StoryPanoway Project Budget and Change Order AuthorizationJune 26, 2026

Wayzata Council Authorizes Panoway Project Change Orders Amid Procedural Debate

City officials approved adjustments to the multi-phase waterfront project, citing unforeseen circumstances and long-term cost efficiencies, following debate over retrospective authorization.

Published Jul 1, 2026

The Wayzata City Council moved to authorize several change orders for the ongoing Panoway Project during its Nov. 12 meeting, approving modifications to the extensive waterfront development despite some council members raising concerns about the timing of the requests, which largely covered work already completed. The changes, presented as necessary adjustments to unforeseen site conditions and future operational efficiencies, ultimately received council authorization.

The discussion centered on the fact that many of the changes had already been implemented before coming to the council for official authorization. This retrospective approval process prompted questions from city leadership.

These are all items that have already been done, so why do you need our approval now? Shouldn't you have gotten, shouldn't we have provided our approval before the work was done?

— Mayor Muton

City Manager Doll clarified that the nature of the construction often necessitated immediate action to address unexpected issues on site, leaving little choice but to proceed with the work.

There were issues that came up that needed to be done; we thought there wasn't a choice.

— City Manager Doll

Bob Jansen, involved with the project, further elaborated on specific modifications, particularly those related to the seasonal maintenance of certain project components. He explained that these adjustments were designed to streamline annual processes and reduce recurring expenses significantly.

The step downs, especially the lower platform and the bridge aspect of them, have to be removed and reinstalled every year... modifications that are being made are to make it more efficient and ultimately save pretty substantially on costs on an annual basis.

— Bob Jansen

While acknowledging the practical necessity of authorizing the payments for work already completed, at least one council member underscored the importance of clearer communication and pre-emptive authorization for future project phases to ensure greater transparency.

At this point, I don't think we have a choice; I think we have to pay for this. But I think my biggest request is some transparency and clarity.

— Council Member Park Hill

Despite the procedural concerns raised during the discussion, the council ultimately authorized the execution of the change orders, moving forward with the project's ongoing development. The decision allows the city to account for the work completed and to realize the promised efficiencies in subsequent years, while also signaling a call for improved communication channels regarding project adjustments in the future.

Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.

Go deeper on this topic

Research related meeting documents and build a brief — without rewriting the story.

Full analysis

Votes (2)

Consider Authorization of the Execution of Panoway Change Orders

3-1 Approved

Dissent: Mayor Muton voted 'Nay', stating that the budget relies on money not yet in hand, leading to an effective over-budget scenario when that factor is considered.

Moved by Council Member McDonald [1:48:50] · Seconded by Council Member Sorenson [1:48:53]

The discussion centered on approving change orders totaling $165,830.98 for the Panoway Project. Council members expressed strong concerns about approving work that had already been completed and the project's depleted contingency fund. Specific issues included unexpected pile obstructions, ice breaking costs due to project delays, use of a hydro crane, acceleration costs, and the need for rail stiffeners due to design limitations. Staff explained that some changes were necessary for project progression and long-term operational efficiency, with further discussion on step-down design changes deferred to a future meeting.

Consider Adoption of Resolution 46-224 Canvasing the Returns and Declaring the Results of the November 5, 2024, City General Election

4-0 Approved

Dissent: None

Moved by Council Member Sorenson [1:59:08] · Seconded by Council Member McDonald [1:59:11]

The City Manager presented the certified election results, confirming Andrew Mullen as Mayor-elect and Alex Pish and Ken Sorenson as re-elected Council Members. The presentation also included Wayzata's federal and state election results, highlighting the city's consistently high voter turnout. The Mayor congratulated all candidates, emphasizing the importance and challenge of public service. Acknowledgment was also given to election staff and judges for their efficient and courteous management of the election.

Notable Quotes (6)

These are all items that have already been done so why do you need our approval now shouldn't you have gotten shouldn't we have provided our approval before the work was done?

— Mayor Muton [1:14:21]
Consider Authorization of the Execution of Panoway Change Orders

and there were issues that came up that needed to be done we thought uh there wasn't a choice.

— City Manager Doll [1:15:01]
Consider Authorization of the Execution of Panoway Change Orders

the step Downs especially the lower platform and the bridge aspect of them have to be removed and reinstalled every year... modifications that are being made are to make it more efficient and uh ultimately save pretty pretty substantially on costs on an annual basis.

— Bob Jansen [1:10:00]
Consider Authorization of the Execution of Panoway Change Orders

at this point I don't think we have a choice I think we have to pay for this but I think my biggest request is some transparency and clarity.

— Council Member Park Hill [1:42:45]
Consider Authorization of the Execution of Panoway Change Orders

everybody should do it once in their life it is a hard thing to do to put yourself out there... it is an incredibly humbling experience but one that we all grow from.

— Mayor Muton [1:58:15]
Consider Adoption of Resolution 46-224 Canvasing the Returns and Declaring the Results of the November 5, 2024, City General Election

here in wetta you are treated like you're the person that matters and our staff led by city clerk leig really has a great team they treat people very kindly and I just want to give them a lot of acknowledgement and recognition because it's one thing to to work your tail off and you know be exhausted after a long season it's another thing to do it with such Grace and kindness and really customer service driven.

— City Manager Doll [2:00:56]
Consider Adoption of Resolution 46-224 Canvasing the Returns and Declaring the Results of the November 5, 2024, City General Election

Ordinances & Resolutions (9)

Minnesota Statute section 13d.05 subdivision 3AOther

Provides an exception to the open meeting law for performance evaluations of individuals subject to council authority.

Ordinance 843Ordinance

Special events ordinance, approved on second reading and adoption.

Resolution 47-224Resolution

Approving Grant agreements for intensive comprehensive peace officer Education and Training.

Resolution 46-224Resolution

Canvasing the returns and declaring the results of the November 5, 2024, City general election.

Memorandum of UnderstandingOther

Agreement between the City and the Wayzata Conservancy regarding maintenance, operations, and dock funding for the Panoway Project.

Professional Services AgreementOther

Agreement for 2025 Recreation services with Wayzata Community Education.

Lease AgreementOther

Amendment to lease agreement with Hennepin County for the Wayzata library.

Transmission Line EasementOther

Northern State's power company Excel Energy amended and restated easement.

Statement of WorkOther

For Police Department IT services and IT services for administration, Public Works, and Municipal liquor operations by Laugher.

Source document

Was this story helpful?

Other Topics from This Document

  • City Manager Performance Evaluation

  • Police Chief Mark Schultz Retirement Recognition

  • Wayzata Conservancy Panoway Project Fundraising Update

  • Canvass of November 5, 2024, City General Election Results

Want to know when new stories arrive?

Enter your email to receive updates.

We will not use your email for any other purpose. You can unsubscribe at any time.