Highway 100 Bridge Deck Completed in Overnight Pour
Construction crews completed pouring the entire Highway 100 bridge deck during an overnight operation last week as part of the ongoing Verdon Avenue and Highway 100 interchange project in Edina.
The concrete pour took place over seven hours from 9 p.m. to 4 a.m., with approximately 15 trucks per hour delivering concrete to the site. Contractors will begin pouring the concrete median, curb and gutter, and sidewalks on the Highway 100 bridge next week, according to the project's 14th bi-weekly update meeting held October 2.
Ames Construction will begin removing the existing west abutment next week after receiving approval for permits and agreements between the railroad and Excel Energy. The utility company has deenergized power lines in the work area to allow construction to proceed. Excel Energy will install new steel conduit and casing before running a new power line through the area.
Project officials requested schedule and cost options from the contractor to potentially open the Vernon Avenue bridge before the end of the year. If early opening proves unfeasible, alternatives include reopening Gus Young Lane while the bridge remains closed during winter construction. The contractor is expected to provide these options by the end of this week.
The eastbound Highway 100 on and off ramps remain closed and are scheduled to reopen in mid-November. Hennepin County and the city will coordinate approval processes for any schedule or cost changes, with the county handling most funding decisions for the Vernon Avenue bridge portion of the project.
Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.
Go deeper on this topic
Research related meeting documents and build a brief — without rewriting the story.
Full analysis
Areas of Interest (4)
- City and Hennepin County evaluating potential cost and schedule options to accelerate the completion of the Vernon Avenue bridge.
- Ongoing challenges with construction-related noise, dust, and vibrations affecting local residents and businesses.
- Complex inter-agency coordination required between the city, Hennepin County, Excel Energy, and CP KC rail for infrastructure work.
- Persistent closure of Gus Young Lane to facilitate contractor equipment and crane staging.
Notable Quotes (1)
We did ask the contractor to create multiple schedules and cost options. We asked if there was any way possible to open this bridge this year, the Vernon Avenue bridge.
People (1)
Unidentified SpeakerProject RepresentativeConducting meeting 14 regarding the project update and construction status.
Conducting meeting 14 regarding the project update and construction status.
Places Mentioned
Events & Meetings (1)
- October 2, 2025: Meeting number 14 for the Vernon Avenue and Highway 100 interchange project
Source document
Was this story helpful?
Other Topics from This Document
Vernon Avenue and Highway 100 interchange project progress
Construction schedule updates and bridge work
Support programs for local businesses in the Grand View District
Traffic safety, pedestrian crosswalks, and detours
Noise wall installation and bridge abutment work
Coordination with Excel Energy and CP KC rail
Want to know when new stories arrive?
Enter your email to receive updates.
We will not use your email for any other purpose. You can unsubscribe at any time.