Mahtomedi Schools Approves $24.7 Million Bid Package Two Amidst Single Bidder Scenario
The unanimous decision locks in a guaranteed maximum price for a significant portion of the district's construction project, despite only one firm submitting a proposal.
Mahtomedi Public Schools' Board of Directors unanimously approved Bid Packet Two, establishing a Guaranteed Maximum Price (GMP) of $24,772,407 for a significant phase of the district's ongoing construction project. The approval, which includes comprehensive costs from contingencies to staffing, was made despite only one of five pre-qualified firms submitting a bid for the package.
The approved sum covers the full scope of construction costs outlined in Bid Packet Two. "That total value for the construction costs is the 24 million 772,407 dollars," stated AJ, a project representative. He elaborated, "And that is inclusive of all contingencies, permitting, insurances, bonding, um subcontractor default insurance, staffing and operations, as well as general conditions."
The board's decision followed a discussion regarding the unexpected lack of competitive bids for this particular package. While five firms initially pre-qualified for the work, only one ultimately submitted a proposal. AJ addressed this situation, noting the expectation for pre-qualified bidders to participate. "As far as addressing the the one out of the five that we had had prequalified so um we had expected um out of the five that prequalified if they'd have taken the time to prequalify we would have expected them to bid on that bid day," he explained, adding that "sometimes businesses make decisions in the moment behind their doors on whether or not they're providing a bid for the project."
The overall project budget also incorporates two distinct layers of contingency funds designed to cover unforeseen circumstances or necessary adjustments during construction. "There are two contingencies. There's ours and that just if if we don't use all of that um we we're able to use it on the project for certain things and that's at the district's discretion," AJ explained. He further detailed a larger contingency: "And then there's a a larger contingency. It's about a a little over a million dollars...If all of that contingency did not get used, then it comes back as a credit to the district."
Other Topics from This Document
Approval of Guaranteed Maximum Price (GMP) for Bid Packet One