

Installation and replacement of curb &

gutter

• Partial watermain and full water services

replacement

• Sanitary lining and localized repairs

• Storm sewer improvements

• 24’ street width 5’ walk:

• Portions of Shannon Drive, Lanham Lane

• Kemrich Drive, Fleetwood Drive

• Typically 27’ street width remaining

streets

Page 228 of 275 Proposed Utility Improvements

Install 12” watermain from

West 70th Street to Gleason

Road

• Existing Utility Easement

• Replace 6” watermain on

Dublin Circle

• Replace 6” watermain on

Lanham Lane

• Upgrade 1.5” watermain in

cul-de-sacs to 6” watermain

Install 8” sanitary sewer on

70th Street

Page 229 of 275 Pedestrian Facilities Plan

• 5’ concrete sidewalk

• Shannon Drive

• Kemrich Drive

• Fleetwood Drive

• Lanham Lane

• Connection to existing Lewis

Park path

• Sidewalk to be maintained by

adjacent property owners

Page 230 of 275 Proposed Roadway Widths – Sidewalk Streets

Existing: 30’ road width, two-sided parking

Proposed: 24’ road width, one-sided parking,

5’ sidewalk (0-5’ grass boulevard)

Page 231 of 275 Proposed Roadway Widths – No Sidewalk Streets

• 27’ road width

• Reduce street widths by 0-

3’

• Two-sided parking to

remain

• Exceptions

• Kerry Road

• 24’ width

• One-sided parking

• Village Drive

• 30’ width

Existing: 26’-30’ road width, two-sided parking

Proposed: 27’ road width, two-sided parking

Page 232 of 275 Revised Roadway Cost Assessment - Local

Sample Assessment During

Transition

Construction

Year

% of Local Roadway

Costs Assessed

$10,000

$20,000

$30,000

2020

2021-2025

2026

2027-2035

2036

100%

78.90%-57.86%

52.60%

$10,000

$7,890-

$5,786

$5,260

$20,000

$15,780-

$11,572

$10,520

$30,000

$23,670-

$17,358

$15,780

47.34%-5.26%

$4,734-$526

$9,468-$1,052

$14,202-$1,578

0%

$0

$0

$0

Page 233 of 275 Market Benefit Estimate

Special assessments are valid if;

• The assessment does not

exceed the special benefit

measured by the increase in

market value due to the

improvement.

• Licensed and Qualified Appraisal

Firm

Page 234 of 275 Assessments Districts – Prospect Knolls

• Disparity

in potential

benefit

• 3 Separate

Districts

Page 235 of 275 Preliminary Assessments – Prospect Knolls &

Parklawn Ct

*Residential equivalent unit (1 single-family home = 1 REU)

Year

Neighborhood

2026

2026

2026

2026

2026

2025

2024

Prospect Knolls

A/C/D

District 1

District 2

District 3

Parklawn Court

Presidents A/B

Concord B/C

% of

Roadway

Costs

Assessed

Estimated

Assessment Range

per REU*

# of

REUs

Square

Yards of

Paving

SY of

Paving per

REU

-

-

-

-

-

-

52.60%

52.60%

52.60%

57.86%

57.86%

63.12%

$16,200

$8,200

$2,900

$1,800

$7,500

$11,900

-

-

-

-

-

-

$21,500

$10,900

$3,800

$2,400

$11,500

$17,100

58.67

153

20

41.5

291.6

174.49

19,250

24,692

1,321

1,221

35,250

30,568

-

328.1

161.4

66.0

29.4

120.9

175.2

Page 236 of 275 Typical Project Timeline

Date

Milestone

July – September 2025

Engineering studies/estimates provided

December 2025

Public hearings

January – March 2026

Plan preparation and bidding

April – May 2026

Construction begins

October – November 2026

Construction concludes

2027

Fall 2027

Warranty work

Final assessment hearing

Page 237 of 275 Assessment Timing

Date

Milestone

December 2025

Summer 2026

October 2027

November 2027

January 2028

Initial Public Hearings

Project Constructed

Final Assessment Hearing

Assessment Filed with County

Assessment on Tax Statement

Page 238 of 275 Payment Options

• Pay entire amount upon receiving bill to avoid interest charges

• Pay min. 25% ; balance rolls to property taxes over 15 years

• Roll entire amount to property taxes over 15 years

• 2024 interest rate was 4.69%

• Finance charges are 1% over City’s borrowing interest rate

• Defer payment if 65 years of age or older and meet specific income

requirements

• Assessing Department – 952-826-0365

Page 239 of 275 Communication

• Regular Mail

• All meetings, public hearings, and questionnaires

Final assessment notices (one year after construction)

• Door hangers and flyers

• Time-sensitive information (water shut-offs, concrete, temporary

inaccessibility)

• Better Together Edina – City Website Project Page

Page 240 of 275 Better Together Edina

• Best way to stay

informed

• www.bettertogether

edina.org

• Free, access to

periodic updates on

project progress and

schedules

Page 241 of 275 Providing Input

• Questionnaires mailed to your home, weigh in on;

• Traffic/pedestrian issues

• Street drainage issues

• Streetlight upgrades

• Public hearing in December 2025

• Opportunity for residents to voice comments and concerns

Page 242 of 275 Questionnaire Results

Neighborhood

Responses Received

to Date

Prospect Knolls

26% (74 / 283)

Parklawn Court

25% (1 / 4)

Page 243 of 275 How To Prepare

• Complete project

questionnaire

• Begin financial planning

• Coordinate home and yard

improvement projects around

street reconstruction

schedule

• Review Better Together Edina

updates

• Ask questions, stay informed

Page 244 of 275 Contact Us

Engineering Department

7450 Metro Boulevard

Hours: 7:00 a.m. – 3:30 p.m.

952-826-0371

Aaron Ditzler

Assistant City Engineer

952-826-0443

ADitzler@edinamn.gov

Liz Moore

Engineering Coordinator

952-826-0449

LMoore@edinamn.gov

Page 245 of 275 Questions?

• Ask questions on Better Together Edina Q&A page

• https://www.bettertogetheredina.org/prospect-knolls

• https://www.bettertogetheredina.org/parklawn-court

• Call or email

Page 246 of 275 Thank you for your time!

Page 247 of 275 APPENDIX J

Resident Questionnaires

Page 248 of 275

Survey Responses

30 January 2019 - 24 August 2025

Neighborhood Reconstruction Survey

Better Together Edina

Project: Parklawn Court Neighborhood Roadway Reconstruction

VISITORS

10

CONTRIBUTORS

RESPONSES

1

0

1

0

1

1

0

0

Registered

Unverified

Anonymous

Registered

Unverified

Anonymous

Page 249 of 275

Respondent No: 1

Login: Registered

Responded At:

Jul 25, 2025 03:32:19 am

Last Seen:

Jul 25, 2025 10:24:55 am

Q1. Does your property have drainage issues the

No

City should know about?Examples: History of

flooding/standing water, grading, backyard

drain, nuisance sump pump, etc.

Q2. Please comment on the location and types of problems you have.

not answered

Q3. How concerned are you with the speed of traffic

Not Concerned

in your neighborhood or on your street?

Q4.

If concerned or very concerned, please enter the location(s) of concern and why you feel that way.

not answered

Q5. How concerned are you with the volume of

Not Concerned

traffic or number of vehicles in your

neighborhood or on your street?

Q6.

If concerned or very concerned, please enter the location(s) of concern and why you feel that way.

not answered

Q7. How concerned are you with motorist behavior

Not Concerned

in your neighborhood? (Excludes speed and

traffic volumes. Examples of poor motorist

behavior include rolling through stop signs,

failing to yield and driving aggressively)

Q8.

If concerned or very concerned, please enter the location(s) of concern and why you feel that way.

not answered

Q9.

In general, these behaviors impact you most

not answered

when you are:

Q10. Do you feel any intersection in your

No

neighborhood is unsafe?

Q11. Which intersection do you feel is unsafe?

not answered

Q12. Which, if any, of the following factors contribute

not answered

to your feeling that the intersection is unsafe?

(select all that apply)

Q13. In general, the intersection feels most unsafe

not answered

when you are:

Page 250 of 275 Q14. How frequently do you walk, jog, or run in your

Never

neighborhood?

Q15. If you walk, jog, or run in your neighborhood,

not answered

what are your primary reasons for doing so?

(select all that apply)

Q16. If you don't walk, jog, or run in your neighborhood as often as you would like, what reconstruction improvement

might increase your walking, jogging, or running? Please list all that you can think of.

This is already a very safe area, and if I had any desire to get out of my apartment I would feel comfortable doing so

Q17. How frequently do you ride a bicycle in your

Never

neighborhood?

Q18. If you ride a bicycle in your neighborhood, what

not answered

are your primary reasons for doing so? (select

all that apply)

Q19. If you don't ride a bicycle in your neighborhood as often as you would like, what reconstruction improvement might

increase your bicycle riding frequency? Please list all that you can think of.

not answered

Q20. How frequently do you or a member of your

Never

household park on the street?

Q21. How frequently do visitors to your household

Rarely (less than once per month)

park on the street?

Q22. How satisfied are you with the availability of on-

Satisfied

street parking in your neighborhood?

Q23. Any additional comments about parking?

not answered

Q24. Please tell us anything else you would like us to know about existing traffic or street conditions in your

neighborhood.

There are no issues with the Parklawn CT area

Q25. Do you support the installation of a sidewalk

Neither side

on:

Q26. Please describe any specific concerns or support you have regarding sidewalks on your street.

not answered

Q27. How many vehicles are typically parked on

3 vehicles

Parklawn Ct (daily)?

Q28. How often do you or your household rely on on-

Never

street parking?

Page 251 of 275 Q29. Do you have off-street parking available (e.g.,

Yes

parking lot, garage)?

Q30. If on-street parking were reduced or restricted

Significant impact

due to new sidewalk installation, how would that

impact you?

Q31. Please elaborate if you have specific concerns regarding parking.

The street parking currently allows just enough room to move through safely. Installing even just 1 sidewalk would make the

street too narrow.

Q32. What is your address?

4435 Parklawn CT, Edina, MN 55435

Page 252 of 275 APPENDIX K

Correspondence from Residents

Page 253 of 275

APPENDIX L

Proposed Typical Sections

Page 254 of 275

APPENDIX M

Preliminary Assessment Roll

Page 255 of 275

Date: October 23, 2025

Meeting: Transportation Commission

Agenda Number: 6.3

Item Type: Report and Recommendation

BOARD & COMMISSION

ITEM REPORT

Item Activity: Discussion

Prepared By: Andrew Scipioni, Transportation Planner

Department: Engineering

Item Title:

South Truck Sanitary Sewer Project

Action Requested:

Review and comment on the proposed roadway improvements.

Information/Background:

See attached supporting materials.

Supporting Documentation:

Draft Layout - W 72nd St

1.

South Trunk Sanitary Sewer Improvements Map

2.

Page 256 of 275

W 72nd Street

City of Edina

R

D

A

I

L

E

N

R

O

C

M

A

5

2

:

2

5

:

9

5

2

0

2

/

5

1

/

0

1

I

.

g

w

d

2

N

A

D

E

M

_

R

E

T

N

E

C

_

2

N

_

E

S

A

B

C

_

3

0

2

6

3

1

\

D

3

C

\

D

A

C

\

0

0

0

3

0

2

6

3

1

X

4

2

\

N

M

_

I

C

_

A

N

D

E

\

:

H

I

October 2025

R

E

V

A

R

E

T

S

E

H

C

U

O

L

G

0

HORZ.

15

30

SCALE

FEET

R

'

6

1

4

.

'

5

'

2

1

'

2

1

'

4

'

8

L

I

A

R

T

N

O

T

R

E

H

T

A

E

H

'

6

1

4

.

'

5

'

2

1

'

2

1

'

4

'

8

0

HORZ.

15

30

SCALE

FEET

R

'

6

1

4

.

'

5

'

2

1

'

2

1

'

4

'

8

INSTALL APPROXIMATELY 80 LF RETAINING WALL

DRIVEWAY REPLACEMENT

LIMITS EXTEND BEYOND ROW

Page 257 of 275

W 72nd Street

City of Edina

D

V

L

B

L

O

T

S

I

R

B

M

A

7

2

:

2

5

:

9

5

2

0

2

/

5

1

/

0

1

I

.

g

w

d

2

N

A

D

E

M

_

R

E

T

N

E

C

_

2

N

_

E

S

A

B

C

_

3

0

2

6

3

1

\

D

3

C

\

D

A

C

\

0

0

0

3

0

2

6

3

1

X

4

2

\

N

M

_

I

C

_

A

N

D

E

\

:

H

I

October 2025

R

N

L

R

A

M

Y

L

0

HORZ.

15

30

SCALE

FEET

R

0

HORZ.

15

30

SCALE

FEET

R

S

E

V

A

E

C

N

A

R

F

'

6

1

4

.

'

5

'

2

1

'

2

1

'

4

'

8

REMOVE EXISTING BOULDER WALL AND FENCE.

INSTALL APPROXIMATELY 95 LF RETAINING WALL

DRIVEWAY REPLACEMENT

LIMITS EXTEND BEYOND ROW

'

5

'

4

1

'

8

'

4

1

'

8

'

5

'

2

1

'

2

1

'

4

'

8

COORDINATE ACCESS WITH DEVELOPER

Page 258 of 275

South Trunk Sanitary Sewer Improvements

Arneson Acres

Arneson Acres

Park

Park

Andover Road

Andover Road

Belvidere Lane

Belvidere Lane

W 70th Street

W 70th Street

Cornelia

Cornelia

Elementary

Elementary

School

School

Cornelia School

Cornelia School

Park

Park

e

e

u

u

n

n

e

e

v

v

A

A

g

g

g

g

o

o

l

l

l

l

e

e

K

K

Lift station 6

Claremore Drive

Claremore Drive

e

e

v

v

i

i

r

r

D

D

a

a

i

i

l

l

e

e

n

n

r

r

o

o

C

C

17

S

S

e

e

u

u

n

n

e

e

v

v

A

A

e

e

c

c

n

n

a

a

r

r

F

F

Mavelle Drive

Mavelle Drive

W 72nd Street

W 72nd Street

ue

ue

dale Aven

dale Aven

Woo

Woo

d

d

Dunham Drive

Dunham Drive

e

e

n

n

a

a

L

L

o

o

d

d

r

r

a

a

n

n

o

o

M

M

e

e

v

v

i

i

r

r

D

D

e

e

r

r

o

o

h

h

S

S

W

W

Ellsworth Drive

Ellsworth Drive

Fondell Drive

Fondell Drive

e

e

u

u

n

n

e

e

v

v

A

A

n

n

w

w

a

a

l

l

k

k

a

a

O

O

e

e

u

u

n

n

e

e

v

v

A

A

r

r

e

e

t

t

s

s

e

e

h

h

c

c

u

u

o

o

l

l

G

G

e

e

v

v

i

i

r

r

D

D

a

a

i

i

l

l

e

e

n

n

r

r

o

o

C

C

Gilford Drive

Gilford Drive

e

e

v

v

A

A

g

g

g

g

o

o

l

l

l

l

e

e

K

K

Hibiscus Avenue

Hibiscus Avenue

Sedum Lane

Sedum Lane

Fred Richards

Fred Richards

Park

Park

Parklawn Avenue

Parklawn Avenue

17

Key Considerations

• Right-of-way encroachments (walls, fences)

• Overhead utility lines / poles

• Maintaining access

• Mature trees

• Groundwater

• Constructability of deep sewer main

Lateral connections to deep sewer main

100

M

M

e

e

t

t

r

r

o

o

B

B

o

o

u

u

l

l

e

e

v

v

a

a

r

r

d

d

Larkspur Lane

Larkspur Lane

Aspasia Lane

Aspasia Lane

Trillium Lane

Trillium Lane

Hibiscus Avenue

Hibiscus Avenue

Lake Edina

Lake Edina

Project Area - Segment 1: 2030 Construction*

Project Area - Segment 2: 2028 Construction*

Project Area - Segment 3: 2026 Construction*

Bike Path

Neighborhood Boundaries

100

Poppy Lane

Poppy Lane

W Shore Drive

W Shore Drive

Walking Path

* Anticipated construction year

CORNELIA SOUTHPARKLAWNLAKE EDINACORNELIA SOUTHPARKLAWNLAKE EDINAPage 259 of 275

Date: October 23, 2025

Meeting: Transportation Commission

Agenda Number: 6.4

Item Type: Report and Recommendation

BOARD & COMMISSION

ITEM REPORT

Item Activity: Discussion

Prepared By: Andrew Scipioni, Transportation Planner

Department: Engineering

Item Title:

Traffic Safety Report of October 1, 2025

Action Requested:

Review and comment on the staff report.

Information/Background:

The Traffic Safety Committee recommends action on two items, no action on four items and further

study on one item. See attached staff report.

Supporting Documentation:

1.

Traffic Safety Report of October 1, 2025

Page 260 of 275

Date: October 23, 2025

To:

Transportation Commission

From:

Nick Bauler, Traffic Safety Coordinator

Subject: Traffic Safety Report of October 1, 2025

Action Requested: Review and comment on staff recommendations.

Information / Background:

The Traffic Safety Committee (TSC) review of traffic safety matters occurred on October 1. The Traffic

Safety Coordinator, Transportation Planner, Engineering Director, Assistant City Planner and Traffic

Safety Specialist were in attendance for this meeting.

On each of the items, persons involved have been contacted and the staff recommendation has been

discussed with them. They were informed that if they disagree with the recommendation or have

additional facts to present, they can submit correspondence to the Transportation Commission and/or

to City Council prior to the October 22 meeting.

Section A: Items on which the Traffic Safety Committee recommends action

A1. Request for pedestrian safety improvements along Ridgeview Dr

Description

AADT

85% Speed

Crashes

Street Width

Bike/Ped Facilities

Previous Work

Future Work

Requester and children feel unsafe when on sidewalk

with vehicle volumes and speeds on Ridgeview.

5,197 (2024)

N/A

One at Ridgeview and Valley Ln. 2016 Heavy snow

conditions.

35’ – one-sided parking on west side.

Northbound driving lane is 14’

Southbound driving (& parking) lane is 21’

Sidewalk on west side of Ridgeview

Last overlay in 2004

Last seal coat in 2008

No plans in 5-year CIP

Staff recommends adding a striped parking lane on Ridgeview Dr between the railroad

tracks and W 66th St. This work will be performed in Spring 2026.

Ridgeview Dr

City of Edina • 4801 W. 50th St. • Edina, MN 55424

Page 261 of 275

A2. Request for speed limit signs on W 74th St

Description

ADT

85% Speed

Crashes

Previous Work

Unique

Circumstances

Bike/Ped

Facilities

Edina Police Sergeant noticed increased speeds

on W 74th and requested a speed limit sign.

4,240 (2025)

2,985 (2021)

32.8 mph (2025)

32.7 mph (2021)

One rear-end of a parked truck in front of Edina

Public Works

W 74th lowered to 25 mph speed limit (from 30

mph) in 2022.

W 74th has one of highest volumes in Edina not

classified as Municipal State-Aid Street

Sidewalk on south side of W 74th

Staff recommends adding a gateway speed limit sign on Bush Lake Rd north of W 78th St.

W 74th St

Section B: Items on which the Traffic Safety Committee recommends no action

B1: Request to lower speed limit on Interlachen Blvd to 25 mph

Description

AADT

85% Speed

Crashes

Previous Work

Unique

Circumstances

Bike/Ped

Facilities

Requester states pedestrians and cyclists would

benefit from a lower speed limit.

7,260 (2024)

38.3 mph (2015)

17 (four rear-ends, seven angle. Only one during

winter months)

Interlachen was overlaid in 2019.

Two permanent dynamic speed display signs

west of Oxford Ave.

Sidewalk on south side from Mirror Lakes to

Vernon Ave.

Standard bike lanes present.

A proposed shared use path is planned between

Blake Rd and Mirror Lakes Dr.

Interlachen Blvd

Staff recommends no action. Staff is considering a future reconstruction of Interlachen

Blvd between Blake Rd and Mirror Lakes Dr that would improve pedestrian and bicycle

facilities and may provide opportunities for traffic calming treatments.

City of Edina • 4801 W. 50th St. • Edina, MN 55424

Page 262 of 275

B2: Request for speed limit signs on Long Brake Trl

Description

ADT

85% Speed

Crashes

Previous Work

Bike/Ped

Facilities

Resident complained of vehicles passing them on

the left when turning onto street.

N/A

N/A

None reported in past 10 years.

This Dewey Hill neighborhood was overlaid in 2015

None between Delaney and Gleason Rd.

Staff recommends no action.

B3: Sight line complaints at W 44th St and North Ave

Long Brake Trl

Description

Resident is requesting a tree be cut down to

improve sight lines looking west over Minnehaha

Creek at W 44th St and North Ave.

3,655 – W 44th St (2024)

None reported in past 10 years.

Bridge guard rail also impacts sight lines.

AADT

Crashes

Unique

Circumstances

Previous Work W 44th reconstructed in 2011

Future Work W 44th Overlay planned for 2028

North Ave was overlaid in 2020

Staff recommends no action.

B4: Sight line complaints at 7401 Bush Lake Rd

W 44th St looking west from North Ave over Minnehaha

Creek

Description

AADT

Crashes

Unique

Circumstances

Previous Work

Discussion

Guests exiting driveway of 7401 Bush Lake have little

visibility when parking is used adjacent to property.

5,134 (2023)

Crash reported of vehicle exiting driveway in April 2022.

Parking restrictions removed in 2019 to accommodate

businesses.

Bush Lake was overlaid in 2018

Any other options to improve sight lines besides adding

parking signage?

Staff recommends no action. The property owner may

consider signing the northern driveway as “exit only" and

the southern driveway as “enter only” to minimize sight

line impacts.

7401 Bush Lake Rd

City of Edina • 4801 W. 50th St. • Edina, MN 55424

Page 263 of 275

Section C: Items on which the Traffic Safety Committee recommends further study

C1. Request to remove No Outlet signs in Country Club neighborhood

Description

ADT

Crashes

Street Width

Unique

Circumstances

Recommendation

Resident noticed two No Outlet signs –

Sunnyside Rd & Browndale Ave and at W

44th St and Mackey Ave, where outlets are

available.

N/A – 36 homes are within impacted

neighborhood.

One rear-end crash in 2017 due to icy

roads.

17’ face to face of curb

Parking is restricted only on the south side

of Sunnyside.

Remove No Outlet signs and install parking

restrictions on north side of Sunnyside for

EMS access.

No Outlet signs in Country Club neighborhood

Staff recommends researching alternative signage for this area and engaging the adjacent

property owners about possible parking restrictions.

Section D: Other traffic safety items

D1. Two requests for stop controls at 3-way intersections; Chowen Ave and Chowen Curve along with

Paiute Pass and Sally Ln. These intersections are uncontrolled with adequate visibility for stopping

distances, low volumes and no crash history. Stop controls do not meet warrants.

D2. A homeowner on Lake Ridge Rd and Blake Rd is requesting a guardrail to be installed adjacent to

their property as it’s along a curve. The homeowner reported a vehicle ran off road this past into their

property. This portion of Blake was reconstructed in 2023 and a guardrail did not meet state design

requirements, no action recommended by staff.

D3. A resident on the 5600 block of Bernard Pl requested staff remove a road closed sign following no

work taking place for weeks. The private contractor managing the project was notified and the sign was

removed.

D4. A reported crash involving a 12 year-old at W 58th and Xerxes. Residents request the 2-way stop

be switched to an all-way stop. Hennepin County reviewed this intersection and is recommending no

changes due to crash history and vehicle volumes.

D5. A complaint of visibility at the southwest corner of York Ave and W 66th St. Staff contacted the

maintenance group in charge of this area and the issue was resolved.

City of Edina • 4801 W. 50th St. • Edina, MN 55424

Page 264 of 275

D6. Many complaints received during new closures around the Vernon Ave bridge project. Staff from

many departments are requesting commuters use extra caution and be patient until the completion of

the project.

D7. A submission was received for a dead animal along the 5300 block of Halifax Ave. Proper staff was

notified of the submission.

D8. A request for a permanent speed display sign for traffic on Dewey Hill Rd. Staff will review Dewey

Hill once a policy for a speed display sign is adopted.

D9. A resident who lives adjacent to Woodland Rd West and Concord Ave S requested all-way stop

controls at the intersection. Stop controls are only warranted for westbound vehicles and no other

warrants along Concord Ave are met. The proximity to Concord and Southview Ln could cause

additional congestion and lack of stopping properly.

D10. A complaint was made of a traffic signal not operating properly at W 77th St and Normandale Rd,

east of HWY 100. MnDOT fixed the issue.

D11. A complaint of a pedestrian cross button not working at W 65th St and France Ave. Hennepin

County staff was notified and fixed the issue.

D12. A resident was hit in a crosswalk in the southwest corner of W 51st St at France Ave and is

requesting crossing safety improvements. Hennepin County is working with City staff with an upcoming

project along France Ave. Safety improvements are planned.

D13. A request for temporary all-way stop controls at W 44th St and Brookside Ave during the final

closure of ramps during the Vernon Ave bridge closure. Staff is monitoring possible detours to see if

changes are needed. The intersection will remain one-way stop controlled for the time being.

D14. A request for a traffic mirror at a residential driveway along Valley View Rd, west of Gleason.

Edina does not utilize mirrors for sight lines. The resident was encouraged to trim vegetation to

improve visibility.

D15. A bicyclist requested improved bike lanes on Wooddale Ave between Valley View Rd and W 50th

St. Staff will consider improvements with an anticipated 2026 overlay project.

D16. Many complaints received regarding tenants at the new Eddi residence parking on Computer Ave.

Property management was notified of City parking policies and parking restrictions were reinstalled on

the west side of Computer following the development project.

City of Edina • 4801 W. 50th St. • Edina, MN 55424

Page 265 of 275

Section E: Items recommended for police enforcement

E1. A complaint was made of drivers speeding and not stopping for pedestrians on Market St and

requested enforcement. The EPD was notified of the request.

E2. A complaint of vehicles parking illegally on W 72nd St, west of France Ave. Edina Police was notified

and added the area to their patrol list for enforcement.

E3. A resident complained of minor children not wearing proper helmet and following safety measures

on an all-terrain vehicle along Madison Ave. The EPD was notified of the instance.

E4. Complaints of vehicles consistently exceeding the speed limit on W 70th St and W 78th St. EPD was

notified for enforcement.

City of Edina • 4801 W. 50th St. • Edina, MN 55424

Page 266 of 275

BOARD & COMMISSION

ITEM REPORT

Item Activity: Information

Prepared By: Andrew Scipioni, Transportation Planner

Department: Engineering

Date: October 23, 2025

Meeting: Transportation Commission

Agenda Number: 6.5

Item Type: Other

Item Title:

SEMAP Update

Action Requested:

None.

Information/Background:

Staff will provide an update on the development of the City's Safe and Equitable Mobility Action Plan.

Supporting Documentation:

None

Page 267 of 275

Date: October 23, 2025

Meeting: Transportation Commission

Agenda Number: 6.6

Item Type: Report and Recommendation

BOARD & COMMISSION

ITEM REPORT

Item Activity: Discussion

Prepared By: Andrew Scipioni, Transportation Planner

Department: Engineering

Item Title:

Initiative #5: City Code Sec. 26-282

Action Requested:

Review and comment on draft report.

Information/Background:

As part of the 2025 Work Plan, the Commission reviewed Edina City Code Section 26 Chapter X.

Bicycles and developed recommendations. See attached draft report.

Supporting Documentation:

1.

Report: Recommendation to Amend City Code Sec. 26-282

Page 268 of 275

City of Edina – Transportation Commission

To: Edina City Council

From: Edina Transportation Commission

Date: October 6, 2025

Subject: Recommendation to Amend Edina City Code Sec. 26-282 to Support Safe, Responsible

E-Bike Use

Work Plan Reference: ETC 2025 Work Plan Item 5

Executive Summary

The Edina Transportation Commission (ETC) recommends revising Edina City Code Sec. 26-282 to

remove the prohibition against operating electric-assisted bicycles (e-bikes) on sidewalks. The current

restriction unintentionally creates safety risks by forcing riders onto streets without protected facilities

and is inconsistent with the approach taken by neighboring cities. The ETC further recommends

reinforcing and publicizing existing safety standards for sidewalk riding already codified in Sec. 26-283,

ensuring that pedestrians maintain the right-of-way and that riders operate responsibly and at low

speed.

Background

At its May 6, 2025 meeting, City Council approved by consent an amendment to Edina City Code Sec.

26-282 adding the following sentence: 'No person may operate an electric-assisted bicycle, as defined

in this Chapter, on a sidewalk.' This language applies broadly to all classes of e-bikes and all locations

within the city, regardless of rider behavior, surrounding land use, or the availability of safe bike

infrastructure.

Situation Summary

The ETC believes this prohibition unintentionally increases safety risks for both cyclists and drivers by

forcing riders—particularly youth, seniors, and less experienced e-bike users—onto busy streets that

lack protected or connected bike lanes.

Edina’s current biking network is incomplete and lacks continuous protected routes connecting key

destinations. Until substantial improvements are made, sidewalks remain the only safe refuge for slower

or cautious riders in many parts of the city. Restricting sidewalk access also discourages e-bike adoption

—a key strategy supporting Edina’s Climate Action Plan and Vision Edina goals for sustainable, low-

carbon mobility. Neighboring communities including Bloomington, Eden Prairie, and Minneapolis permit e-

bikes on sidewalks with safety limitations, offering regional consistency for riders who travel across

municipal boundaries.

It is also important to note that concerns about pedestrian safety from bikes or e-bikes on sidewalks are

not supported by data. According to state records, the last known fatal incident involving a pedestrian

struck by a bicyclist in Minnesota occurred in 1972—more than 50 years ago. In contrast, 41 people

have been killed by cars while biking in Minnesota in the most recent five-year period where data is

readily available (2018–2022). This data underscores that the far greater public safety risk comes from

vehicle interactions, not from bicycles or e-bikes sharing space with pedestrians at low speeds.

Recommendations

1 Amend Edina City Code Sec. 26-282 to delete the sentence: 'No person may operate an

electric-assisted bicycle, as defined in this Chapter, on a sidewalk.'

2 Reaffirm and promote the safety provisions already contained in Sec. 26-283 governing bicycle

Page 269 of 275 operation on sidewalks, emphasizing pedestrian right-of-way, reasonable speed (not exceeding 10

mph), slowing to walking pace near pedestrians, driveways, and intersections, and avoiding

sidewalks adjacent to building entrances or where posted restrictions apply.

Electric-assisted bike riders can be held by law enforcement to the same safety standards as

conventional bike riders, including the caveat that pedestrians on sidewalks have the right of way.

3 Direct staff to update public materials (website, signage, and education programs) to clearly

communicate these safety requirements and expectations for responsible e-bike use.

4 Consider implementing a one-year pilot period allowing e-bike use on sidewalks citywide, with a

follow-up safety and compliance evaluation presented to City Council in 2026.

Conclusion

Allowing responsible e-bike use on sidewalks—within clear, enforceable safety limits—will enhance

safety for both cyclists and motorists, support Edina’s climate and mobility goals, and align Edina’s

policies with those of neighboring communities for a consistent regional approach. The ETC

respectfully requests City Council’s consideration and approval of this recommendation.

Thank you

Page 270 of 275 Date: October 23, 2025

Meeting: Transportation Commission

Agenda Number: 6.7

Item Type: Other

BOARD & COMMISSION

ITEM REPORT

Item Activity: Information

Prepared By: Andrew Scipioni, Transportation Planner

Department: Engineering

Item Title:

2025 Work Plan Updates

Action Requested:

None.

Information/Background:

Commissioners will provide updates on the status of current work plan initiatives (unless an item is

elsewhere on the current agenda). See attached work plan progress report.

Supporting Documentation:

1.

2025 Work Plan Progress Report

Page 271 of 275

Page 272 of 275 Page 273 of 275 Date: October 23, 2025

Meeting: Transportation Commission

Agenda Number: 6.8

Item Type: Other

BOARD & COMMISSION

ITEM REPORT

Item Activity: Information

Prepared By: Andrew Scipioni, Transportation Planner

Department: Engineering

Item Title:

2026/2027 Work Plan Update

Action Requested:

None.

Information/Background:

Staff will provide an update on the 2026/2027 work plan development process.

Supporting Documentation:

None

Page 274 of 275

Date: October 23, 2025

Meeting: Transportation Commission

Agenda Number: 7.1

Item Type: Other

BOARD & COMMISSION

ITEM REPORT

Item Activity: Information

Prepared By: Andrew Scipioni, Transportation Planner

Department: Engineering

Item Title:

Transportation Projects Update

Action Requested:

None.

Information/Background:

Staff will provide a brief update on current and upcoming transportation projects in and around Edina.

Supporting Documentation:

None

Page 275 of 275

Was this story helpful?

Other Topics from This Document

  • 2025 Work Plan Updates

  • 2026/2027 Work Plan Proposal

  • Transportation Projects Update (Staff Comments)

  • Prospect Knolls A/C/D Roadway Reconstruction Project (Future Discussion Item for Oct 23, 2025)