StoryConstruction delays due to utility conflicts affecting major infrastructure projectAugust 7, 2025

Highway 100 Interchange Project Faces Three-Month Delay

Meeting date: Aug 7, 2025
Published Aug 23, 2025

The Vernon Avenue Highway 100 interchange project continues to face significant delays due to unresolved utility conflicts, project officials said during a bi-weekly update meeting Thursday.

Excel Energy power line issues have stalled construction for three months, with no resolution in sight between the utility company and CP Rail, according to project representatives. The power line was found to be in a different location than shown on project plans and was struck during construction. Both parties are working on permits and agreements, but no construction progress has been made in the affected area.

"I'm having major concerns, major impacts to schedule and cost are coming and we don't even know what that is yet," a project representative said during the meeting. The delays could affect the entire $20 million project timeline and budget.

Meanwhile, other aspects of the project are progressing. Bridge girders for the Highway 100 overpass are scheduled for installation in early September, with overnight operations planned over four nights. The northbound on-ramp from 50th Street closed July 28 and will remain closed through fall to allow construction of ramp realignments and noise walls.

Traffic impacts are expected to worsen in September with additional ramp closures planned, including westbound off-ramps and the northbound exit to Grandview. The closures coincide with the start of the school year August 25, which will add to congestion on detour routes including Benton Avenue.

Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.

Go deeper on this topic

Research related meeting documents and build a brief — without rewriting the story.

Full analysis
  • Significant schedule and budget uncertainty due to unresolved utility conflicts with Excel Energy and CPKC Rail.
  • Concerns over the $20 million project budget following a $2,000 expedited decision fee that failed to resolve utility delays.
  • Local business access and residential traffic frustration peak as school returns and further ramp closures are scheduled for September.
  • Transparency issues regarding who bears financial responsibility for project cost overruns between City, County, and private entities.

I'm having major concerns, major impacts to schedule and cost are coming and we don't even know what that is yet.

Speaker
Utility ConflictRegarding the utility line conflict delay.

I have a lot of commentary, but I don't think it's appropriate for this meeting on the lack of urgency by both parties.

Speaker
Utility ConflictCommenting on Excel and the Rail company's lack of action.

It is going to get worse before it gets better from a traffic standpoint within this area.

Speaker
Traffic ManagementWarning residents about upcoming ramp closures and school traffic.

That was a $2,000 fee if you want to know. We felt like that was justified for a $20 million project.

Speaker
Project BudgetExplaining the expedited decision fee paid to CPKC.
Source document

[0:00] Okay, we'll get started. But we're here

[0:02] for the Vernon Avenue Highway 100

[0:03] interchange project. This is update

[0:05] meeting number 10, August 7th, 2025.

[0:10] Again, thanks for the patience. Uh

[0:12] businesses, again, a reminder, they're

[0:14] open and accessible. There's routes to

[0:16] get to them. We have all the

[0:18] construction related stuff, noise, dust,

[0:19] vibrations.

[0:21] Uh please stop for those pedestrians in

[0:23] the crosswalks. Be courteous to fellow

[0:25] drivers in the roundabouts. Truck is

[0:28] heavy. Uh so please take your time and

[0:31] again if you're not comfortable using

[0:33] that midblock crossing Eden we would

[0:35] recommend using the crosswalk at Vernon

[0:37] in Eden instead of the fully signaled uh

[0:42] intersection there of the crosswalk.

[0:46] Yeah, we always share the project goals.

[0:49] Uh we're here to improve safety and

[0:50] mobility of all users, improve traffic

[0:53] operations, create those pedestrian

[0:55] separated pedestrian routes, and improve

[0:58] connectivity in the area. Uh we'll talk

[1:00] a little bit about schedule here uh as

[1:03] we go through the presentation today.

[1:06] And this is the project starts west of

[1:08] Interlockan Boulevard. We have the

[1:10] Vernon Avenue bridge over CP Rail,

[1:13] Casey, CP Casey Rail, and then we have

[1:16] the bridge over Highway 100. This is the

[1:18] project and the interchange at 100 is

[1:21] called a tight diamond interchange.

[1:25] Lots of ways to communicate. We have

[1:27] this bi-weekly meeting every other week

[1:31] 11 a.m. Thursdays. We have a better

[1:33] together website betterto

[1:35] togetherdina.org/veron-hwy00.

[1:42] We also been doing press releases,

[1:43] Friday reports, email updates. Uh people

[1:46] were signing up for those when the

[1:47] project started. Direct mailers, lots

[1:50] and lots of different ways to

[1:51] communicate with both people in the

[1:54] area, traveling in the area, businesses,

[1:56] and a lot of information posted to the

[1:58] website. So if you're looking for more

[1:59] info, check out the website. If you

[2:02] haven't signed up for emails, do we also

[2:07] some specific details of where the

[2:09] project is at this point. So, if we

[2:11] start at the Vernon interlocking

[2:13] intersection, uh that is and continues

[2:16] to be free flowing. There's no signal

[2:18] there today. Uh Gus Young is still

[2:21] closed by Dina Liquor Store. Most of the

[2:24] work is complete or will be complete

[2:26] this week, next week. Then they'll be

[2:28] shifting traffic back to the west

[2:32] here, the corner, kind of what I have

[2:33] drawn here. and they'll continue to be

[2:36] free flowing there as long as they need

[2:38] it to complete the rest of the work to

[2:41] the east of this intersection.

[2:44] So, look for some slight changes there

[2:46] as they wrap up this work in the next

[2:47] week or so.

[2:50] Uh the power line, we've talked about

[2:52] this for at least 6 weeks, I believe.

[2:55] So, the Excel power line is horizontally

[2:57] and vertically different in the field

[2:59] than what we thought. Uh it was shown on

[3:02] the plans. It was struck and repaired.

[3:05] There's no agreements. Uh both parties

[3:07] are working on permits and agreements.

[3:09] There has been no

[3:12] construction movement on this. So what

[3:14] you see in the picture is still today.

[3:16] Uh that concrete is from the old bridge.

[3:20] Uh I'm having major concerns, major

[3:23] impacts to schedule and cost are coming

[3:25] and we don't even know what that is yet

[3:27] until we can actually get Excel and CP

[3:29] to get a permit to move this stuff

[3:32] around. So,

[3:34] uh, I'm very concerned on how this is

[3:37] going to impact the entire project cuz

[3:39] this has been 3 months and it's still

[3:41] sitting in the same spot.

[3:44] Um, and neither agency was willing to do

[3:46] any kind of temporary moves and stuff

[3:47] like that. So, more to come on this when

[3:50] we actually know

[3:52] when the permits will be done, when the

[3:54] contractor could potentially assist with

[3:56] some of the work. Once we know that,

[4:00] then we can actually put together some

[4:02] contractor could put together some

[4:03] schedules and some potential cost

[4:07] implications to the project.

[4:11] Uh last week on Monday, July 28th, the

[4:14] northbound on-ramp from 50th Street was

[4:17] closed. It's closed until the fall so

[4:20] they can build the ramp, realignment of

[4:22] the ramps and the noise wall from

[4:24] Minihana Creek up to 50th. And again,

[4:26] there's GIS mapping. There's a link

[4:28] there that shows the different mapping

[4:31] for the detours. One is along Highway

[4:34] 100. You would exit on eastbound 62 and

[4:37] then stay and exit right away again to

[4:40] northbound 100. The other detour is the

[4:42] local frontage roads on each side of 100

[4:44] down to Benton Heaven.

[4:48] So, we know Benton Avenue shown here is

[4:51] experiencing more traffic. There's more

[4:53] delays at that location. We have been

[4:56] working with MDOT. They did ret time the

[4:58] on-ramp signals for that northbound

[5:00] exit. We'll continue to look at that,

[5:03] work with MDOT, but just know that

[5:06] Benton Avenue is has had a big increase

[5:09] in traffic and it's going to get worse.

[5:12] School starts August 25th. So, we got

[5:15] the Dina schools right at this location

[5:16] and we have OG on Eden and Arcadia area.

[5:20] So, in a couple weeks, we're going to

[5:22] have all the school traffic back at both

[5:24] these locations.

[5:27] What's coming up? Uh, at some point, we

[5:29] need to do the stage 3A part two, which

[5:32] is the westbound ramps or the southbound

[5:36] off-ramps.

[5:37] Sometime in September. We don't have a

[5:39] hard date yet. Um, sometimes in

[5:42] September, that is going to close. And

[5:44] then we also need to do stage 3B, which

[5:47] is the northbound

[5:51] exit to Graange. They have to build that

[5:54] ramp there, too. So, that one will need

[5:56] to change. So, we have two ramp closures

[5:59] still to conduct sometime in September

[6:03] when we know those dates. We'll be

[6:04] sharing those out. Um, so Benton Avenue

[6:07] will get worse with those closures also.

[6:09] So, it is going to get

[6:12] worse before it gets better from a

[6:14] traffic standpoint within this area.

[6:17] Uh some cool things, the bridge is going

[6:19] to start to really take shape for the

[6:21] first week of September. If everything

[6:23] goes according to schedule, the gerters

[6:25] are going to show up overnights.

[6:27] Uh two nights for northbound, two nights

[6:30] for southbound, placing those girders uh

[6:33] over the highway. So that's really going

[6:35] to start to take shape that Highway 100

[6:36] bridge is moving forward very nicely.

[6:42] Another thing that's going to start to

[6:43] impact stuff is the 5100 Even Eden

[6:46] Avenue. It was a development project

[6:48] approved by the city council. They are

[6:51] going to start work uh some temporary

[6:53] work starting August 18th. So, as shown

[6:56] in this graphic, uh they're going to

[6:58] build a temporary sidewalk along the

[7:01] west side of Arcadia Avenue from just

[7:04] north of the roundabout at Arcadia and

[7:06] Eden up to the crosswalk

[7:09] near the Vernon shops. During this work,

[7:12] the parking will be removed along the

[7:14] west side and they'll have flaggers out

[7:16] there. Once that work is complete, the

[7:18] parking will be reestablished. Also

[7:21] during that week, they'll install jersey

[7:22] barriers and fencing around their

[7:25] property uh as they get ready to start

[7:28] doing demo and grading operations for

[7:30] their project. Then that blue dash line

[7:33] is the sidewalk detour. So, there'll be

[7:35] signs placed uh over at the roundabout

[7:38] at Graange to use that crosswalk and use

[7:42] the south sidewalk along Eden Avenue

[7:46] around the Eden Arcadia roundabout and

[7:48] then use this new west temporary

[7:51] sidewalk up the west side of Arcadia

[7:54] where there is no sidewalk today. So,

[7:56] they're building that. They need to

[7:58] close the sidewalk adjacent to that

[8:00] parcel on both Eden and Arcadia so they

[8:03] can safely work on that parcel.

[8:08] And then some pictures. Uh we always go

[8:10] through some pictures and provide some

[8:11] updates. Uh this picture is again

[8:13] looking at the Vonnies on the right hand

[8:16] side from various weeks of construction.

[8:18] And the one on the right is what it

[8:19] looks like today. So that bridge

[8:23] foundation and bridge support is is

[8:25] coming along very very nicely there on

[8:28] the east side of the CPKC rail with the

[8:31] B bridge.

[8:34] Uh this is the intersection. The one on

[8:35] the left was from two weeks ago where

[8:37] they were still doing utility work.

[8:39] Photo on the right is what it looks like

[8:41] today. So they have curb and gutter in.

[8:43] They're pouring sidewalks. You can see

[8:45] the signal base is in and then they'll

[8:47] be paving next week and then shifting

[8:50] this traffic back over to that side in

[8:53] that intersection like I discussed

[8:55] earlier.

[8:58] Uh the area in front of the Dino liquor

[9:01] store is complete. So this is a picture

[9:02] of that and we got the bike racks

[9:04] installed uh in this photo on the left.

[9:08] Then on the right is a photo looking

[9:10] west. That's Washurn McCree funeral

[9:14] chapel in the background. And this is

[9:16] the east side of the high 100 bridge. So

[9:19] just seeing some of the work taking

[9:21] shape there on the east side of Highway

[9:23] 100.

[9:26] This is near Hawthorne Court, Hawthorne

[9:28] Apartments. The one on the left was a

[9:30] photo from a couple weeks ago. And the

[9:31] one on the right is from this morning as

[9:33] they continue to pour that retaining

[9:36] wall before the noise wall gets

[9:38] installed on top of that retaining wall.

[9:44] This is looking east towards city hall.

[9:48] You can see the green traffic signals in

[9:50] the background. Photo on the upper left

[9:52] was from four weeks ago. Bottom left was

[9:56] from two weeks ago. And the bigger photo

[9:59] on the right is from this morning

[10:01] showing all the bridge supports

[10:03] foundation work that's happened as they

[10:05] get ready for those gvers here in a few

[10:07] weeks of that first early September.

[10:12] Then a couple zoomed in more give you

[10:15] some scale of the bridge and the work

[10:17] these guys are doing. So both left and

[10:20] right are both on the Highway 100

[10:22] bridge. I think they're both on the west

[10:24] side of Highway 100, but just giving you

[10:26] an idea of the work they're doing, the

[10:29] scale there.

[10:32] And the again are renderings of the

[10:33] finished bridge at 100. Left photo is

[10:37] showing those wide sidewalks, new

[10:39] traffic signals, and new turn lanes. One

[10:43] on the right is the rendering of the

[10:46] bridge from Highway 100 heading

[10:47] northbound. And you're seeing all those

[10:49] supports are nearly complete. And those

[10:52] girders will be coming in just a few

[10:54] weeks as this thing really starts to

[10:55] take shape. Uh so we do this meeting in

[10:58] two every two weeks. In two weeks Derek

[11:01] Houston, our rep with TKDA is going to

[11:04] be hosting this meeting and sharing

[11:05] additional information as I will be out

[11:07] at the office. So for Derek to host the

[11:11] next meeting here in two weeks.

[11:14] So I'll stop sharing and see there's any

[11:17] questions

[11:19] in the chat. Any

[11:26] questions

[11:31] for people to type in questions?

[11:34] Diana staff

[11:36] unmute and ask questions if you have it.

[11:40] Uh, question one, will there be new

[11:42] trees planted and if so, where and what

[11:44] kind? Um, most likely not. We took a few

[11:49] trees down that were volunteer trees.

[11:54] Most of the bridges are wider than they

[11:56] were before. So, we needed that space

[11:58] for either the bridge structures or the

[12:00] sidewalks. There was really not a lot of

[12:03] space left for trees. Other than some

[12:07] promises we made to Hawthorne apartments

[12:10] there on their on their property behind

[12:13] the new noise. So, in that area, there

[12:15] will be some trees. We look if there's

[12:18] other space, but right now it doesn't

[12:19] look like there'll be too many new trees

[12:20] just because we needed the space for

[12:22] these new facilities.

[12:26] Will mulch borders be replaced by my

[12:29] road sign?

[12:31] Uh, and Ryan, the holiday manager,

[12:35] we can meet with you and talk through

[12:38] restoration of your property as part of

[12:40] this project. So, uh, typically we want

[12:42] to put stuff back the way it was before

[12:44] we got there. So we can definitely work

[12:46] with you. We'll have Derek reach out. We

[12:49] can have a conversation.

[12:53] Brian had a question. Any more

[12:54] commentary to offer about why Rail and

[12:56] Excel don't seem to care about time,

[12:57] cost, or inconvenience?

[13:00] I have a lot of commentary, but I don't

[13:02] think it's appropriate for this meeting

[13:06] on on the lack of urgency by both

[13:08] parties. The why a great question. I

[13:10] have no idea why. We've communicated

[13:13] with them multiple times for three

[13:16] months every week. What are we doing?

[13:18] This is the major issue. Um, stuff like

[13:22] that. Uh, Mr. Crabtree, doesn't the 1968

[13:26] agreement cover? It covers an aerial

[13:28] line, not a buried line is what we got

[13:30] confirmation from those parties. So,

[13:33] buried line got hit. It technically

[13:36] wasn't covered in any agreements between

[13:38] the parties. And again, that's between

[13:40] them.

[13:43] I have a question regarding the east

[13:44] side of the new Vernon Avenue bridge

[13:47] adjacent to Devanis.

[13:50] Will there be an open gap between the

[13:52] new bridge structure and the Devan's

[13:54] building or will that space be filled

[13:56] with new concrete and other landscaping?

[13:59] Uh very detailed question Darren. I

[14:02] think we would check in with you offline

[14:05] and we can show you some plans and the

[14:07] verific

[14:13] have a conversation and help answer that

[14:15] question.

[14:17] Uh Mr. crab tree again and who's

[14:19] responsible for any cost over on the

[14:21] city, the county, the mindot. Great

[14:24] question. We don't know yet. I would add

[14:27] additional parties to that list. Excel

[14:28] and rail, but how would what's our

[14:31] ability to get those from them? That's a

[14:34] good question. So, there's cooperative

[14:36] agreements that lay out cost

[14:38] responsibilities for the Hannipan County

[14:40] Bridge, the Highway and Hinder Bridge,

[14:42] and everything in between. And so

[14:44] typically if items overrun those cost

[14:46] share agreements, operative agreements

[14:49] would dictate where those additional

[14:51] costs go. Feel like this bridge side is

[14:54] a different conversation that uh

[14:58] potentially attorneys would get involved

[15:00] in that discussion.

[15:02] I live near Hawthorne Court near the

[15:05] Atra crossing going through West 49th

[15:08] Street. It appears the recent concrete

[15:10] patching down on the street top of the

[15:12] tracks were too high. Seems like every

[15:14] time the train cut these massive scrapes

[15:16] against the grout.

[15:19] Uh we could take a look at what you're

[15:21] talking about. So it sounds like the

[15:22] crossing at 49th Street, the Buminous

[15:24] was recently repaired.

[15:26] Um we can take a look.

[15:30] Will there be any tree clearing done

[15:32] around 5100 building and the bridge that

[15:36] connects to the other side?

[15:40] Good question.

[15:42] The map here and look at that site.

[15:45] Nothing is being done to the Eden Avenue

[15:47] bridge.

[15:51] I don't think they have any trees on

[15:53] their site. There's a few trees and

[15:56] landscaping above that big retaining

[15:58] wall. There's a few trees along Eden by

[16:04] their east driveway.

[16:07] those would get removed but then the

[16:09] other trees are mostly in mind rightway.

[16:11] So that's a question for

[16:14] the developer and whether they worked

[16:16] out any agreements with Mindot and those

[16:18] trees that are outside their property

[16:20] line in the Mindot right away on the

[16:22] east or the north side of this port.

[16:29] At a previous update you mentioned that

[16:32] CPKC was paid to expedite a decision on

[16:35] the line. Who paid to expedite the

[16:37] decision and how was it paid?

[16:40] Uh it's a project expense. So it's split

[16:43] between all the parties

[16:45] and paid as such.

[16:55] Great questions.

[16:57] Great questions.

[17:01] What will replace the 5100 Eden

[17:04] building? Uh it's going to be a

[17:07] corporate headquarters, so commercial

[17:10] building

[17:12] uh for Opus, the Opus Development

[17:15] Company, and then have a little retail

[17:20] space on the first floor.

[17:22] Those can be found, those were in

[17:24] council packets earlier this year if

[17:26] you're interested in seeing all those

[17:28] renderings

[17:29] of the project that was approved by the

[17:31] city council.

[17:39] questions.

[17:41] Uh, I didn't answer. So, Justin, on that

[17:45] decision to expedite, that was a $2,000

[17:49] fee if you want to know. We felt like

[17:51] that was justified for a $20 million

[17:54] project to try to keep it on schedule as

[17:57] best we could because we felt like that

[17:58] could be the hangup of this. my opinion

[18:02] it's been more Excel has been the hang

[18:04] up on this matter.

[18:14] Um and Bill just put a link in from

[18:16] better together.org the Opus 5100 Eden

[18:19] development. So there's a link if you're

[18:22] interested in looking at that

[18:24] development project. Thanks, Bill, doing

[18:26] that.

[18:31] Other questions? So, I think there's a

[18:34] lot of unknowns, unknown schedule on the

[18:36] ramp closures coming up, unknowns on

[18:40] when two parties are going to figure out

[18:43] the power line.

[18:46] So then that creates an unknown on just

[18:48] the overall project schedule and

[18:50] potential costs.

[18:52] When we know more, we'll be sharing more

[18:55] specifics out on these meetings, on the

[18:57] website, and all those other

[18:59] communication channels that we discussed

[19:01] earlier.

[19:08] Uh Darren, where can I reach out to you

[19:10] about a question space? Uh go to the

[19:12] better together.org

[19:14] website, find the project page, and

[19:16] Derek and I's phone number and emails

[19:18] are on there. So then you can just ping

[19:22] us that way, share your info and we can

[19:24] reach out and meet you probably the best

[19:26] is meet you out at Devanis and review

[19:29] the area you're concerned about.

[19:31] Derrick's out there every day for the

[19:33] most part and can meet with you to have

[19:35] those discussions.

[19:39] Check out the website for emails and

[19:41] phone numbers.

[19:48] Anything else?

[19:52] Great questions.

[20:00] We will post the slides. We'll post this

[20:04] recording to the website

[20:07] as soon as we can. So, if you know of

[20:08] others that want to see or hear this

[20:10] information, send them there. If you got

[20:12] specific questions, just reach out to me

[20:14] or Derek. Be appreciated. For a

[20:17] reminder, in two weeks, Derek will be

[20:18] presenting information on where we're

[20:20] at. So,

[20:22] thanks everybody. Appreciate your time

[20:25] and interest.

Was this story helpful?

Other Topics from This Document

  • Vernon Avenue Highway 100 interchange project status

  • Construction impacts (noise, dust, vibration)

  • Traffic management and detours

  • Pedestrian and school zone safety

  • Utility conflict resolution (Excel power line)

  • 5100 Eden Avenue development project

  • Project schedule and future ramp closures

  • Bridge construction progress

Want to know when new stories arrive?

Enter your email to receive updates.

We will not use your email for any other purpose. You can unsubscribe at any time.